The data center boom, discounted: 205 gigawatts announced, 55 expected by 2030

Discovery Energy's Data Center Index follows 87 large data center campuses across 24 U.S. states and Alberta. About three of every four megawatts their developers have announced are unlikely to be running by 2030. The quarter that is likely is landing on the grids that already price data centers into business electricity bills, and one megawatt in five plans to make its own power from natural gas.

As of November 20, 2026, the Data Center Index counts 87 campuses with 204,593 MW of announced capacity. Weighted by build stage and timing, it expects 54,941 MW to be operating by 2030, about 27% of the announced total, close to Wood Mackenzie's estimate that utilities will commit to roughly 28% of the 1,066 GW of data center power requests filed nationwide. Of the expected load, 10,325 MW (19%) is planned behind the meter, mostly on natural gas, and at full load the campuses would burn about 5.1 Bcf/d of gas. Measured against each grid's peak, the expected load equals 16.7% of ERCOT's record, 11.6% of SPP's and 10.3% of PJM's. Texas alone holds 34% of the expected megawatts.

01 / 10

The buildout in six numbers

The Data Center Index is Discovery Energy's running census of large data center campuses in the United States and Canada, built to show what each one does to the power grid, to natural gas demand and to the communities around it. Every figure below comes from its public feed as it stood on the morning of November 20, 2026.

  • 87

    campuses tracked in 24 U.S. states and Alberta

  • 204,593 MW

    announced what developers say they will build

  • 54,941 MW

    expected by 2030 27% of the announced total

  • 10,325 MW

    behind the meter 19% of expected load, mostly gas

  • 5.1 Bcf/d

    natural gas burn at full expected load, on site and grid

  • 16.7%

    of ERCOT's record peak the largest share of any grid

02 / 10

A 150-gigawatt discount

Add up what developers say they will build at the 87 campuses in the index and the total comes to 204,593 megawatts. That is more than the highest demand PJM, the country's largest grid, has ever served: its all-time summer peak is 166,929 MW, set in 2006.

The index does not take those figures at face value. Most of them, 53 of the 87, describe what a site could eventually hold, not power that anyone has contracted to deliver. So the index weights each campus by how far along it is, from proposed to operating, and by how much of its announced size could plausibly be running by 2030. The result is 54,941 MW, or 27% of what was announced. (The method is published at datacenterindex.info.)

Wood Mackenzie reached almost the same haircut by a different route. Its mid-2026 count found 1,066 GW of data center power requests filed with U.S. utilities and grid operators, and it expects them to commit to about 28%; the rest, some 768 GW, it describes as largely phantom load, duplicate or speculative requests that are unlikely to be built, Capacity reported.

The discount is far from even. MISO keeps 38% of its announced megawatts, PJM 34% and the Southeast 34%. ERCOT keeps 29%. SPP and the Mountain West keep 19%, and Alberta less than 10%. The low-retention regions are where developers have pitched the largest campuses on open land, often with no named tenant: Fermi America's 11,000 MW Project Matador near Amarillo, Creekstone Energy's 10,000 MW Delta Gigasite in Utah, O'Leary Digital's 9,000 MW Stratos campus at Lucin, Utah, and New Era Energy & Digital's 7,000 MW site in Lea County, New Mexico.

Project Matador shows why the discount matters. On November 12, Fermi reported that its lease with TensorWave, its first binding tenant, had been terminated, and that it had signed a non-binding letter of intent with an unnamed investment-grade hyperscaler for about 600 MW, backed by a $200 million prepayment agreement. The index carries Matador at 11,000 MW announced and 2,640 MW expected by 2030. Even that discounted figure is more than four times the only load now under negotiation. At Piketon, Ohio, SB Energy still describes a 10 GW complex, but its latest state environmental filings cover less than 500 acres of private land, down from more than 1,000, WOUB reported.

Grid queues show the same gap at a larger scale. ERCOT's large-load requests total about 474 GW, roughly 90% of them data centers, according to Gov. Greg Abbott's letter ordering an audit of the queue; the Texas grid's record peak is 91.1 GW. Alberta has requests for about 19,565 MW of new data centre load and allowed 1,200 MW to connect in its first stage. In PJM, the independent market monitor counted 4,016.9 MW of forecast data center load, 42% of the growth PJM had forecast between the 2026/27 and 2028/29 delivery years, as cancelled or delayed by September 21, Forbes reported.

Figure 1

Announced versus expected by 2030, by grid region

The pale bar is what developers announced. The solid bar is what the Data Center Index expects to be running by 2030, split into grid-served and on-site supply. Hover, tap or use the arrow keys for details.

