Data Center Tracking Index

What is new in data center construction across the US and Canada, and what it means for the power grid, natural gas supply and the communities that host it. Updated every day from the Data Center Index.

Updated November 18, 2026. Figures as of November 3, 2026.

Campuses tracked87100 MW or more, US and Canada
Announced205 GWAt full buildout
Expected by 203055 GWWeighted by build stage
Added gas burn5.1 Bcf/dAverage day, grid and on-site

This week

  1. · Policy · Virginia

    Loudoun County, Virginia supervisors approve a 12-month pause on data center applications

    Loudoun County's Board of Supervisors voted 7-1-1 on Nov 17, 2026 to stop acting on legislative data center and substation applications (rezonings and special exceptions) for 12 months, counted from Sept 15, while it finishes Phase Two of its data center zoning standards, Loudoun Now reports. Staff will keep accepting applications into a backlog; substations needed for grid reliability and some special districts are excepted. The county attorney said the board cannot impose a moratorium on a single use and warned of "a real threat of litigation."

    Sources: Loudoun Now · Data Center Index

  2. · Build · Georgia

    Effingham County, Georgia approves OpenAI Project Camellia site plan; moratorium tabled to January

    Effingham County commissioners unanimously approved the site plan for OpenAI's Project Camellia on Nov 17, 2026: six data center buildings, two substations and cooling infrastructure on about 1,400 acres of the Savannah Gateway Industrial Hub, the Effingham Herald reports. The plan does not allow construction yet; OpenAI still needs other county approvals and a federal Section 404 permit to fill about 72 acres of wetlands (comments open to Dec 3). Commissioners tabled a data center moratorium, which would not cover Camellia, to January (4-1) and held a first reading of rules making data centers a conditional use.

    Sources: Effingham Herald · Data Center Index

  3. · Grid · North Carolina

    North Carolina regulators approve Duke rate increases and a new rate schedule for 50 MW+ data centers

    The North Carolina Utilities Commission approved Duke Energy Carolinas' and Duke Energy Progress' rate settlements on Nov 16, 2026, and set a separate rate schedule for data center customers above 50 MW, Duke said on Nov 17. Duke says the orders add upfront payments for dedicated facilities, transmission upgrade financial requirements and security against stranded generation costs, and that it is still assessing the data center portion. WRAL reports the schedule requires contracts of at least 10 years (15 years at 100 MW or more) and demand charges on at least 75% of contracted demand, and that data centers make up 92% of the 6.7 GW of new large-load demand Duke signed in the Carolinas between March 2024 and April 2026.

    Sources: Duke Energy · WRAL · Data Center Index

  4. · Grid

    MISO, CAISO, NYISO and ISO-NE file large-load interconnection reforms at FERC; SPP due Nov 20

    Responding to FERC's June 18 show-cause orders, MISO, CAISO and NYISO filed large-load reforms on Nov 16, 2026 and ISO-NE on Nov 13, alongside PJM, Utility Dive reports. MISO proposes a Large Load Project Review process, new transmission services (including a service for loads that cut use under price or reliability conditions) and standard cost recovery agreements; CAISO proposes standardized connection paths and service for flexible large loads; NYISO proposes firm and non-firm withdrawal services; ISO-NE would publish each large load's network upgrades with cost estimates and require large loads to bring new capacity. SPP's filing was due by Nov 20.

    Sources: Utility Dive · Data Center Index

  5. · Grid

    PJM files to halve large-load study time to one year and sets ride-through rules for data centers

    PJM filed its "Fast Energization" proposal with FERC on Nov 16, 2026. PJM says it would cut projected study time for new generation and for large-load transmission service from about two years to one by studying them together, create new transmission services for large loads that bring their own generation or can reduce demand (plus an interim service while upgrades are built), and give states access to data-center-driven transmission costs so they can decide whether to bill large loads for them. PJM asked for a 60-day comment period and a FERC order within 120 days. In a separate filing the same day, PJM proposed voltage and frequency ride-through rules for computational loads above 50 MW, effective Jan 16, 2027, after nearly 3.9 GW of data centers switched to on-site generators during a Jul 22 transmission disturbance.

