The data center boom, discounted: 205 gigawatts announced, 55 expected by 2030
Discovery Energy's Data Center Index follows 87 large data center campuses across 24 U.S. states and Alberta. About three of every four megawatts their developers have announced are unlikely to be running by 2030. The quarter that is likely is landing on the grids that already price data centers into business electricity bills, and one megawatt in five plans to make its own power from natural gas.
As of November 20, 2026, the Data Center Index counts 87 campuses with 204,593 MW of announced capacity. Weighted by build stage and timing, it expects 54,941 MW to be operating by 2030, about 27% of the announced total, close to Wood Mackenzie's estimate that utilities will commit to roughly 28% of the 1,066 GW of data center power requests filed nationwide. Of the expected load, 10,325 MW (19%) is planned behind the meter, mostly on natural gas, and at full load the campuses would burn about 5.1 Bcf/d of gas. Measured against each grid's peak, the expected load equals 16.7% of ERCOT's record, 11.6% of SPP's and 10.3% of PJM's. Texas alone holds 34% of the expected megawatts.
01 / 10
The buildout in six numbers
The Data Center Index is Discovery Energy's running census of large data center campuses in the United States and Canada, built to show what each one does to the power grid, to natural gas demand and to the communities around it. Every figure below comes from its public feed as it stood on the morning of November 20, 2026.
87
campuses tracked in 24 U.S. states and Alberta
204,593 MW
announced what developers say they will build
54,941 MW
expected by 2030 27% of the announced total
10,325 MW
behind the meter 19% of expected load, mostly gas
5.1 Bcf/d
natural gas burn at full expected load, on site and grid
16.7%
of ERCOT's record peak the largest share of any grid
02 / 10
A 150-gigawatt discount
Add up what developers say they will build at the 87 campuses in the index and the total comes to 204,593 megawatts. That is more than the highest demand PJM, the country's largest grid, has ever served: its all-time summer peak is 166,929 MW, set in 2006.
The index does not take those figures at face value. Most of them, 53 of the 87, describe what a site could eventually hold, not power that anyone has contracted to deliver. So the index weights each campus by how far along it is, from proposed to operating, and by how much of its announced size could plausibly be running by 2030. The result is 54,941 MW, or 27% of what was announced. (The method is published at datacenterindex.info.)
Wood Mackenzie reached almost the same haircut by a different route. Its mid-2026 count found 1,066 GW of data center power requests filed with U.S. utilities and grid operators, and it expects them to commit to about 28%; the rest, some 768 GW, it describes as largely phantom load, duplicate or speculative requests that are unlikely to be built, Capacity reported.
The discount is far from even. MISO keeps 38% of its announced megawatts, PJM 34% and the Southeast 34%. ERCOT keeps 29%. SPP and the Mountain West keep 19%, and Alberta less than 10%. The low-retention regions are where developers have pitched the largest campuses on open land, often with no named tenant: Fermi America's 11,000 MW Project Matador near Amarillo, Creekstone Energy's 10,000 MW Delta Gigasite in Utah, O'Leary Digital's 9,000 MW Stratos campus at Lucin, Utah, and New Era Energy & Digital's 7,000 MW site in Lea County, New Mexico.
Project Matador shows why the discount matters. On November 12, Fermi reported that its lease with TensorWave, its first binding tenant, had been terminated, and that it had signed a non-binding letter of intent with an unnamed investment-grade hyperscaler for about 600 MW, backed by a $200 million prepayment agreement. The index carries Matador at 11,000 MW announced and 2,640 MW expected by 2030. Even that discounted figure is more than four times the only load now under negotiation. At Piketon, Ohio, SB Energy still describes a 10 GW complex, but its latest state environmental filings cover less than 500 acres of private land, down from more than 1,000, WOUB reported.
Grid queues show the same gap at a larger scale. ERCOT's large-load requests total about 474 GW, roughly 90% of them data centers, according to Gov. Greg Abbott's letter ordering an audit of the queue; the Texas grid's record peak is 91.1 GW. Alberta has requests for about 19,565 MW of new data centre load and allowed 1,200 MW to connect in its first stage. In PJM, the independent market monitor counted 4,016.9 MW of forecast data center load, 42% of the growth PJM had forecast between the 2026/27 and 2028/29 delivery years, as cancelled or delayed by September 21, Forbes reported.
Figure 1
Announced versus expected by 2030, by grid region
The pale bar is what developers announced. The solid bar is what the Data Center Index expects to be running by 2030, split into grid-served and on-site supply. Hover, tap or use the arrow keys for details.
- Announced
- Expected 2030, grid-served
- Expected 2030, on site (behind the meter)
Show the data
| Region | Campuses | Announced MW | Expected MW by 2030 | Share kept | Grid-served MW | On-site MW | Gas MMcf/d | Share of peak |
|---|---|---|---|---|---|---|---|---|
| ERCOT | 27 | 52,347 | 15,196 | 29% | 11,873 | 3,323 | 1,400 | 16.7% |
| PJM | 22 | 48,310 | 16,446 | 34% | 15,265 | 1,181 | 1,389 | 10.3% |
| SPP | 12 | 34,700 | 6,484 | 19% | 3,844 | 2,640 | 686 | 11.6% |
| West: Mountain/Northwest | 6 | 29,300 | 5,625 | 19% | 4,857 | 768 | 443 | Not calculated |
| MISO | 7 | 12,980 | 4,968 | 38% | 4,968 | 0 | 451 | Not calculated |
| Alberta (AESO) | 3 | 8,730 | 838 | 10% | 500 | 338 | 119 | 6.5% |
| Southeast utilities | 5 | 8,476 | 2,860 | 34% | 1,960 | 900 | 340 | Not calculated |
| West: Desert Southwest | 4 | 6,750 | 2,254 | 33% | 1,079 | 1,175 | 237 | Not calculated |
| Alaska | 1 | 3,000 | 270 | 9% | 270 | 0 | 32 | Not calculated |
| Total | 87 | 204,593 | 54,941 | 27% | 44,616 | 10,325 | 5,097 |
03 / 10
Where the expected load is landing
Texas dominates. Its 29 campuses account for 18,636 MW of the load the index expects by 2030, 34% of the total, spread across three grids: ERCOT, the Panhandle's share of SPP and the El Paso area of the Desert Southwest. Ohio (4,740 MW), Indiana (4,103 MW), Pennsylvania (3,780 MW), Utah (3,573 MW) and Virginia (3,501 MW) follow.