  • Announced
  • Expected 2030, grid-served
  • Expected 2030, on site (behind the meter)
ERCOT 27 campuses
15.2 GW of 52.3 GW 29%
PJM 22 campuses
16.4 GW of 48.3 GW 34%
SPP 12 campuses
6.5 GW of 34.7 GW 19%
West: Mountain/Northwest 6 campuses
5.6 GW of 29.3 GW 19%
MISO 7 campuses
5.0 GW of 13.0 GW 38%
Alberta (AESO) 3 campuses
0.8 GW of 8.7 GW 10%
Southeast utilities 5 campuses
2.9 GW of 8.5 GW 34%
West: Desert Southwest 4 campuses
2.3 GW of 6.8 GW 33%
Alaska 1 campuses
0.3 GW of 3.0 GW 9%
Source: Data Center Index (datacenterindex.info), Discovery Energy, feed of November 20, 2026. Expected megawatts weight each campus by build stage and timing. Select a region to open its page on datacenterindex.info. Not covered: NYISO, ISO-NE, CAISO, Ontario and Québec.
Show the data
RegionCampusesAnnounced MWExpected MW by 2030Share keptGrid-served MWOn-site MWGas MMcf/dShare of peak
ERCOT2752,34715,19629%11,8733,3231,40016.7%
PJM2248,31016,44634%15,2651,1811,38910.3%
SPP1234,7006,48419%3,8442,64068611.6%
West: Mountain/Northwest629,3005,62519%4,857768443Not calculated
MISO712,9804,96838%4,9680451Not calculated
Alberta (AESO)38,73083810%5003381196.5%
Southeast utilities58,4762,86034%1,960900340Not calculated
West: Desert Southwest46,7502,25433%1,0791,175237Not calculated
Alaska13,0002709%270032Not calculated
Total87204,59354,94127%44,61610,3255,097

03 / 10

Where the expected load is landing

Texas dominates. Its 29 campuses account for 18,636 MW of the load the index expects by 2030, 34% of the total, spread across three grids: ERCOT, the Panhandle's share of SPP and the El Paso area of the Desert Southwest. Ohio (4,740 MW), Indiana (4,103 MW), Pennsylvania (3,780 MW), Utah (3,573 MW) and Virginia (3,501 MW) follow.

The largest projects have moved away from metro clusters. Thirty-three campuses sit outside any metropolitan area; they hold 51% of the announced megawatts and 41% of the expected load. Gigawatt-scale sites go where land, transmission and gas are available: the Permian Basin around Pecos and Fort Stockton, the Panhandle near Amarillo, Utah's west desert around Delta, and western Pennsylvania and southern Ohio, where retired coal plants and the former uranium enrichment site at Piketon offer land and existing grid connections.

The index follows large new and expanding campuses, generally 100 MW or more, not every operating data center, so established markets such as Northern Virginia appear only through their newest projects. It does not yet cover New York, New England, California, Ontario or Québec.

Figure 2

Where the expected load is landing

Every campus in the index, sized by announced and expected megawatts and coloured by how it plans to get power. Switch views for gas burn or state totals. Hover, tap or use the arrow keys for details.

  • Grid power
  • Gas on site (all or part)
  • Power supply not disclosed

Pale ring: announced size. Solid circle: expected by 2030. Area is proportional to megawatts.