    Sources: PJM Inside Lines · PJM Inside Lines · Data Center Index

  6. · Build · Texas

    Core Scientific registers $1.3B first building at 285 MW Hunt County, Texas campus (watch list)

    A Core Scientific subsidiary, Telios Quinlan One LLC, registered a $1.3 billion, 341,326 sq ft data center building ("Core Scientific - Hunt") at 4852 CR 3507, Quinlan, Hunt County, Texas with the Texas Department of Licensing and Regulation on Nov 13, 2026, with construction listed from Nov 24, 2026 to Sep 4, 2028. Baxtel and Data Center Dynamics report the campus is planned for up to 285 MW of leasable capacity on about 430 MW of gross utility power, with power ramping from 2027 to 2029, and that AMD has leased 110 MW there. The index has no campus record for this site yet, so it is on the watch list.

    Sources: Texas Department of Licensing and Regulation · Baxtel · Data Center Index

  7. · Build · Illinois

    Rockford, Illinois names Microsoft as company evaluating Monarch's data center site (watch list)

    The City of Rockford announced on Nov 13, 2026 that Microsoft is the company evaluating the Monarch-controlled property in south Rockford for a possible data center; Microsoft is still in due diligence and has submitted no site plans. Baxtel reports the site could host a phased campus of up to 1.4 GW and that ComEd cancelled its transmission security agreement with the landowner, Monarch Rock Air, in July 2026, moving the project into a later ComEd study. No MW figure has come from Microsoft or the city, so the site is on the watch list.

    Sources: City of Rockford · Baxtel · Data Center Index

  8. · Gas · Louisiana

    Venture Global seeks Louisiana air permit for gas generators at a Cameron Parish data center site

    KPLC reports that Cameron Generation LLC, a Venture Global company, applied to the Louisiana Department of Environmental Quality (received Oct 15) for an air permit for natural gas generators at "Cameron Campus Data Center No. 2" near the Calcasieu Ship Channel. In its Nov 10 third-quarter release, Venture Global said it plans to offer off-grid, island-mode gas power for data centers at its Cameron and Plaquemines Parish sites, starting in late 2028 and scaling to about 5 GW by the end of 2031, and that it has frame agreements with GE Vernova and Baker Hughes for up to 16 power islands of 720 MW each. The CEO said no data center customer has signed yet, and nothing has gone before the Cameron Parish Police Jury.

    Sources: KPLC · Venture Global (SEC) · Data Center Index

  9. · Build · Indiana

    AWS breaks ground on $7B Project Rise campus in Wheatfield, Indiana (watch list)

    Amazon Web Services held a ceremonial groundbreaking on Nov 12 for its $7 billion Project Rise data center campus on 304 acres of former NIPSCO land in Wheatfield, Jasper County, Indiana, next to NIPSCO's Schahfer Generating Station; Inside Indiana Business reports more than 350 workers already on site. Jasper County commissioners approved the development agreements and rezoning on Jun 17, 2026, when 250 permanent jobs were cited. Amazon has not stated the campus MW, so it stays on the watch list; it is a separate site from the AWS Hobart campus (DC-037).

    Sources: Inside Indiana Business · Northwest Indiana Business Magazine · Data Center Index

  10. · Build · Pennsylvania

    Bethlehem, Pennsylvania planners approve 120 MW data center plan 5-0 despite opposition

    Bethlehem's Planning Commission voted 5-0 on Nov 12 to approve, with conditions, plans by Boyle Construction and Tensor IQ for a two-story, 131,380 sq ft data center at 2184 Industrial Drive beside Route 22 that would draw about 120 MW, Lehigh Daily reports. The plan was filed before city council banned data centers in that district in October, so the new rules do not apply. About 30 residents spoke against it and none in favor; building permits wait on state sewer and stormwater approvals.

    Sources: Lehigh Daily · Data Center Index

  11. · Policy · Minnesota

    Minneapolis council passes 7-6 data center limits; mayor's veto possible before Nov 21 expiry

    The Minneapolis City Council voted 7-6 on Nov 12 to limit new data centers to existing buildings in two downtown zoning districts and to require a council vote on each one, MPR News reports. KSTP reports a size cap of 50,000 sq ft, or 150,000 sq ft for facilities using renewable energy. Mayor Jacob Frey reportedly opposes case-by-case council votes and could veto; an override needs nine votes, and the council plans to meet Nov 20, the day before the city's moratorium expires.