The largest projects have moved away from metro clusters. Thirty-three campuses sit outside any metropolitan area; they hold 51% of the announced megawatts and 41% of the expected load. Gigawatt-scale sites go where land, transmission and gas are available: the Permian Basin around Pecos and Fort Stockton, the Panhandle near Amarillo, Utah's west desert around Delta, and western Pennsylvania and southern Ohio, where retired coal plants and the former uranium enrichment site at Piketon offer land and existing grid connections.
The index follows large new and expanding campuses, generally 100 MW or more, not every operating data center, so established markets such as Northern Virginia appear only through their newest projects. It does not yet cover New York, New England, California, Ontario or Québec.
Figure 2
Where the expected load is landing
Every campus in the index, sized by announced and expected megawatts and coloured by how it plans to get power. Switch views for gas burn or state totals. Hover, tap or use the arrow keys for details.
- Grid power
- Gas on site (all or part)
- Power supply not disclosed
Pale ring: announced size. Solid circle: expected by 2030. Area is proportional to megawatts.
Circle area is proportional to modelled natural gas burn at full expected load, MMcf/d.
- Under 500 MW
- 500 to 999
- 1,000 to 1,999
- 2,000 to 3,999
- 4,000 MW or more
Expected data center load by 2030, by state or province.
Show the data
| Campus | Location | Grid region | Status | Announced MW | Expected MW by 2030 | Power supply |
|---|---|---|---|---|---|---|
| Fermi America Project Matador (HyperGrid) | Amarillo (Carson County), TX | SPP | Under construction | 11,000 | 2,640 | Gas on site (all or part) |
| Creekstone Delta Gigasite | Delta, UT | West: Mountain/Northwest | Under construction | 10,000 | 2,400 | Not disclosed |
| PORTS Technology Campus | Piketon, OH | PJM | Under construction | 10,000 | 2,400 | Not disclosed |
| TECfusions Keystone Connect | Upper Burrell, PA | PJM | Operating, expanding | 3,000 | 1,620 | Not disclosed |
| GW Ranch (Pecos County) | Fort Stockton, TX | ERCOT | Under construction | 7,650 | 1,469 | Gas on site (all or part) |
| Amazon Northeast Creek Technology Campus | Louisa County, VA | PJM | Under construction | 2,700 | 1,296 | Grid power |
| Google Project Tembo | Cheyenne, WY | West: Mountain/Northwest | Under construction | 2,700 | 1,296 | Not disclosed |
| Meta Hyperion | Richland Parish (Holly Ridge), LA | MISO | Under construction | 5,000 | 1,200 | Grid power |
| Amazon Project Rainier | New Carlisle, IN | PJM | Operating, expanding | 2,200 | 1,188 | Grid power |
| AWS Northern Indiana (Hobart) | Hobart, IN | MISO | Under construction | 2,400 | 1,152 | Grid power |
| Aligned Shippingport (Bruce Mansfield) | Shippingport, PA | PJM | Under construction | 2,000 | 960 | Not disclosed |
| IREN Sweetwater | Sweetwater, TX | ERCOT | Under construction | 2,000 | 960 | Grid power |
| Nscale Monarch Compute Campus | Point Pleasant, WV | PJM | Under construction | 2,000 | 960 | Not disclosed |
| Stargate Project Jupiter | Santa Teresa (Doña Ana County), NM | West: Desert Southwest | Under construction | 2,450 | 941 | Gas on site (all or part) |
| Tract Hanover Technology Park | Ashland, VA | PJM | Approved | 2,400 | 936 | Grid power |
| Meta Prometheus | New Albany, OH | PJM | Operating, expanding | 1,000 | 900 | Gas on site (all or part) |
| Riot Platforms Corsicana | Corsicana, TX | ERCOT | Operating, expanding | 1,000 | 900 | Grid power |
| xAI Colossus 1 + 2 | Memphis / Southaven, TN | Southeast utilities | Operating, expanding | 1,000 | 900 | Gas on site (all or part) |
| Homer City Energy Campus | Homer City, PA | PJM | Under construction | 4,500 | 864 | Gas on site (all or part) |
| PowerHouse Grand Prairie Campus | Grand Prairie, TX | ERCOT | Under construction | 1,800 | 864 | Not disclosed |
| Meta El Paso | El Paso, TX | West: Desert Southwest | Under construction | 1,000 | 800 | Gas on site (all or part) |
| Meta Lebanon | Lebanon, IN | MISO | Under construction | 1,000 | 800 | Not disclosed |
| Microsoft Fairwater 1 | Mount Pleasant, WI | MISO | Operating, expanding | 1,480 | 799 | Grid power |
| Galaxy Helios Campus | Afton (Dickens County), TX | ERCOT | Under construction | 1,630 | 782 | Grid power |
| Microsoft Pecos Campus (Project Kilby) | Pecos, TX | ERCOT | Approved | 2,000 | 780 | Gas on site (all or part) |
| Joule Energy & Data Center Campus | Holden (Millard County), UT | West: Mountain/Northwest | Under construction | 4,000 | 768 | Gas on site (all or part) |
| IREN Childress | Childress, TX | ERCOT | Operating | 750 | 750 | Grid power |