ALBERTA
Source: Data Center Index, feed of November 20, 2026. Locations are approximate (town or county). Select a campus to open its profile on datacenterindex.info, or a state for its page on deaudits.com. Alberta is shown as an inset, not to scale.
Show the data
All 87 campuses in the Data Center Index, by expected load
CampusLocationGrid regionStatusAnnounced MWExpected MW by 2030Power supply
Fermi America Project Matador (HyperGrid)Amarillo (Carson County), TXSPPUnder construction11,0002,640Gas on site (all or part)
Creekstone Delta GigasiteDelta, UTWest: Mountain/NorthwestUnder construction10,0002,400Not disclosed
PORTS Technology CampusPiketon, OHPJMUnder construction10,0002,400Not disclosed
TECfusions Keystone ConnectUpper Burrell, PAPJMOperating, expanding3,0001,620Not disclosed
GW Ranch (Pecos County)Fort Stockton, TXERCOTUnder construction7,6501,469Gas on site (all or part)
Amazon Northeast Creek Technology CampusLouisa County, VAPJMUnder construction2,7001,296Grid power
Google Project TemboCheyenne, WYWest: Mountain/NorthwestUnder construction2,7001,296Not disclosed
Meta HyperionRichland Parish (Holly Ridge), LAMISOUnder construction5,0001,200Grid power
Amazon Project RainierNew Carlisle, INPJMOperating, expanding2,2001,188Grid power
AWS Northern Indiana (Hobart)Hobart, INMISOUnder construction2,4001,152Grid power
Aligned Shippingport (Bruce Mansfield)Shippingport, PAPJMUnder construction2,000960Not disclosed
IREN SweetwaterSweetwater, TXERCOTUnder construction2,000960Grid power
Nscale Monarch Compute CampusPoint Pleasant, WVPJMUnder construction2,000960Not disclosed
Stargate Project JupiterSanta Teresa (Doña Ana County), NMWest: Desert SouthwestUnder construction2,450941Gas on site (all or part)
Tract Hanover Technology ParkAshland, VAPJMApproved2,400936Grid power
Meta PrometheusNew Albany, OHPJMOperating, expanding1,000900Gas on site (all or part)
Riot Platforms CorsicanaCorsicana, TXERCOTOperating, expanding1,000900Grid power
xAI Colossus 1 + 2Memphis / Southaven, TNSoutheast utilitiesOperating, expanding1,000900Gas on site (all or part)
Homer City Energy CampusHomer City, PAPJMUnder construction4,500864Gas on site (all or part)
PowerHouse Grand Prairie CampusGrand Prairie, TXERCOTUnder construction1,800864Not disclosed
Meta El PasoEl Paso, TXWest: Desert SouthwestUnder construction1,000800Gas on site (all or part)
Meta LebanonLebanon, INMISOUnder construction1,000800Not disclosed
Microsoft Fairwater 1Mount Pleasant, WIMISOOperating, expanding1,480799Grid power
Galaxy Helios CampusAfton (Dickens County), TXERCOTUnder construction1,630782Grid power
Microsoft Pecos Campus (Project Kilby)Pecos, TXERCOTApproved2,000780Gas on site (all or part)
Joule Energy & Data Center CampusHolden (Millard County), UTWest: Mountain/NorthwestUnder construction4,000768Gas on site (all or part)
IREN ChildressChildress, TXERCOTOperating750750Grid power
AWS Project GalaxySidney, OHPJMUnder construction1,500720Grid power
Core Scientific Pecos AI CampusPecos, TXERCOTUnder construction1,500720Not disclosed
Stargate LordstownLordstown, OHPJMUnder construction1,500720Not disclosed
Atlas Power WillistonWilliston, NDSPPOperating700700Grid power
Riot Platforms RockdaleRockdale, TXERCOTOperating700700Grid power
Stargate Michigan 'The Barn'Saline Township, MIMISOUnder construction1,400672Grid power
Vantage Frontier (Stargate)Shackelford County, TXERCOTUnder construction1,400672Gas on site (all or part)
Taylor Technology CampusTaylor (Williamson County), TXERCOTApproved1,000650Gas on site (all or part)
Google Project ZodiacFort Wayne, INPJMOperating, expanding1,200648Grid power
Stargate AbileneAbilene, TXERCOTOperating, expanding1,200648Gas on site (all or part)
OpenAI Project CamelliaEffingham County, GASoutheast utilitiesApproved3,210626Grid power
Stargate Milam County (Project Freebird)Burlington (Milam County), TXERCOTUnder construction1,200576Not disclosed
Microsoft Fairwater AtlantaFayetteville, GASoutheast utilitiesOperating, expanding636572Grid power
Bitdeer TexasRockdale, TXERCOTOperating563563Grid power
STACK NVA02Bristow, VAPJMOperating420504Grid power
TA Realty Leesburg campusLeesburg, VAPJMOperating450450Grid power
Tesla Cortex 2 (Giga Texas)Austin, TXERCOTOperating, expanding500450Grid power
Core Scientific Muskogee 2Muskogee, OKSPPOperating440440Grid power
Caldwell County campuses (PowerHouse / Tract)Uhland, TXERCOTAnnounced4,000420Not disclosed
Digital Realty Astra Enterprise ParkDe Soto, KSSPPAnnounced2,000420Not disclosed
Poolside Project HorizonFort Stockton, TXERCOTAnnounced2,000420Not disclosed
Tract TRIC Master-Planned ParkSparks (Storey County), NVWest: Mountain/NorthwestAnnounced2,000420Not disclosed
Stratos AI Data Center CampusLucin, UTWest: Mountain/NorthwestProposed9,000405Not disclosed
Data Journey The BunkerMontgomery, TXERCOTOperating400400Grid power
Core Scientific DentonDenton, TXERCOTOperating394394Grid power
Project BunkhouseStilesboro, GASoutheast utilitiesAnnounced1,830384Not disclosed
Joliet Technology CenterJoliet, ILPJMAnnounced1,800378Not disclosed
Paducah GDP AI CampusKevil, KYSoutheast utilitiesAnnounced1,800378Not disclosed
Project CardinalYorkville, ILPJMAnnounced1,800378Not disclosed
Tract Buckeye Tech CorridorBuckeye, AZWest: Desert SouthwestAnnounced1,800378Not disclosed
Galaxy Project Merlin (Helios II)McGregor, TXERCOTAnnounced3,500368Not disclosed
Stark Hallam HyperscaleHallam, NESPPAnnounced1,700357Not disclosed
Meta Sturgeon CountySturgeon County, ABAlberta (AESO)Announced1,000350Gas on site (all or part)
Hyperscale Data MichiganDowagiac, MIPJMOperating340340Grid power
Wonder ValleyGreenview (MD), ABAlberta (AESO)Proposed7,500338Gas on site (all or part)
IREN SE Oklahoma CampusClayton, OKSPPAnnounced1,600336Not disclosed
IREN Woods County CampusAlva, OKSPPAnnounced1,600336Not disclosed
Tract Silver Springs ParkSilver Springs, NVWest: Mountain/NorthwestAnnounced1,600336Not disclosed
Wildcat Ridge AI CampusArchbald, PAPJMAnnounced1,600336Not disclosed
Compass Red Oak DFW IIIRed Oak, TXERCOTOperating, expanding360324Grid power
AWS Wilderness CrossingMontford (Orange County), VAPJMAnnounced1,500315Not disclosed
Cloverleaf Project Open SkyPiedmont, OKSPPAnnounced1,500315Not disclosed
Crusoe Victoria AI FactoryVictoria, TXERCOTAnnounced1,500315Not disclosed
Digital Realty Kokomo campusKokomo (Howard County), INMISOAnnounced1,500315Grid power
New Era Lea County Data CenterLovington, NMSPPProposed7,000315Not disclosed
Stak Energy North SlopeNorth Slope, AKAlaskaProposed3,000270Not disclosed
CloudBurst San Marcos Data Center ISan Marcos, TXERCOTAnnounced1,200252Not disclosed
Nebius IndependenceIndependence, MOSPPAnnounced1,200252Not disclosed
Data City TexasLaredo, TXERCOTProposed5,000225Not disclosed
Sailfish Comanche CircleTolar, TXERCOTProposed5,000225Not disclosed
Roswell Information ParkRoswell, NMSPPProposed4,960223Not disclosed
Amp Energy East TexasLufkin, TXERCOTProposed2,100189Not disclosed
Eneus Energy HarlingenHarlingen, TXERCOTProposed2,000180Not disclosed
Fundamental Data RidgelineHambleton, WVPJMProposed2,000180Not disclosed
Rubix Project AshlandRussell, KYPJMProposed2,000180Not disclosed
Adams Fork Data Center Energy CampusWharncliffe, WVPJMProposed2,400173Gas on site (all or part)
Google / Tenaska SE NebraskaSoutheast Nebraska, NESPPProposed1,000150Not disclosed
TransAlta Keephills data centreKeephills (Parkland County), ABAlberta (AESO)Approved230150Grid power
Hassayampa Ranch Data CenterTonopah, AZWest: Desert SouthwestProposed1,500135Not disclosed
TerraWatt Alton (former Alton Steel)Alton (Madison County), ILMISOProposed20030Not disclosed

