Data Center Index · United States

Data centers in Indiana

The latest data center news for Indiana, then every tracked campus of 100 MW or more with its status, size, power supply and impact rating.

Campuses5100 MW or more
Announced8,300 MWAt full buildout
Expected by 20304,103 MWWeighted by build stage
Added gas burn320.8 MMcf/dAverage day

Latest updates in Indiana

  1. · Build · Indiana

    Digital Realty picks Kokomo, Indiana for a 1 GW campus

    Digital Realty plans about 1 GW of IT load (1.5 GW of power) on 476 acres in Kokomo, served by Duke Energy Indiana, with build-out to 2033. Added as DC-085 (announced).

    Sources: Baxtel · DatacenterDynamics · Data Center Index

The buildout in Indiana

We track 5 data center campuses of 100 MW or more in Indiana (2 operating and expanding, 2 under construction, 1 announced). Together they announce 8,300 MW at full buildout; weighted by build stage, we expect about 4,103 MW to be running by 2030. That load lands on the MISO, PJM grids. Named power suppliers: Duke Energy Indiana; Indiana Michigan Power (AEP); NIPSCO. The largest expected load is Amazon Project Rainier (1,188 MW by 2030, operating, expanding). Added natural gas burn, from grid-supplied and on-site generation, comes to about 320.8 MMcf/d on an average day.

CampusLocationStatusAnnounced MWExpected MW 2030Power supplyUtilityImpactLast change
Amazon Project RainierAmazon (for Anthropic)New Carlisle, INOperating, expanding2,2001,188GridIndiana Michigan Power (AEP)GridNov 4, 2026
AWS Northern Indiana (Hobart)AmazonHobart, INUnder construction2,4001,152GridNIPSCOGrid–
Meta LebanonMetaLebanon, INUnder construction1,000800Not disclosedNot disclosedGridNov 4, 2026
Google Project ZodiacGoogleFort Wayne, INOperating, expanding1,200648GridIndiana Michigan Power (AEP)Grid–
Digital Realty Kokomo campusDigital RealtyKokomo (Howard County), INAnnounced1,500315Grid (Duke Energy Indiana)Duke Energy IndianaGridOct 17, 2026

Campus names link to full profiles on datacenterindex.info. Figures as of November 3, 2026. Source: Data Center Index (datacenterindex.info), Discovery Energy. How campuses are sized and rated: methodology.