| AWS Project Galaxy | Sidney, OH | PJM | Under construction | 1,500 | 720 | Grid power |
| Core Scientific Pecos AI Campus | Pecos, TX | ERCOT | Under construction | 1,500 | 720 | Not disclosed |
| Stargate Lordstown | Lordstown, OH | PJM | Under construction | 1,500 | 720 | Not disclosed |
| Atlas Power Williston | Williston, ND | SPP | Operating | 700 | 700 | Grid power |
| Riot Platforms Rockdale | Rockdale, TX | ERCOT | Operating | 700 | 700 | Grid power |
| Stargate Michigan 'The Barn' | Saline Township, MI | MISO | Under construction | 1,400 | 672 | Grid power |
| Vantage Frontier (Stargate) | Shackelford County, TX | ERCOT | Under construction | 1,400 | 672 | Gas on site (all or part) |
| Taylor Technology Campus | Taylor (Williamson County), TX | ERCOT | Approved | 1,000 | 650 | Gas on site (all or part) |
| Google Project Zodiac | Fort Wayne, IN | PJM | Operating, expanding | 1,200 | 648 | Grid power |
| Stargate Abilene | Abilene, TX | ERCOT | Operating, expanding | 1,200 | 648 | Gas on site (all or part) |
| OpenAI Project Camellia | Effingham County, GA | Southeast utilities | Approved | 3,210 | 626 | Grid power |
| Stargate Milam County (Project Freebird) | Burlington (Milam County), TX | ERCOT | Under construction | 1,200 | 576 | Not disclosed |
| Microsoft Fairwater Atlanta | Fayetteville, GA | Southeast utilities | Operating, expanding | 636 | 572 | Grid power |
| Bitdeer Texas | Rockdale, TX | ERCOT | Operating | 563 | 563 | Grid power |
| STACK NVA02 | Bristow, VA | PJM | Operating | 420 | 504 | Grid power |
| TA Realty Leesburg campus | Leesburg, VA | PJM | Operating | 450 | 450 | Grid power |
| Tesla Cortex 2 (Giga Texas) | Austin, TX | ERCOT | Operating, expanding | 500 | 450 | Grid power |
| Core Scientific Muskogee 2 | Muskogee, OK | SPP | Operating | 440 | 440 | Grid power |
| Caldwell County campuses (PowerHouse / Tract) | Uhland, TX | ERCOT | Announced | 4,000 | 420 | Not disclosed |
| Digital Realty Astra Enterprise Park | De Soto, KS | SPP | Announced | 2,000 | 420 | Not disclosed |
| Poolside Project Horizon | Fort Stockton, TX | ERCOT | Announced | 2,000 | 420 | Not disclosed |
| Tract TRIC Master-Planned Park | Sparks (Storey County), NV | West: Mountain/Northwest | Announced | 2,000 | 420 | Not disclosed |
| Stratos AI Data Center Campus | Lucin, UT | West: Mountain/Northwest | Proposed | 9,000 | 405 | Not disclosed |
| Data Journey The Bunker | Montgomery, TX | ERCOT | Operating | 400 | 400 | Grid power |
| Core Scientific Denton | Denton, TX | ERCOT | Operating | 394 | 394 | Grid power |
| Project Bunkhouse | Stilesboro, GA | Southeast utilities | Announced | 1,830 | 384 | Not disclosed |
| Joliet Technology Center | Joliet, IL | PJM | Announced | 1,800 | 378 | Not disclosed |
| Paducah GDP AI Campus | Kevil, KY | Southeast utilities | Announced | 1,800 | 378 | Not disclosed |
| Project Cardinal | Yorkville, IL | PJM | Announced | 1,800 | 378 | Not disclosed |
| Tract Buckeye Tech Corridor | Buckeye, AZ | West: Desert Southwest | Announced | 1,800 | 378 | Not disclosed |
| Galaxy Project Merlin (Helios II) | McGregor, TX | ERCOT | Announced | 3,500 | 368 | Not disclosed |
| Stark Hallam Hyperscale | Hallam, NE | SPP | Announced | 1,700 | 357 | Not disclosed |
| Meta Sturgeon County | Sturgeon County, AB | Alberta (AESO) | Announced | 1,000 | 350 | Gas on site (all or part) |
| Hyperscale Data Michigan | Dowagiac, MI | PJM | Operating | 340 | 340 | Grid power |
| Wonder Valley | Greenview (MD), AB | Alberta (AESO) | Proposed | 7,500 | 338 | Gas on site (all or part) |
| IREN SE Oklahoma Campus | Clayton, OK | SPP | Announced | 1,600 | 336 | Not disclosed |
| IREN Woods County Campus | Alva, OK | SPP | Announced | 1,600 | 336 | Not disclosed |
| Tract Silver Springs Park | Silver Springs, NV | West: Mountain/Northwest | Announced | 1,600 | 336 | Not disclosed |
| Wildcat Ridge AI Campus | Archbald, PA | PJM | Announced | 1,600 | 336 | Not disclosed |
| Compass Red Oak DFW III | Red Oak, TX | ERCOT | Operating, expanding | 360 | 324 | Grid power |
| AWS Wilderness Crossing | Montford (Orange County), VA | PJM | Announced | 1,500 | 315 | Not disclosed |
| Cloverleaf Project Open Sky | Piedmont, OK | SPP | Announced | 1,500 | 315 | Not disclosed |
| Crusoe Victoria AI Factory | Victoria, TX | ERCOT | Announced | 1,500 | 315 | Not disclosed |
| Digital Realty Kokomo campus | Kokomo (Howard County), IN | MISO | Announced | 1,500 | 315 | Grid power |
| New Era Lea County Data Center | Lovington, NM | SPP | Proposed | 7,000 | 315 | Not disclosed |