04 / 10

Measured against the peak

A megawatt matters most in relation to the grid that has to serve it. In ERCOT, the 15,196 MW the index expects by 2030 equals 16.7% of the record 91,134 MW peak set on July 22, 2026, according to ERCOT. In SPP, the expected 6,484 MW equals 11.6% of the 2025 peak, or 11.2% of the 57.9 GW record the pool set on July 27, 2026, EIA reported. PJM's 16,446 MW is 10.3% of a 160 GW peak, and Alberta's 838 MW is 6.5% of its record.

Not all of that load will draw on the grid at the peak hour. On-site plants carry 22% of ERCOT's expected load and 41% of SPP's. Counting grid-served load only, the shares fall to 13.0% in ERCOT, 6.9% in SPP and 9.5% in PJM. Several on-site campuses still hold or seek a grid connection as well, so planners cannot simply subtract them.

In PJM the numbers land in a market already priced at its ceiling. The 2029/30 capacity auction, scheduled for December 9 to 15, uses a forecast peak of 171,916 MW, 3.6% above the year before, PJM's planning parameters show. The independent market monitor estimates that keeping forecast data center load in the auction could add $5 billion to $10 billion to its cost and has asked PJM to postpone it; consumer advocates from seven states made the same request on November 18, Utility Dive reported. The monitor already attributes $29.4 billion of capacity costs across four auctions to data center load, and puts the total cost of wholesale power in the first nine months of 2026 at $111.61 per MWh, $9.95 higher than it would have been without that load in the capacity market, S&P Global reported.

Texas is meeting the same pressure through operating rules more than prices. ERCOT chief executive Pablo Vegas said on November 11 that he will ask lawmakers for authority to curtail data centers at the first level of an energy emergency, earlier than the law now allows, Bloomberg reported.

Figure 3

Expected data center load as a share of each grid's peak

Each bar is the grid's peak demand; the coloured part is the data center load the index expects by 2030.

  • Peak demand (whole bar)
  • Expected data center load, grid-served
  • Expected data center load, on site
ERCOT peak 91.1 GW
16.7% 13.0% grid-served
SPP peak 56.0 GW
11.6% 6.9% grid-served
PJM peak 160 GW
10.3% 9.5% grid-served
Alberta (AESO) peak 12.8 GW
6.5% 3.9% grid-served
Sources: Data Center Index, feed of November 20, 2026; ERCOT Monthly Operational Overview, July 2026; EIA. MISO, the Southeast and the West have no single peak in the index, so their shares are not calculated.
Show the data
GridExpected MW by 2030Grid-served MWOn-site MWPeak usedShare of peakGrid-served share
ERCOT15,19611,8733,32391.1 GW, record set July 22, 202616.7%13.0%
SPP6,4843,8442,64056.0 GW, 2025 peak (record 57.9 GW, July 27, 2026)11.6%6.9%
PJM16,44615,2651,181160 GW, 2025 summer peak10.3%9.5%
Alberta (AESO)83850033812.8 GW, record peak6.5%3.9%

05 / 10

2027 to 2029: the crunch years

Timing matters as much as size. The index models 9.7 GW of its campuses as running by the end of 2025 and only 3.0 GW more arriving in 2026. Then the additions jump: 9.9 GW in 2027, 11.4 GW in 2028 and 12.4 GW in 2029, before easing to 8.4 GW in 2030. Running for a full year at the loads the index expects, the 87 campuses would use about 361 TWh of electricity, roughly twice the 176 TWh that Lawrence Berkeley National Laboratory estimates every data center in the United States used in 2023.

The later the year, the less anyone knows about where the power will come from. Of the load running by the end of 2025, 79% sits on campuses that buy grid power and say so. Of the megawatts the index expects to arrive in 2029, 59% belong to campuses that have not disclosed their power supply; in 2030 the share is 65%. Those megawatts will either appear in a utility's load forecast or build their own plants, and for most of them the choice is still open.

Equipment narrows the options. GE Vernova's backlog and slot reservations for gas turbines reached 116 GW in the second quarter, and like Siemens Energy and Mitsubishi Heavy Industries it is booking reservations four to five years out, Utility Dive reported. Its third-quarter gas equipment orders were priced more than 20% above late-2025 levels, DCD reported. A campus that has not secured generation by now is competing for turbines that arrive at the very end of this decade or later, which pushes more of the late-decade load back onto the grid.