    Sources: MPR News · KSTP · Data Center Index

  12. · Grid

    PJM market monitor: data center load has added $29.4B to capacity costs, urges auction delay

    PJM's independent market monitor, Monitoring Analytics, said in its Jan–Sept 2026 State of the Market report (posted Nov 12) that including data center load in the capacity market has raised capacity costs for all customers by $29.4 billion to date. It found the total wholesale cost of power averaged $111.61/MWh in the first nine months of 2026, $9.95/MWh (9.8%) more than it would have been without data center load's effect on capacity prices, and warned that the December 2026 auction for 2029/2030 will likely clear at the maximum price and add another $5 to $10 billion. The monitor recommends postponing that auction until forecast data center load can be removed and served through bilateral contracts or a backstop procurement; PJM told the Pennsylvania Capital-Star that state regulators, not PJM, decide how those costs are shared.

    Sources: Monitoring Analytics (PJM Independent Market Monitor) · Pennsylvania Capital-Star (via WITF) · Data Center Index

  13. · Build · Utah

    Carbon County, Utah approves permit for Valar Atomics' nuclear-and-gas data center campus

    The Carbon County Planning Commission approved a conditional use permit on Nov 12, with one vote against, for Valar Atomics' Raceway Energy Campus on 640 acres of Utah trust land, The Salt Lake Tribune reports. The company describes the campus as about 3 GW, with a natural gas plant powering the data centers first and 40 to 120 small reactors later; data center MW is not stated. Conditions include an emergency response plan, workforce housing, noise, water and waste plans, a goal of zero local water use, and road upgrades; the project still needs a county building permit, a Utah air quality permit and an NRC construction permit. Watch list.

    Sources: The Salt Lake Tribune · Data Center Index

  14. · Build · Texas

    Fermi ends TensorWave lease, signs non-binding 600 MW letter of intent with a hyperscaler

    Fermi said in its Q3 2026 results on Nov 12 that it and TensorWave terminated their August 2026 lease at Project Matador near Amarillo, Texas; its 10-Q says the lease ended on Nov 10 after the Oct 31 closing date passed. Fermi also reported a non-binding letter of intent with an unnamed investment-grade hyperscaler for about 600 MW of powered land, backed by a $200 million prepayment agreement and a $15 million early construction agreement, with a definitive lease still to be negotiated. Fermi says the site could ramp to about 17 GW, subject to binding customer agreements and permits.

    Sources: Fermi Inc. / SEC · Fermi Inc. / SEC · Data Center Index

  15. · Grid · Texas

    ERCOT CEO will ask Texas lawmakers to let it curtail data centers before a grid emergency

    ERCOT CEO Pablo Vegas said at the BloombergNEF Summit in Houston on Nov 11 that he will seek legislative authority to require data centers to cut power use at energy emergency level one or earlier, Bloomberg reported. Today large loads can be asked to cut demand only once the grid reaches level two of a three-level emergency; SB 6 (2025) already lets ERCOT order large non-critical loads to curtail with 24 hours' notice, but ERCOT has not used it. Vegas said data centers have access to low single-digit gigawatts of flexibility for the coming winter; the change needs the 2027 Legislature.

    Sources: Bloomberg (via Insurance Journal) · TexasPowerCost · Data Center Index

  16. · Build · Alberta

    Filings show 3.6 GW 'Lynx' data centre and two gas plants planned next to Meta's Alberta campus

    The Logic reports that AESO grid filings describe 'Lynx', a phased data centre of up to 3.6 GW in Sturgeon County, Alberta, with two proposed gas plants called Sturgeon Gas, targeting a June 2031 in-service date. A newly incorporated company whose directors include Pembina executives and a Morgan Stanley Infrastructure Partners investor in Pembina's Greenlight Electricity Centre (which supplies Meta's Sturgeon campus) bought about 134 acres next to Meta's site last month, per Alberta land records. Pembina declined to comment on the land; no customer is named and the gas plants' size is not stated. Watch list: early-stage grid request, single secondary source.