| Stak Energy North Slope | North Slope, AK | Alaska | Proposed | 3,000 | 270 | Not disclosed |
| CloudBurst San Marcos Data Center I | San Marcos, TX | ERCOT | Announced | 1,200 | 252 | Not disclosed |
| Nebius Independence | Independence, MO | SPP | Announced | 1,200 | 252 | Not disclosed |
| Data City Texas | Laredo, TX | ERCOT | Proposed | 5,000 | 225 | Not disclosed |
| Sailfish Comanche Circle | Tolar, TX | ERCOT | Proposed | 5,000 | 225 | Not disclosed |
| Roswell Information Park | Roswell, NM | SPP | Proposed | 4,960 | 223 | Not disclosed |
| Amp Energy East Texas | Lufkin, TX | ERCOT | Proposed | 2,100 | 189 | Not disclosed |
| Eneus Energy Harlingen | Harlingen, TX | ERCOT | Proposed | 2,000 | 180 | Not disclosed |
| Fundamental Data Ridgeline | Hambleton, WV | PJM | Proposed | 2,000 | 180 | Not disclosed |
| Rubix Project Ashland | Russell, KY | PJM | Proposed | 2,000 | 180 | Not disclosed |
| Adams Fork Data Center Energy Campus | Wharncliffe, WV | PJM | Proposed | 2,400 | 173 | Gas on site (all or part) |
| Google / Tenaska SE Nebraska | Southeast Nebraska, NE | SPP | Proposed | 1,000 | 150 | Not disclosed |
| TransAlta Keephills data centre | Keephills (Parkland County), AB | Alberta (AESO) | Approved | 230 | 150 | Grid power |
| Hassayampa Ranch Data Center | Tonopah, AZ | West: Desert Southwest | Proposed | 1,500 | 135 | Not disclosed |
| TerraWatt Alton (former Alton Steel) | Alton (Madison County), IL | MISO | Proposed | 200 | 30 | Not disclosed |
04 / 10
Measured against the peak
A megawatt matters most in relation to the grid that has to serve it. In ERCOT, the 15,196 MW the index expects by 2030 equals 16.7% of the record 91,134 MW peak set on July 22, 2026, according to ERCOT. In SPP, the expected 6,484 MW equals 11.6% of the 2025 peak, or 11.2% of the 57.9 GW record the pool set on July 27, 2026, EIA reported. PJM's 16,446 MW is 10.3% of a 160 GW peak, and Alberta's 838 MW is 6.5% of its record.
Not all of that load will draw on the grid at the peak hour. On-site plants carry 22% of ERCOT's expected load and 41% of SPP's. Counting grid-served load only, the shares fall to 13.0% in ERCOT, 6.9% in SPP and 9.5% in PJM. Several on-site campuses still hold or seek a grid connection as well, so planners cannot simply subtract them.
In PJM the numbers land in a market already priced at its ceiling. The 2029/30 capacity auction, scheduled for December 9 to 15, uses a forecast peak of 171,916 MW, 3.6% above the year before, PJM's planning parameters show. The independent market monitor estimates that keeping forecast data center load in the auction could add $5 billion to $10 billion to its cost and has asked PJM to postpone it; consumer advocates from seven states made the same request on November 18, Utility Dive reported. The monitor already attributes $29.4 billion of capacity costs across four auctions to data center load, and puts the total cost of wholesale power in the first nine months of 2026 at $111.61 per MWh, $9.95 higher than it would have been without that load in the capacity market, S&P Global reported.
Texas is meeting the same pressure through operating rules more than prices. ERCOT chief executive Pablo Vegas said on November 11 that he will ask lawmakers for authority to curtail data centers at the first level of an energy emergency, earlier than the law now allows, Bloomberg reported.
Figure 3
Expected data center load as a share of each grid's peak
Each bar is the grid's peak demand; the coloured part is the data center load the index expects by 2030.
- Peak demand (whole bar)
- Expected data center load, grid-served
- Expected data center load, on site
Show the data
| Grid | Expected MW by 2030 | Grid-served MW | On-site MW | Peak used | Share of peak | Grid-served share |
|---|---|---|---|---|---|---|
| ERCOT | 15,196 | 11,873 | 3,323 | 91.1 GW, record set July 22, 2026 | 16.7% | 13.0% |
| SPP | 6,484 | 3,844 | 2,640 | 56.0 GW, 2025 peak (record 57.9 GW, July 27, 2026) | 11.6% | 6.9% |
| PJM | 16,446 | 15,265 | 1,181 | 160 GW, 2025 summer peak | 10.3% | 9.5% |
| Alberta (AESO) | 838 | 500 | 338 | 12.8 GW, record peak | 6.5% | 3.9% |
05 / 10
2027 to 2029: the crunch years
Timing matters as much as size. The index models 9.7 GW of its campuses as running by the end of 2025 and only 3.0 GW more arriving in 2026. Then the additions jump: 9.9 GW in 2027, 11.4 GW in 2028 and 12.4 GW in 2029, before easing to 8.4 GW in 2030. Running for a full year at the loads the index expects, the 87 campuses would use about 361 TWh of electricity, roughly twice the 176 TWh that Lawrence Berkeley National Laboratory estimates every data center in the United States used in 2023.