Figure 4

Megawatts arriving each year, by how they will be powered

Expected load added each year at the 87 campuses, modelled by the index from build stage. Pick a region; hover, tap or use the arrow keys for each year.

  • Grid power
  • Gas on site (all or part)
  • Not disclosed
02.557.51012.5GW added9.7By 2025+3.02026+9.92027+11.42028+12.42029+8.42030

Running total, GW: 9.7 → 12.8 → 22.7 → 34.1 → 46.5 → 54.9

Source: Data Center Index, feed of November 20, 2026 (modelled timeline). “Gas on site” includes campuses that combine grid power with on-site gas. Year-by-year detail by stage is on datacenterindex.info/timeline.
Show the data
All regions, megawatts added by year
YearGrid power MWGas on site MWNot disclosed MWAdded MWRunning total MW
Through 20257,6821,2248109,7169,716
20261,2201,0128053,03712,753
20274,3092,3723,2439,92522,678
20282,9853,0265,39711,40834,086
20292,2052,8717,34512,42146,507
20305302,3875,5168,43454,940

06 / 10

The gas grid behind the meter

One megawatt in five of the expected load will not come from the grid at all. The index counts 10,325 MW of behind-the-meter supply by 2030, 19% of the total. In the Desert Southwest the share is 52%, in SPP 41% and in ERCOT 22%; in MISO it is zero. Fifteen campuses plan natural gas on site for all or part of their power, together 12.9 GW of expected load. Nationally the trend is larger on paper than on the ground: Cleanview identified 59 data centers with about 90 GW of planned behind-the-meter generation, and about 2 GW running in mid-2026, in its tracker report.

Approvals are now arriving weekly. On November 19 the Ohio Power Siting Board approved two gas plants that will serve only data centers, an 800 MW plant at Ashville and the 1,350 MW Fairfield Energy Center at Millersport, Signal Ohio reported. The Texas Commission on Environmental Quality resumed data center air permitting on November 16 and the same day cleared a 748 MW gas plant for SpaceX's Starbase campus, according to state records and Energy News Beat. In Louisiana, Entergy's latest estimate for Waterford 5, the gas plant it is building for Meta's Hyperion campus, is $1.755 billion, 63% above the first estimate, and the utility plans to seek approval in December for seven more plants for the same campus, WWNO reported.

Figure 5

Natural gas burn at full expected load, by region

Million cubic feet a day, by how each campus plans to get power. Grid campuses count the gas-fired share of the regional power supply.

  • Grid power
  • Gas on site (all or part)
  • Not disclosed
ERCOT 15.2 GW expected
1,400 MMcf/d
PJM 16.4 GW expected
1,389 MMcf/d
SPP 6.5 GW expected
686 MMcf/d
MISO 5.0 GW expected
451 MMcf/d
West: Mountain/Northwest 5.6 GW expected
443 MMcf/d
Southeast utilities 2.9 GW expected
340 MMcf/d
West: Desert Southwest 2.3 GW expected
238 MMcf/d
Alberta (AESO) 0.8 GW expected
119 MMcf/d
Alaska 0.3 GW expected
32 MMcf/d
Source: Data Center Index, feed of November 20, 2026. The index models on-site gas at 9,500 Btu/kWh and grid load at each region's gas share and heat rate.
Show the data
RegionGrid power campusesGas on site campusesSupply not disclosedTotal MMcf/d
ERCOT4466133411,400
PJM4762546591,389
SPP74436176686
MISO386065451
West: Mountain/Northwest0127316443
Southeast utilities11714974340
West: Desert Southwest019740238
Alberta (AESO)181010119
Alaska003232
Total1,5171,8761,7045,097

At full expected load the 87 campuses would burn about 5.1 billion cubic feet of natural gas a day, counting both on-site plants and the gas-fired share of the grid power they buy. About 4.3 Bcf/d of that is growth after 2025. For scale, EIA expects U.S. LNG exports to average 17.6 Bcf/d this year and 19 Bcf/d in 2027, in its November Short-Term Energy Outlook. Published estimates of data center gas demand by 2030 run from up to 4.1 Bcf/d (Enverus) to 6.1 Bcf/d (RBC Capital Markets), with East Daley Analytics at 4.2 to 6.1 and PwC's base case at 5.8. The index lands inside that range from the bottom up, campus by campus.

Figure 6

How the index compares with published 2030 gas demand estimates

Data center natural gas demand by 2030, billion cubic feet a day. Bars are ranges, dots single or base-case figures. For the index, the open dot is growth after 2025 and the solid dot the total.

  • Data Center Index
  • Published estimates
Data Center Index Nov 2026, 87 campuses
4.3 / 5.1 Bcf/d
Enverus Intelligence Research Dec 2025
up to 4.1 Bcf/d
East Daley Analytics base case
4.2–6.1 Bcf/d
PwC bear, base and bull cases
5.2–8.0 Bcf/d
RBC Capital Markets May 2026
6.1 Bcf/d
Sources: Data Center Index; Enverus (December 2025); East Daley Analytics; PwC; RBC Capital Markets (May 2026). Estimates differ in scope and baseline year, so compare ranges, not decimals.
Show the data
EstimatePublishedBcf/d by 2030
Data Center IndexNov 2026, 87 campuses4.3 Bcf/d of growth after 2025; 5.1 Bcf/d in total at full expected load
Enverus Intelligence ResearchDec 2025Up to 4.1 Bcf/d by 2030 if all new capacity were gas-fired
East Daley Analyticsbase case4.2 to 6.1 Bcf/d of new demand by 2030
PwCbear, base and bull cases5.2, 5.8 and 8.0 Bcf/d of AI-linked demand by 2030
RBC Capital MarketsMay 2026About 6.1 Bcf/d by 2030 versus 2024