    Sources: The Logic · Data Center Index

Latest updates

The 20 newest entries: new campuses, approvals, utility contracts, grid operator and pipeline actions, and policy changes. Every entry links to its sources. All updates

Show
  1. · Policy · Virginia

    Loudoun County, Virginia supervisors approve a 12-month pause on data center applications

    Loudoun County's Board of Supervisors voted 7-1-1 on Nov 17, 2026 to stop acting on legislative data center and substation applications (rezonings and special exceptions) for 12 months, counted from Sept 15, while it finishes Phase Two of its data center zoning standards, Loudoun Now reports. Staff will keep accepting applications into a backlog; substations needed for grid reliability and some special districts are excepted. The county attorney said the board cannot impose a moratorium on a single use and warned of "a real threat of litigation."

    Sources: Loudoun Now · Data Center Index

  2. · Build · Georgia

    Effingham County, Georgia approves OpenAI Project Camellia site plan; moratorium tabled to January

    Effingham County commissioners unanimously approved the site plan for OpenAI's Project Camellia on Nov 17, 2026: six data center buildings, two substations and cooling infrastructure on about 1,400 acres of the Savannah Gateway Industrial Hub, the Effingham Herald reports. The plan does not allow construction yet; OpenAI still needs other county approvals and a federal Section 404 permit to fill about 72 acres of wetlands (comments open to Dec 3). Commissioners tabled a data center moratorium, which would not cover Camellia, to January (4-1) and held a first reading of rules making data centers a conditional use.

    Sources: Effingham Herald · Data Center Index

  3. · Grid · North Carolina

    North Carolina regulators approve Duke rate increases and a new rate schedule for 50 MW+ data centers

    The North Carolina Utilities Commission approved Duke Energy Carolinas' and Duke Energy Progress' rate settlements on Nov 16, 2026, and set a separate rate schedule for data center customers above 50 MW, Duke said on Nov 17. Duke says the orders add upfront payments for dedicated facilities, transmission upgrade financial requirements and security against stranded generation costs, and that it is still assessing the data center portion. WRAL reports the schedule requires contracts of at least 10 years (15 years at 100 MW or more) and demand charges on at least 75% of contracted demand, and that data centers make up 92% of the 6.7 GW of new large-load demand Duke signed in the Carolinas between March 2024 and April 2026.

    Sources: Duke Energy · WRAL · Data Center Index

  4. · Grid

    MISO, CAISO, NYISO and ISO-NE file large-load interconnection reforms at FERC; SPP due Nov 20

    Responding to FERC's June 18 show-cause orders, MISO, CAISO and NYISO filed large-load reforms on Nov 16, 2026 and ISO-NE on Nov 13, alongside PJM, Utility Dive reports. MISO proposes a Large Load Project Review process, new transmission services (including a service for loads that cut use under price or reliability conditions) and standard cost recovery agreements; CAISO proposes standardized connection paths and service for flexible large loads; NYISO proposes firm and non-firm withdrawal services; ISO-NE would publish each large load's network upgrades with cost estimates and require large loads to bring new capacity. SPP's filing was due by Nov 20.

    Sources: Utility Dive · Data Center Index

  5. · Grid

    PJM files to halve large-load study time to one year and sets ride-through rules for data centers

    PJM filed its "Fast Energization" proposal with FERC on Nov 16, 2026. PJM says it would cut projected study time for new generation and for large-load transmission service from about two years to one by studying them together, create new transmission services for large loads that bring their own generation or can reduce demand (plus an interim service while upgrades are built), and give states access to data-center-driven transmission costs so they can decide whether to bill large loads for them. PJM asked for a 60-day comment period and a FERC order within 120 days. In a separate filing the same day, PJM proposed voltage and frequency ride-through rules for computational loads above 50 MW, effective Jan 16, 2027, after nearly 3.9 GW of data centers switched to on-site generators during a Jul 22 transmission disturbance.

    Sources: PJM Inside Lines · PJM Inside Lines · Data Center Index

  6. · Build · Texas

    Core Scientific registers $1.3B first building at 285 MW Hunt County, Texas campus (watch list)

    A Core Scientific subsidiary, Telios Quinlan One LLC, registered a $1.3 billion, 341,326 sq ft data center building ("Core Scientific - Hunt") at 4852 CR 3507, Quinlan, Hunt County, Texas with the Texas Department of Licensing and Regulation on Nov 13, 2026, with construction listed from Nov 24, 2026 to Sep 4, 2028. Baxtel and Data Center Dynamics report the campus is planned for up to 285 MW of leasable capacity on about 430 MW of gross utility power, with power ramping from 2027 to 2029, and that AMD has leased 110 MW there. The index has no campus record for this site yet, so it is on the watch list.