The later the year, the less anyone knows about where the power will come from. Of the load running by the end of 2025, 79% sits on campuses that buy grid power and say so. Of the megawatts the index expects to arrive in 2029, 59% belong to campuses that have not disclosed their power supply; in 2030 the share is 65%. Those megawatts will either appear in a utility's load forecast or build their own plants, and for most of them the choice is still open.
Equipment narrows the options. GE Vernova's backlog and slot reservations for gas turbines reached 116 GW in the second quarter, and like Siemens Energy and Mitsubishi Heavy Industries it is booking reservations four to five years out, Utility Dive reported. Its third-quarter gas equipment orders were priced more than 20% above late-2025 levels, DCD reported. A campus that has not secured generation by now is competing for turbines that arrive at the very end of this decade or later, which pushes more of the late-decade load back onto the grid.
Figure 4
Megawatts arriving each year, by how they will be powered
Expected load added each year at the 87 campuses, modelled by the index from build stage. Pick a region; hover, tap or use the arrow keys for each year.
- Grid power
- Gas on site (all or part)
- Not disclosed
Running total, GW: 9.7 → 12.8 → 22.7 → 34.1 → 46.5 → 54.9
Running total, GW: 3.5 → 4.6 → 8.0 → 11.2 → 14.5 → 16.4
Running total, GW: 4.0 → 4.5 → 7.7 → 10.7 → 13.7 → 15.2
Running total, GW: 1.1 → 1.1 → 1.1 → 2.5 → 4.5 → 6.5
Running total, GW: 0.4 → 1.0 → 2.3 → 3.3 → 4.4 → 5.0
Running total, GW: 0.0 → 0.4 → 1.7 → 3.7 → 6.1 → 7.9
Running total, GW: 0.7 → 1.1 → 1.9 → 2.6 → 3.3 → 4.0
Show the data
| Year | Grid power MW | Gas on site MW | Not disclosed MW | Added MW | Running total MW |
|---|---|---|---|---|---|
| Through 2025 | 7,682 | 1,224 | 810 | 9,716 | 9,716 |
| 2026 | 1,220 | 1,012 | 805 | 3,037 | 12,753 |
| 2027 | 4,309 | 2,372 | 3,243 | 9,925 | 22,678 |
| 2028 | 2,985 | 3,026 | 5,397 | 11,408 | 34,086 |
| 2029 | 2,205 | 2,871 | 7,345 | 12,421 | 46,507 |
| 2030 | 530 | 2,387 | 5,516 | 8,434 | 54,940 |
06 / 10
The gas grid behind the meter
One megawatt in five of the expected load will not come from the grid at all. The index counts 10,325 MW of behind-the-meter supply by 2030, 19% of the total. In the Desert Southwest the share is 52%, in SPP 41% and in ERCOT 22%; in MISO it is zero. Fifteen campuses plan natural gas on site for all or part of their power, together 12.9 GW of expected load. Nationally the trend is larger on paper than on the ground: Cleanview identified 59 data centers with about 90 GW of planned behind-the-meter generation, and about 2 GW running in mid-2026, in its tracker report.
Approvals are now arriving weekly. On November 19 the Ohio Power Siting Board approved two gas plants that will serve only data centers, an 800 MW plant at Ashville and the 1,350 MW Fairfield Energy Center at Millersport, Signal Ohio reported. The Texas Commission on Environmental Quality resumed data center air permitting on November 16 and the same day cleared a 748 MW gas plant for SpaceX's Starbase campus, according to state records and Energy News Beat. In Louisiana, Entergy's latest estimate for Waterford 5, the gas plant it is building for Meta's Hyperion campus, is $1.755 billion, 63% above the first estimate, and the utility plans to seek approval in December for seven more plants for the same campus, WWNO reported.
Figure 5
Natural gas burn at full expected load, by region
Million cubic feet a day, by how each campus plans to get power. Grid campuses count the gas-fired share of the regional power supply.
- Grid power
- Gas on site (all or part)
- Not disclosed
Show the data
| Region | Grid power campuses | Gas on site campuses | Supply not disclosed | Total MMcf/d |
|---|---|---|---|---|
| ERCOT | 446 | 613 | 341 | 1,400 |
| PJM | 476 | 254 | 659 | 1,389 |
| SPP | 74 | 436 | 176 | 686 |
| MISO | 386 | 0 | 65 | 451 |
| West: Mountain/Northwest | 0 | 127 | 316 | 443 |
| Southeast utilities | 117 | 149 | 74 | 340 |
| West: Desert Southwest | 0 | 197 | 40 | 238 |
| Alberta (AESO) | 18 | 101 | 0 | 119 |
| Alaska | 0 | 0 | 32 | 32 |
| Total | 1,517 | 1,876 | 1,704 | 5,097 |
At full expected load the 87 campuses would burn about 5.1 billion cubic feet of natural gas a day, counting both on-site plants and the gas-fired share of the grid power they buy. About 4.3 Bcf/d of that is growth after 2025. For scale, EIA expects U.S. LNG exports to average 17.6 Bcf/d this year and 19 Bcf/d in 2027, in its November Short-Term Energy Outlook. Published estimates of data center gas demand by 2030 run from up to 4.1 Bcf/d (Enverus) to 6.1 Bcf/d (RBC Capital Markets), with East Daley Analytics at 4.2 to 6.1 and PwC's base case at 5.8. The index lands inside that range from the bottom up, campus by campus.