The burn is concentrated where gas is already cheap and short of pipe. Prices at the Waha hub in the Permian traded below zero on 118 of the first 131 trading days of 2026 as production outran takeaway capacity, Oil & Gas Journal reported. Several of the largest on-site projects, including GW Ranch (7,650 MW announced) near Fort Stockton and Microsoft's Pecos campus, sit in that basin. Pipelines are being extended toward new loads: Natural Gas Pipeline Company of America has applied to FERC for a $139 million Amarillo expansion to carry more gas for power generation in the Texas Panhandle (Docket CP26-581), and Transwestern has filed for a lateral able to deliver 400,000 Dth/d to a power plant for an AI data center in Doña Ana County, New Mexico (Federal Register).

For industrial gas buyers in West Texas, the Panhandle and central Ohio, local demand of that size can narrow the discount to Henry Hub they have been used to, and it puts data center plants in line for the same pipeline capacity on cold days. Nationally, EIA forecasts Henry Hub at $3.37 per MMBtu for 2026 and $2.88 for 2027 as production growth outpaces demand, it said on November 10.

07 / 10

Separating firm projects from hopeful ones

Build stage drives most of the discount. The 15 proposed campuses announce 54,660 MW; the index expects 3,218 MW of it, 6%. The 22 campuses that are announced but not yet approved keep 19%. Campuses under construction keep 32%, because many of them are first phases of much larger plans. The 21 operating and expanding campuses keep 76% and already account for 14,190 MW.

Who stands behind a campus matters as much. Thirty-seven developer campuses, many without a named end user, make up 65% of the announced megawatts and 40% of the expected load. Twenty-eight campuses built by or for large cloud and AI companies, among them Amazon, Google, Meta, Microsoft, OpenAI and xAI, keep 43% of what they announced. Former cryptocurrency-mining sites converting to AI computing keep 60%, because most of them already run.

Half the campuses, 44 of 87, have not said how they will be powered, and they hold 58% of the announced megawatts. Twenty-one campuses rest on information the index grades as disputed or stale; they claim 72,900 MW and the index expects 9,415 MW from them. Size itself is a warning sign: the ten largest announcements add up to 77,150 MW, 38% of the total, and the index expects 15% of that to be running by 2030.

Figure 7

Where the announced megawatts fall away

Announced (pale) against expected by 2030 (solid), grouped four ways. Switch the grouping; hover, tap or use the arrow keys for details.

  • Announced
  • Expected by 2030
Operating or expanding 21 campuses
14.2 GW of 18.7 GW 76%
Under construction 24 campuses
26.6 GW of 82.3 GW 32%
Approved 5 campuses
3.1 GW of 8.8 GW 36%
Announced 22 campuses
7.8 GW of 40.0 GW 19%
Proposed 15 campuses
3.2 GW of 54.7 GW 6%
Source: Data Center Index, feed of November 20, 2026. Source grades are the index's confidence ratings; no campus in this feed is graded A (a primary source for every figure).
Show the data
GroupCampusesAnnounced MWExpected MW by 2030Share kept
By build stage
Operating or expanding2118,73314,19076%
Under construction2482,33026,63232%
Approved58,8403,14236%
Announced2240,0307,75919%
Proposed1554,6603,2186%
By who is building
Developer campuses37133,74022,24117%
AI campuses of large tech firms2031,87613,80143%
Cloud campuses of large tech firms815,0006,35742%
Crypto-mining and HPC conversions1313,2177,92160%
Colocation910,7604,62143%
By power supply
Grid power2836,50318,93152%
Gas on site (all or part)1549,10012,89326%
Not disclosed44118,99023,11719%
By source quality
Grade B: several reliable sources1529,70011,49639%
Grade C: one secondary source51101,99334,03033%
Grade D: disputed or stale2172,9009,41513%

08 / 10

The rulebook changes this winter

Nearly every rule that decides who pays for this load is being rewritten between now and spring. On June 18, FERC ordered all six regional grid operators to justify or reform how they connect large loads (FERC). PJM answered on November 16 with a plan to cut study time for large loads and new generation from about two years to one and to create transmission services for loads that bring their own generation or can reduce demand (PJM). The same day, utilities filed long-term contracts at FERC that would commit a PJM data center to pay for at least 80% of the transmission service it requests for at least 10 years, Latitude Media reported. SPP's response is due today.

On November 19 the Senate passed the Bipartisan American Affordability and Jobs Act, 62 to 33. As introduced, it requires new data centers of 20 MW or more to pay the full incremental cost of the infrastructure built to serve them, NBC News reported; the House takes it up next. North Carolina regulators set a separate rate schedule for data centers above 50 MW on November 16 (Duke Energy), Alberta tabled a bill on November 18 that would keep data centres of 10 MW or more at least 600 metres from homes and put them under the Alberta Utilities Commission (BNN Bloomberg), and Loudoun County, Virginia paused action on new data center rezonings for 12 months (Loudoun Now).