    Sources: Texas Department of Licensing and Regulation · Baxtel · Data Center Index

  7. · Build · Illinois

    Rockford, Illinois names Microsoft as company evaluating Monarch's data center site (watch list)

    The City of Rockford announced on Nov 13, 2026 that Microsoft is the company evaluating the Monarch-controlled property in south Rockford for a possible data center; Microsoft is still in due diligence and has submitted no site plans. Baxtel reports the site could host a phased campus of up to 1.4 GW and that ComEd cancelled its transmission security agreement with the landowner, Monarch Rock Air, in July 2026, moving the project into a later ComEd study. No MW figure has come from Microsoft or the city, so the site is on the watch list.

    Sources: City of Rockford · Baxtel · Data Center Index

  8. · Gas · Louisiana

    Venture Global seeks Louisiana air permit for gas generators at a Cameron Parish data center site

    KPLC reports that Cameron Generation LLC, a Venture Global company, applied to the Louisiana Department of Environmental Quality (received Oct 15) for an air permit for natural gas generators at "Cameron Campus Data Center No. 2" near the Calcasieu Ship Channel. In its Nov 10 third-quarter release, Venture Global said it plans to offer off-grid, island-mode gas power for data centers at its Cameron and Plaquemines Parish sites, starting in late 2028 and scaling to about 5 GW by the end of 2031, and that it has frame agreements with GE Vernova and Baker Hughes for up to 16 power islands of 720 MW each. The CEO said no data center customer has signed yet, and nothing has gone before the Cameron Parish Police Jury.

    Sources: KPLC · Venture Global (SEC) · Data Center Index

  9. · Build · Indiana

    AWS breaks ground on $7B Project Rise campus in Wheatfield, Indiana (watch list)

    Amazon Web Services held a ceremonial groundbreaking on Nov 12 for its $7 billion Project Rise data center campus on 304 acres of former NIPSCO land in Wheatfield, Jasper County, Indiana, next to NIPSCO's Schahfer Generating Station; Inside Indiana Business reports more than 350 workers already on site. Jasper County commissioners approved the development agreements and rezoning on Jun 17, 2026, when 250 permanent jobs were cited. Amazon has not stated the campus MW, so it stays on the watch list; it is a separate site from the AWS Hobart campus (DC-037).

    Sources: Inside Indiana Business · Northwest Indiana Business Magazine · Data Center Index

  10. · Build · Pennsylvania

    Bethlehem, Pennsylvania planners approve 120 MW data center plan 5-0 despite opposition

    Bethlehem's Planning Commission voted 5-0 on Nov 12 to approve, with conditions, plans by Boyle Construction and Tensor IQ for a two-story, 131,380 sq ft data center at 2184 Industrial Drive beside Route 22 that would draw about 120 MW, Lehigh Daily reports. The plan was filed before city council banned data centers in that district in October, so the new rules do not apply. About 30 residents spoke against it and none in favor; building permits wait on state sewer and stormwater approvals.

    Sources: Lehigh Daily · Data Center Index

  11. · Policy · Minnesota

    Minneapolis council passes 7-6 data center limits; mayor's veto possible before Nov 21 expiry

    The Minneapolis City Council voted 7-6 on Nov 12 to limit new data centers to existing buildings in two downtown zoning districts and to require a council vote on each one, MPR News reports. KSTP reports a size cap of 50,000 sq ft, or 150,000 sq ft for facilities using renewable energy. Mayor Jacob Frey reportedly opposes case-by-case council votes and could veto; an override needs nine votes, and the council plans to meet Nov 20, the day before the city's moratorium expires.

    Sources: MPR News · KSTP · Data Center Index

  12. · Grid

    PJM market monitor: data center load has added $29.4B to capacity costs, urges auction delay

    PJM's independent market monitor, Monitoring Analytics, said in its Jan–Sept 2026 State of the Market report (posted Nov 12) that including data center load in the capacity market has raised capacity costs for all customers by $29.4 billion to date. It found the total wholesale cost of power averaged $111.61/MWh in the first nine months of 2026, $9.95/MWh (9.8%) more than it would have been without data center load's effect on capacity prices, and warned that the December 2026 auction for 2029/2030 will likely clear at the maximum price and add another $5 to $10 billion. The monitor recommends postponing that auction until forecast data center load can be removed and served through bilateral contracts or a backstop procurement; PJM told the Pennsylvania Capital-Star that state regulators, not PJM, decide how those costs are shared.