Figure 6
How the index compares with published 2030 gas demand estimates
Data center natural gas demand by 2030, billion cubic feet a day. Bars are ranges, dots single or base-case figures. For the index, the open dot is growth after 2025 and the solid dot the total.
- Data Center Index
- Published estimates
Show the data
| Estimate | Published | Bcf/d by 2030 |
|---|---|---|
| Data Center Index | Nov 2026, 87 campuses | 4.3 Bcf/d of growth after 2025; 5.1 Bcf/d in total at full expected load |
| Enverus Intelligence Research | Dec 2025 | Up to 4.1 Bcf/d by 2030 if all new capacity were gas-fired |
| East Daley Analytics | base case | 4.2 to 6.1 Bcf/d of new demand by 2030 |
| PwC | bear, base and bull cases | 5.2, 5.8 and 8.0 Bcf/d of AI-linked demand by 2030 |
| RBC Capital Markets | May 2026 | About 6.1 Bcf/d by 2030 versus 2024 |
The burn is concentrated where gas is already cheap and short of pipe. Prices at the Waha hub in the Permian traded below zero on 118 of the first 131 trading days of 2026 as production outran takeaway capacity, Oil & Gas Journal reported. Several of the largest on-site projects, including GW Ranch (7,650 MW announced) near Fort Stockton and Microsoft's Pecos campus, sit in that basin. Pipelines are being extended toward new loads: Natural Gas Pipeline Company of America has applied to FERC for a $139 million Amarillo expansion to carry more gas for power generation in the Texas Panhandle (Docket CP26-581), and Transwestern has filed for a lateral able to deliver 400,000 Dth/d to a power plant for an AI data center in Doña Ana County, New Mexico (Federal Register).
For industrial gas buyers in West Texas, the Panhandle and central Ohio, local demand of that size can narrow the discount to Henry Hub they have been used to, and it puts data center plants in line for the same pipeline capacity on cold days. Nationally, EIA forecasts Henry Hub at $3.37 per MMBtu for 2026 and $2.88 for 2027 as production growth outpaces demand, it said on November 10.
07 / 10
Separating firm projects from hopeful ones
Build stage drives most of the discount. The 15 proposed campuses announce 54,660 MW; the index expects 3,218 MW of it, 6%. The 22 campuses that are announced but not yet approved keep 19%. Campuses under construction keep 32%, because many of them are first phases of much larger plans. The 21 operating and expanding campuses keep 76% and already account for 14,190 MW.
Who stands behind a campus matters as much. Thirty-seven developer campuses, many without a named end user, make up 65% of the announced megawatts and 40% of the expected load. Twenty-eight campuses built by or for large cloud and AI companies, among them Amazon, Google, Meta, Microsoft, OpenAI and xAI, keep 43% of what they announced. Former cryptocurrency-mining sites converting to AI computing keep 60%, because most of them already run.
Half the campuses, 44 of 87, have not said how they will be powered, and they hold 58% of the announced megawatts. Twenty-one campuses rest on information the index grades as disputed or stale; they claim 72,900 MW and the index expects 9,415 MW from them. Size itself is a warning sign: the ten largest announcements add up to 77,150 MW, 38% of the total, and the index expects 15% of that to be running by 2030.
Figure 7
Where the announced megawatts fall away
Announced (pale) against expected by 2030 (solid), grouped four ways. Switch the grouping; hover, tap or use the arrow keys for details.
- Announced
- Expected by 2030
Show the data
| Group | Campuses | Announced MW | Expected MW by 2030 | Share kept |
|---|---|---|---|---|
| By build stage | ||||
| Operating or expanding | 21 | 18,733 | 14,190 | 76% |
| Under construction | 24 | 82,330 | 26,632 | 32% |
| Approved | 5 | 8,840 | 3,142 | 36% |
| Announced | 22 | 40,030 | 7,759 | 19% |
| Proposed | 15 | 54,660 | 3,218 | 6% |
| By who is building | ||||
| Developer campuses | 37 | 133,740 | 22,241 | 17% |
| AI campuses of large tech firms | 20 | 31,876 | 13,801 | 43% |
| Cloud campuses of large tech firms | 8 | 15,000 | 6,357 | 42% |
| Crypto-mining and HPC conversions | 13 | 13,217 | 7,921 | 60% |
| Colocation | 9 | 10,760 | 4,621 | 43% |
| By power supply | ||||
| Grid power | 28 | 36,503 | 18,931 | 52% |
| Gas on site (all or part) | 15 | 49,100 | 12,893 | 26% |
| Not disclosed | 44 | 118,990 | 23,117 | 19% |
| By source quality | ||||
| Grade B: several reliable sources | 15 | 29,700 | 11,496 | 39% |
| Grade C: one secondary source | 51 | 101,993 | 34,030 | 33% |
| Grade D: disputed or stale | 21 | 72,900 | 9,415 | 13% |
08 / 10
The rulebook changes this winter
Nearly every rule that decides who pays for this load is being rewritten between now and spring. On June 18, FERC ordered all six regional grid operators to justify or reform how they connect large loads (FERC). PJM answered on November 16 with a plan to cut study time for large loads and new generation from about two years to one and to create transmission services for loads that bring their own generation or can reduce demand (PJM). The same day, utilities filed long-term contracts at FERC that would commit a PJM data center to pay for at least 80% of the transmission service it requests for at least 10 years, Latitude Media reported. SPP's response is due today.