Figure 8

Decisions that will set who pays, June 2026 to May 2027

One dot per decision, stacked by month; past events are faded. Hover, tap or use the arrow keys for details; the list below links to each source.

  • Grid and markets
  • Natural gas
  • Legislation
Jun2026JulAugSepOctNovDecJan2027FebMarAprMayNow
  1. Jun 18GridFERC orders all six grid operators to justify or reform their large-load rules Responses were due November 16 (SPP November 20).
  2. Nov 16GridPJM files its Fast Energization plan; utilities propose 10- to 20-year transmission contracts MISO, CAISO, NYISO and ISO-NE also filed large-load reforms.
  3. Nov 18GridConsumer advocates from seven states ask PJM to delay its December auction Backed by the independent market monitor, which puts the cost of forecast data center load at $5 billion to $10 billion.
  4. Nov 19PolicySenate passes the Bipartisan American Affordability and Jobs Act, 62 to 33 As introduced, data centers of 20 MW or more pay the full incremental cost of infrastructure built for them. The House is next.
  5. Nov 19GasOhio approves 800 MW and 1,350 MW gas plants built only for data centers PowerConneX at Ashville; the Fairfield Energy Center at Millersport.
  6. Nov 20GridSPP's large-load filing due at FERC The last of the six responses to the June show cause orders.
  7. Dec 7GridComments due at FERC on utilities' large-load transmission contracts PJM transmission owners, MISO, California and New York utilities.
  8. Dec 9–15GridPJM 2029/30 capacity auction Sets capacity prices for June 2029 to May 2030 across 13 states and DC.
  9. Dec 10GridERCOT reports to the Texas PUC on data center eligibility and community impact Part of the audit Gov. Abbott ordered of the large-load queue (PUCT Project 58482).
  10. DecemberGasEntergy to seek Louisiana approval for seven more gas plants for Meta Hyperion Its estimate for the first plant, Waterford 5, rose 63% to $1.755 billion.
  11. Apr 9, 2027GridERCOT Batch Zero study results The first large-load group studied under Texas's new process.
  12. May 10, 2027GridPJM reliability backstop auction results Moved from December 2, 2026 by PJM's October 29 refiling.
Sources: FERC, PJM, Utility Dive, NBC News, Signal Ohio, Latitude Media, Public Utility Commission of Texas, WWNO and the Data Center Index calendar.

09 / 10

What business energy buyers should do now

Data centers reach a commercial or industrial bill through capacity prices, transmission charges, wholesale energy and, increasingly, regional natural gas prices. The index's discounted numbers are still large enough to move all four. What to do depends on where a company's sites are.

Sites in PJM

December's auction sets capacity prices for June 2029 to May 2030, and whether forecast data center load stays in it decides much of the result. Check every peak load contribution on your bills, decide deliberately between capacity pass-through and fixed pricing, and line up contract terms with the auction calendar. See what to do about PJM capacity charges.

Sites in ERCOT

Expected data center load equals a sixth of the record peak, and the rules for curtailing it are still being written. Manage your share of the four summer peak intervals that set transmission costs, and price fixed terms with that summer peak risk in view. See ERCOT 4CP transmission charges.

Natural gas buyers

Data center burn is concentrated in the Permian, the Panhandle, Ohio and Louisiana. With EIA forecasting a softer 2027, consider fixing part of 2027 and 2028 supply while the forward curve reflects that outlook, and review basis exposure at local delivery points. See natural gas procurement and the pipeline map.

Regulated states

Large-load tariffs in Ohio, Virginia, North Carolina and elsewhere shift some costs to data centers, but generation and transmission built for them still enter rate cases. Follow your utility's filings and audit your rate class and riders before new rates take effect. See utility bill audits.

Every portfolio

Know what is being built near your facilities. The Data Center Index on deaudits.com lists every campus by state with the latest filings, and Discovery Energy runs one RFP across every deregulated state and audits bills everywhere else.

About the data. Figures are from the Data Center Index public feed (version 1) generated at 11:49 UTC on November 20, 2026: 87 indexed campuses, no watch-list or dropped sites. Expected megawatts and gas burn are modelled by the index from each campus's build stage and power supply; the method, the year-by-year timeline, campus profiles and data downloads are on datacenterindex.info. "Gas on site" in the map and charts means a campus plans natural gas generation for all or part of its power; the regional behind-the-meter totals use the index's own split of grid-served and on-site load. Map locations are approximate.

10 / 10

Questions about data center power demand

How much data center capacity will come online by 2030?

Discovery Energy's Data Center Index expects 54,941 MW at the 87 large campuses it tracks to be operating by 2030, out of 204,593 MW announced. Wood Mackenzie expects utilities to commit to about 28% of the 1,066 GW of data center power requests filed nationwide. Both point to roughly a quarter of announced capacity being built this decade.

Why is expected data center load so much lower than announced?

Most announced figures describe what a site could eventually hold, not contracted power. Developers file the same project with several utilities, many large campuses have no named tenant, and power equipment and grid connections take years. The index discounts each campus by build stage and timing: proposed campuses keep about 6% of their announced megawatts by 2030, campuses under construction about 32%.

How much natural gas will data centers use?

At full expected load, the 87 campuses in the Data Center Index would burn about 5.1 Bcf/d of natural gas by 2030, including the gas-fired share of the grid power they buy; about 4.3 Bcf/d of that is growth after 2025. Published analyst estimates of data center gas demand by 2030 range from about 4 to 6 Bcf/d.