    Sources: Monitoring Analytics (PJM Independent Market Monitor) · Pennsylvania Capital-Star (via WITF) · Data Center Index

  13. · Build · Utah

    Carbon County, Utah approves permit for Valar Atomics' nuclear-and-gas data center campus

    The Carbon County Planning Commission approved a conditional use permit on Nov 12, with one vote against, for Valar Atomics' Raceway Energy Campus on 640 acres of Utah trust land, The Salt Lake Tribune reports. The company describes the campus as about 3 GW, with a natural gas plant powering the data centers first and 40 to 120 small reactors later; data center MW is not stated. Conditions include an emergency response plan, workforce housing, noise, water and waste plans, a goal of zero local water use, and road upgrades; the project still needs a county building permit, a Utah air quality permit and an NRC construction permit. Watch list.

    Sources: The Salt Lake Tribune · Data Center Index

  14. · Build · Texas

    Fermi ends TensorWave lease, signs non-binding 600 MW letter of intent with a hyperscaler

    Fermi said in its Q3 2026 results on Nov 12 that it and TensorWave terminated their August 2026 lease at Project Matador near Amarillo, Texas; its 10-Q says the lease ended on Nov 10 after the Oct 31 closing date passed. Fermi also reported a non-binding letter of intent with an unnamed investment-grade hyperscaler for about 600 MW of powered land, backed by a $200 million prepayment agreement and a $15 million early construction agreement, with a definitive lease still to be negotiated. Fermi says the site could ramp to about 17 GW, subject to binding customer agreements and permits.

    Sources: Fermi Inc. / SEC · Fermi Inc. / SEC · Data Center Index

  15. · Grid · Texas

    ERCOT CEO will ask Texas lawmakers to let it curtail data centers before a grid emergency

    ERCOT CEO Pablo Vegas said at the BloombergNEF Summit in Houston on Nov 11 that he will seek legislative authority to require data centers to cut power use at energy emergency level one or earlier, Bloomberg reported. Today large loads can be asked to cut demand only once the grid reaches level two of a three-level emergency; SB 6 (2025) already lets ERCOT order large non-critical loads to curtail with 24 hours' notice, but ERCOT has not used it. Vegas said data centers have access to low single-digit gigawatts of flexibility for the coming winter; the change needs the 2027 Legislature.

    Sources: Bloomberg (via Insurance Journal) · TexasPowerCost · Data Center Index

  16. · Build · Alberta

    Filings show 3.6 GW 'Lynx' data centre and two gas plants planned next to Meta's Alberta campus

    The Logic reports that AESO grid filings describe 'Lynx', a phased data centre of up to 3.6 GW in Sturgeon County, Alberta, with two proposed gas plants called Sturgeon Gas, targeting a June 2031 in-service date. A newly incorporated company whose directors include Pembina executives and a Morgan Stanley Infrastructure Partners investor in Pembina's Greenlight Electricity Centre (which supplies Meta's Sturgeon campus) bought about 134 acres next to Meta's site last month, per Alberta land records. Pembina declined to comment on the land; no customer is named and the gas plants' size is not stated. Watch list: early-stage grid request, single secondary source.

    Sources: The Logic · Data Center Index

  17. · Policy · California

    Oakland, California extends its data center moratorium to Oct 5, 2027

    Oakland's city council voted unanimously on Nov 10 to extend its temporary moratorium on new data center approvals to Oct 5, 2027, and passed an emergency ordinance barring permits, zoning changes and other land-use agreements for data centers, The Oaklandside reports. The original 45-day moratorium, adopted Oct 6, was due to expire Nov 20. Officials cited power and water use, air and noise pollution, and a planning code that does not account for facilities of this scale; the city is consulting PG&E, EBMUD and Ava Community Energy.