On November 19 the Senate passed the Bipartisan American Affordability and Jobs Act, 62 to 33. As introduced, it requires new data centers of 20 MW or more to pay the full incremental cost of the infrastructure built to serve them, NBC News reported; the House takes it up next. North Carolina regulators set a separate rate schedule for data centers above 50 MW on November 16 (Duke Energy), Alberta tabled a bill on November 18 that would keep data centres of 10 MW or more at least 600 metres from homes and put them under the Alberta Utilities Commission (BNN Bloomberg), and Loudoun County, Virginia paused action on new data center rezonings for 12 months (Loudoun Now).
Figure 8
Decisions that will set who pays, June 2026 to May 2027
One dot per decision, stacked by month; past events are faded. Hover, tap or use the arrow keys for details; the list below links to each source.
- Grid and markets
- Natural gas
- Legislation
- Jun 18GridFERC orders all six grid operators to justify or reform their large-load rules Responses were due November 16 (SPP November 20).
- Nov 16GridPJM files its Fast Energization plan; utilities propose 10- to 20-year transmission contracts MISO, CAISO, NYISO and ISO-NE also filed large-load reforms.
- Nov 18GridConsumer advocates from seven states ask PJM to delay its December auction Backed by the independent market monitor, which puts the cost of forecast data center load at $5 billion to $10 billion.
- Nov 19PolicySenate passes the Bipartisan American Affordability and Jobs Act, 62 to 33 As introduced, data centers of 20 MW or more pay the full incremental cost of infrastructure built for them. The House is next.
- Nov 19GasOhio approves 800 MW and 1,350 MW gas plants built only for data centers PowerConneX at Ashville; the Fairfield Energy Center at Millersport.
- Nov 20GridSPP's large-load filing due at FERC The last of the six responses to the June show cause orders.
- Dec 7GridComments due at FERC on utilities' large-load transmission contracts PJM transmission owners, MISO, California and New York utilities.
- Dec 9–15GridPJM 2029/30 capacity auction Sets capacity prices for June 2029 to May 2030 across 13 states and DC.
- Dec 10GridERCOT reports to the Texas PUC on data center eligibility and community impact Part of the audit Gov. Abbott ordered of the large-load queue (PUCT Project 58482).
- DecemberGasEntergy to seek Louisiana approval for seven more gas plants for Meta Hyperion Its estimate for the first plant, Waterford 5, rose 63% to $1.755 billion.
- Apr 9, 2027GridERCOT Batch Zero study results The first large-load group studied under Texas's new process.
- May 10, 2027GridPJM reliability backstop auction results Moved from December 2, 2026 by PJM's October 29 refiling.
09 / 10
What business energy buyers should do now
Data centers reach a commercial or industrial bill through capacity prices, transmission charges, wholesale energy and, increasingly, regional natural gas prices. The index's discounted numbers are still large enough to move all four. What to do depends on where a company's sites are.
Sites in PJM
December's auction sets capacity prices for June 2029 to May 2030, and whether forecast data center load stays in it decides much of the result. Check every peak load contribution on your bills, decide deliberately between capacity pass-through and fixed pricing, and line up contract terms with the auction calendar. See what to do about PJM capacity charges.
Sites in ERCOT
Expected data center load equals a sixth of the record peak, and the rules for curtailing it are still being written. Manage your share of the four summer peak intervals that set transmission costs, and price fixed terms with that summer peak risk in view. See ERCOT 4CP transmission charges.
Natural gas buyers
Data center burn is concentrated in the Permian, the Panhandle, Ohio and Louisiana. With EIA forecasting a softer 2027, consider fixing part of 2027 and 2028 supply while the forward curve reflects that outlook, and review basis exposure at local delivery points. See natural gas procurement and the pipeline map.
Regulated states
Large-load tariffs in Ohio, Virginia, North Carolina and elsewhere shift some costs to data centers, but generation and transmission built for them still enter rate cases. Follow your utility's filings and audit your rate class and riders before new rates take effect. See utility bill audits.
Every portfolio
Know what is being built near your facilities. The Data Center Index on deaudits.com lists every campus by state with the latest filings, and Discovery Energy runs one RFP across every deregulated state and audits bills everywhere else.
About the data. Figures are from the Data Center Index public feed (version 1) generated at 11:49 UTC on November 20, 2026: 87 indexed campuses, no watch-list or dropped sites. Expected megawatts and gas burn are modelled by the index from each campus's build stage and power supply; the method, the year-by-year timeline, campus profiles and data downloads are on datacenterindex.info. "Gas on site" in the map and charts means a campus plans natural gas generation for all or part of its power; the regional behind-the-meter totals use the index's own split of grid-served and on-site load. Map locations are approximate.
10 / 10
Questions about data center power demand
How much data center capacity will come online by 2030?
Discovery Energy's Data Center Index expects 54,941 MW at the 87 large campuses it tracks to be operating by 2030, out of 204,593 MW announced. Wood Mackenzie expects utilities to commit to about 28% of the 1,066 GW of data center power requests filed nationwide. Both point to roughly a quarter of announced capacity being built this decade.
Why is expected data center load so much lower than announced?
Most announced figures describe what a site could eventually hold, not contracted power. Developers file the same project with several utilities, many large campuses have no named tenant, and power equipment and grid connections take years. The index discounts each campus by build stage and timing: proposed campuses keep about 6% of their announced megawatts by 2030, campuses under construction about 32%.
How much natural gas will data centers use?