Which grid has the most data center load relative to its size?

ERCOT. The load the index expects by 2030 equals 16.7% of the Texas grid's record 91,134 MW peak. In SPP the figure is 11.6% and in PJM 10.3%. Counting only grid-served load, the shares are 13.0%, 6.9% and 9.5%.

What does behind-the-meter power mean for a data center?

It means the campus makes its own electricity on site, usually with natural gas turbines, engines or fuel cells, instead of taking all of it from the utility grid. The index counts 10,325 MW of behind-the-meter supply by 2030, 19% of expected load, rising to 41% in SPP and 52% in the Desert Southwest.

How do data centers affect a business's electricity bill?

Through capacity prices, transmission charges and wholesale energy prices, and in some places through natural gas prices. The effect is largest in PJM, where forecast data center load raises capacity costs every customer pays. Discovery Energy explains the regional differences in how data centers affect commercial electricity prices by region.

Sources

  1. Data Center Index (datacenterindex.info), Discovery Energy, public feed v1, generated 2026-11-20 11:49 UTC: campuses, regions, states and modelled timeline. Method: datacenterindex.info/methodology.
  2. Capacity, Wood Mackenzie: US grid operators set to serve just 28% of requested data centre power (August 2026), 1,066 GW requested, about 768 GW phantom load.
  3. Fermi Inc., third-quarter 2026 results (SEC exhibit 99.1, November 12, 2026), TensorWave lease terminated; 600 MW letter of intent and $200 million prepayment agreement.
  4. WOUB, SB Energy's Pike County filings (November 17, 2026)
  5. Utility Dive, ERCOT aims to complete Texas governor's data center audit by December (2026), about 474 GW of requests, roughly 90% data centers.
  6. Government of Alberta, Is Alberta's grid ready?, about 19,565 MW requested; 1,200 MW interim limit.
  7. Forbes, PJM market monitor says 42% of forecast data center growth is delayed or canceled (October 12, 2026)
  8. American Public Power Association, PJM 2026 Long-Term Load Forecast, record summer peak of 166,929 MW in 2006.
  9. ERCOT, Monthly Operational Overview, July 2026, peak demand of 91,134 MW on July 22, 2026.
  10. EIA, Today in Energy: hourly peak load in ERCOT set a new record (August 3, 2026), SPP record of 57.9 GW on July 27.
  11. PJM, 2029/2030 Base Residual Auction planning period parameters, forecast peak 171,916 MW.
  12. Utility Dive, PJM urged to delay base capacity auction until data centers cut from forecast (November 19, 2026)
  13. S&P Global, PJM customer costs could increase by $10 billion after December capacity auction (November 12, 2026); Monitoring Analytics, 2026 Quarterly State of the Market Report, January to September.
  14. Bloomberg via Insurance Journal, ERCOT chief seeks earlier data center curtailment (November 12, 2026)
  15. Utility Dive, GE Vernova gas turbine backlog climbs to 116 GW (2026); DCD, GE Vernova order backlog hits $197bn (2026).
  16. Cleanview, Bypassing the Grid: how data center developers are building their own power plants (2026)
  17. Signal Ohio, Ohio approves two large power plants exclusively for data centers (November 19, 2026)
  18. Energy News Beat, Texas cleared a 748 MW gas plant for SpaceX's Starbase campus (November 2026), from TCEQ air registration 185303.
  19. WWNO, Entergy's Meta gas plant costs soar as utility seeks approval for seven more (November 19, 2026)
  20. EIA, Short-Term Energy Outlook, November 2026; EIA press release (November 10, 2026), Henry Hub $3.37 per MMBtu in 2026 and $2.88 in 2027.
  21. Enverus Intelligence Research, data center gas demand forecast (December 2025), up to 4.1 Bcf/d by 2030.
  22. East Daley Analytics, Data centers could add 6 Bcf/d to gas demand, base case 4.2 to 6.1 Bcf/d by 2030.
  23. PwC, Natural gas infrastructure for AI data centers (2026), 5.2, 5.8 and 8.0 Bcf/d by 2030.
  24. RBC Capital Markets, Natural gas powers the data center boom (May 2026), about 6.1 Bcf/d by 2030 versus 2024.
  25. Oil & Gas Journal, Permian gas-pipeline debottlenecking advancing at full speed (2026)
  26. Pipeline & Gas Journal, NGPL seeks FERC approval for Amarillo Expansion Project, Docket CP26-581 (October 2026)
  27. Federal Register, Transwestern Pipeline Company, Green Chile Project (February 17, 2026)
  28. FERC, show cause orders on large load interconnection (June 18, 2026)
  29. PJM Inside Lines, PJM proposal would cut interconnection process time in half (November 16, 2026)
  30. Latitude Media, Utilities want FERC to lock data centers into paying for grid upgrades (November 2026)
  31. NBC News, Senate passes sweeping bill simplifying permitting rules (November 19, 2026); NPR (November 20, 2026).
  32. Duke Energy, North Carolina regulators approve rate orders (November 17, 2026)
  33. BNN Bloomberg (The Canadian Press), Alberta data centre policies (November 18, 2026)
  34. Loudoun Now, Loudoun supervisors approve 12-month data center pause (November 2026)
  35. Lawrence Berkeley National Laboratory, 2024 United States Data Center Energy Usage Report, 176 TWh in 2023.