    Sources: The Oaklandside · Data Center Index

  18. · Build · Alaska

    Alaska approves 50-year state land lease for STAK's gas-powered North Slope data center

    The Alaska Department of Natural Resources issued a final decision on Nov 10 granting STAK a 50-year lease of about 715 acres on the North Slope near the Dalton Highway for its STAK Energy Campus, Alaska Beacon reports (via KNBA). DNR describes a 1-3 GW generation system fired with locally produced North Slope gas, not tied to the Railbelt grid; the state would collect land rent plus a fee on electricity produced and used. More than 1,200 public comments were filed, most opposed; the decision is open to a 20-day reconsideration period, and the project still needs a federal wetlands permit and a state air permit.

    Sources: KNBA / Alaska Beacon · Baxtel · Data Center Index

  19. · Policy · Georgia

    Lee County, Georgia extends data center moratorium to June 30, 2027; Dade County weighs 90-day pause

    Lee County commissioners voted on Nov 10 to extend their pause on data center zoning, permitting and construction in unincorporated areas to June 30, 2027, or until a data center ordinance is adopted, WALB reports. In northwest Georgia, Dade County commissioners took up a 90-day moratorium on Nov 5 after Atlanta-based Masterworks floated a data center of about 300 MW at the county's development park; the Chattanooga Times Free Press reported a unanimous vote, while WTVC reported the ordinance was sent to the county's Special Use Permit Board for input (both as summarized by Baxtel). The Masterworks proposal is early-stage and stays on the watch list.

    Sources: WALB · Baxtel · Data Center Index

  20. · Policy · Oklahoma, Idaho

    Oklahoma City extends data center moratorium through 2027; Boise adopts six-month pause

    Oklahoma City's council voted unanimously on Nov 10 to extend its moratorium on new applications and rezonings for data centers over 75 MW to Dec 31, 2027, or until the zoning code is updated, The Oklahoman reports. The same night Boise's council unanimously adopted a six-month emergency moratorium on data centers of at least 100,000 sq ft or 20 MW (including on-site power), KTVB reports. No qualifying Boise application had been filed, and a proposed Rhea Data campus outside city limits is not covered.

    Sources: The Oklahoman (via Yahoo News) · KTVB (via Yahoo News) · Data Center Index

All updates

What changed

Campus figures changed in the last 30 days, with the basis for each change.

No campus figures changed in the last 30 days.

The buildout, state by state

Tracked campuses of 100 MW or more, announced capacity, the load we expect to be running by 2030 and the natural gas it adds on an average day. Select a state for its latest updates and every campus.

State or provinceCampusesAnnounced MWExpected MW 2030Added gas MMcf/dLatest update
Texas2964,34718,6361,918.2Nov 13, 2026
Ohio414,0004,740383.1Nov 3, 2026
Indiana58,3004,103320.8Nov 12, 2026
Pennsylvania411,1003,780370.7Nov 12, 2026
Utah323,0003,573309.6Nov 12, 2026
Virginia57,4703,501273.7Nov 17, 2026
Georgia35,6761,582154.7Nov 17, 2026
New Mexico314,4101,479149.4–
Oklahoma45,1401,42793.0Nov 10, 2026
West Virginia36,4001,313117.7Oct 30, 2026
Wyoming12,7001,29684.4Nov 5, 2026
Louisiana15,0001,200156.4Nov 13, 2026
Michigan21,7401,01279.1Oct 27, 2026
Tennessee11,000900148.6–
Alberta38,730838118.8Nov 11, 2026
Wisconsin11,48079962.5–
Illinois33,80078661.5Nov 13, 2026
Nevada23,60075649.3Nov 10, 2026
North Dakota170070045.6–
Kentucky23,80055851.0Nov 9, 2026
Arizona23,30051340.2Nov 7, 2026
Nebraska22,70050733.1–
Kansas12,00042027.4Nov 3, 2026
Alaska13,00027031.7Nov 10, 2026
Missouri11,20025216.4–
California0000.0Nov 10, 2026
Idaho0000.0Nov 10, 2026
Maine0000.0Nov 3, 2026
Minnesota0000.0Nov 12, 2026
New Jersey0000.0Nov 3, 2026
North Carolina0000.0Nov 16, 2026

Methodology, timeline and data

The reference side of the index lives on datacenterindex.info: how campuses are sized and rated, the modelled timeline to 2030, every source, and the downloadable data.

Source: Data Center Index (datacenterindex.info), Discovery Energy.