At full expected load, the 87 campuses in the Data Center Index would burn about 5.1 Bcf/d of natural gas by 2030, including the gas-fired share of the grid power they buy; about 4.3 Bcf/d of that is growth after 2025. Published analyst estimates of data center gas demand by 2030 range from about 4 to 6 Bcf/d.
Which grid has the most data center load relative to its size?
ERCOT. The load the index expects by 2030 equals 16.7% of the Texas grid's record 91,134 MW peak. In SPP the figure is 11.6% and in PJM 10.3%. Counting only grid-served load, the shares are 13.0%, 6.9% and 9.5%.
What does behind-the-meter power mean for a data center?
It means the campus makes its own electricity on site, usually with natural gas turbines, engines or fuel cells, instead of taking all of it from the utility grid. The index counts 10,325 MW of behind-the-meter supply by 2030, 19% of expected load, rising to 41% in SPP and 52% in the Desert Southwest.
How do data centers affect a business's electricity bill?
Through capacity prices, transmission charges and wholesale energy prices, and in some places through natural gas prices. The effect is largest in PJM, where forecast data center load raises capacity costs every customer pays. Discovery Energy explains the regional differences in how data centers affect commercial electricity prices by region.
Sources
- Data Center Index (datacenterindex.info), Discovery Energy, public feed v1, generated 2026-11-20 11:49 UTC: campuses, regions, states and modelled timeline. Method: datacenterindex.info/methodology.
- Capacity, Wood Mackenzie: US grid operators set to serve just 28% of requested data centre power (August 2026), 1,066 GW requested, about 768 GW phantom load.
- Fermi Inc., third-quarter 2026 results (SEC exhibit 99.1, November 12, 2026), TensorWave lease terminated; 600 MW letter of intent and $200 million prepayment agreement.
- WOUB, SB Energy's Pike County filings (November 17, 2026)
- Utility Dive, ERCOT aims to complete Texas governor's data center audit by December (2026), about 474 GW of requests, roughly 90% data centers.
- Government of Alberta, Is Alberta's grid ready?, about 19,565 MW requested; 1,200 MW interim limit.
- Forbes, PJM market monitor says 42% of forecast data center growth is delayed or canceled (October 12, 2026)
- American Public Power Association, PJM 2026 Long-Term Load Forecast, record summer peak of 166,929 MW in 2006.
- ERCOT, Monthly Operational Overview, July 2026, peak demand of 91,134 MW on July 22, 2026.
- EIA, Today in Energy: hourly peak load in ERCOT set a new record (August 3, 2026), SPP record of 57.9 GW on July 27.
- PJM, 2029/2030 Base Residual Auction planning period parameters, forecast peak 171,916 MW.
- Utility Dive, PJM urged to delay base capacity auction until data centers cut from forecast (November 19, 2026)
- S&P Global, PJM customer costs could increase by $10 billion after December capacity auction (November 12, 2026); Monitoring Analytics, 2026 Quarterly State of the Market Report, January to September.
- Bloomberg via Insurance Journal, ERCOT chief seeks earlier data center curtailment (November 12, 2026)
- Utility Dive, GE Vernova gas turbine backlog climbs to 116 GW (2026); DCD, GE Vernova order backlog hits $197bn (2026).
- Cleanview, Bypassing the Grid: how data center developers are building their own power plants (2026)
- Signal Ohio, Ohio approves two large power plants exclusively for data centers (November 19, 2026)
- Energy News Beat, Texas cleared a 748 MW gas plant for SpaceX's Starbase campus (November 2026), from TCEQ air registration 185303.
- WWNO, Entergy's Meta gas plant costs soar as utility seeks approval for seven more (November 19, 2026)
- EIA, Short-Term Energy Outlook, November 2026; EIA press release (November 10, 2026), Henry Hub $3.37 per MMBtu in 2026 and $2.88 in 2027.
- Enverus Intelligence Research, data center gas demand forecast (December 2025), up to 4.1 Bcf/d by 2030.
- East Daley Analytics, Data centers could add 6 Bcf/d to gas demand, base case 4.2 to 6.1 Bcf/d by 2030.
- PwC, Natural gas infrastructure for AI data centers (2026), 5.2, 5.8 and 8.0 Bcf/d by 2030.
- RBC Capital Markets, Natural gas powers the data center boom (May 2026), about 6.1 Bcf/d by 2030 versus 2024.
- Oil & Gas Journal, Permian gas-pipeline debottlenecking advancing at full speed (2026)
- Pipeline & Gas Journal, NGPL seeks FERC approval for Amarillo Expansion Project, Docket CP26-581 (October 2026)
- Federal Register, Transwestern Pipeline Company, Green Chile Project (February 17, 2026)
- FERC, show cause orders on large load interconnection (June 18, 2026)
- PJM Inside Lines, PJM proposal would cut interconnection process time in half (November 16, 2026)
- Latitude Media, Utilities want FERC to lock data centers into paying for grid upgrades (November 2026)
- NBC News, Senate passes sweeping bill simplifying permitting rules (November 19, 2026); NPR (November 20, 2026).
- Duke Energy, North Carolina regulators approve rate orders (November 17, 2026)
- BNN Bloomberg (The Canadian Press), Alberta data centre policies (November 18, 2026)
- Loudoun Now, Loudoun supervisors approve 12-month data center pause (November 2026)
- Lawrence Berkeley National Laboratory, 2024 United States Data Center Energy Usage Report, 176 TWh in 2023.
Find out what your bills should have cost.
Send one recent bill per site, or a list of accounts. We tell you where we expect findings before you sign anything. No upfront audit fee.