Pennsylvania natural gas case study, Pittsburgh, Pennsylvania. November 2026
Pittsburgh-area natural gas capacity: two gas utilities, both with thin peak-day margins
Peoples told regulators in March 2026 its design-day supply would be within 0.73 MMcf of its 1,487.6 MMcf per day requirement; Columbia Gas PA's firm capacity is about 2.8% above demand. Both are whole-system figures.
Metro used: the Pittsburgh, PA metropolitan statistical area, as delineated in OMB Bulletin No. 23-01 (July 21, 2023), which has eight counties (listed in the notes). Peoples Natural Gas Company LLC (Peoples) and Columbia Gas of Pennsylvania, Inc. (Columbia Gas PA) both list all eight in their tariffs. The design-day and peak-day figures below are for each utility's whole system, not the metro alone.5
Key takeaways
- Peoples said in a March 2026 rate case filing that its design-day requirement covers its whole 18-county system, not the Pittsburgh metro alone.1
- Peoples said its design-day supply assets will be within 0.73 MMcf of its requirement; the testimony does not say which way the gap runs.2
- Peoples projects 1,127.9 MMcf per day from six interstate pipelines (about 76%, our calculation) but does not split it by pipeline, so reliance on one pipeline is not shown.3
- Peoples said in March 2026 no data center or power project has a signed agreement.7 A gas pipeline is being built to the Shippingport Power Station in Beaver County.17
- Conventional-well gas delivered into Peoples' systems fell 29% from 2020 to 2025 and Peoples does not expect a reversal.4
- System context: Peoples said parts of its territory, such as Punxsutawney in Jefferson County (outside the metro), need support from specific interstate delivery points at times of high demand.6
- Columbia Gas PA's February 2026 filing shows firm capacity about 2.8% above firm design-day demand for winter 2026-27, below Discovery Energy's 5% thin-margin threshold, for its whole system.11
- Columbia Gas PA said the Warrendale and Bradford Woods market needs more capacity; a winter-only 10,500 Dth per day contract ran November 2025 to March 2026, renewable.12
What is the outlook for Pittsburgh gas capacity through 2029?
Discovery Energy rates the outlook for Pittsburgh-area natural gas capacity through 2029 as Elevated (confidence: Medium): Peoples said in March 2026 that its design-day supply would be within a stated margin of its requirement for its whole system, a margin so small that the testimony does not say which way the gap runs. Columbia Gas PA's filing shows firm capacity about 2.8% above firm design-day demand for winter 2026-27, for its whole system, and Columbia Gas PA says a Pittsburgh-area market needs more capacity. The record shows no approved or scheduled fix, no unmet need date and no signed large load in Peoples' filing.
Documented risk factors: none. We did not count the Columbia Gas PA flow restriction as an upstream limit: Columbia Gas PA says it is subject to hourly flow restrictions on the Eastern Gas Transmission and Storage pipeline, but that is a whole-system statement that names no gate or take station inside the metro, and Warrendale, in Allegheny County, is a market it is evaluating for more capacity, not a named take station.
We also did not count the Shippingport Power Station lateral as new load ahead of the fix. National Fuel Gas Supply Corporation (National Fuel), one of the six interstate pipelines Peoples names, asked the Federal Energy Regulatory Commission (FERC) in August 2025 to approve 205,000 Dth per day of incremental firm transportation to the plant in Beaver County, inside the metro, with construction under way and a target in-service date of fall 2026. Its filing says the plant is not served by a local distribution company, and under the Outlook Scale a load that takes gas directly from an interstate pipeline is context and does not count.37 We show the lateral under 'What is driving new natural gas demand?' as context; no filing shows an effect on either utility's margin.
Columbia Gas PA's contract with Tennessee Gas Pipeline Company, LLC for its Newcastle market (a supply contract that expires) ends on October 31, 2029. It is 7.3% of Columbia Gas PA's firm transportation capacity and 2.5% of its firm design-day demand by our calculation, so we did not count it as a risk.
Three developments would change the assessment: the final order of the Pennsylvania Public Utility Commission (the Commission) in the Peoples rate case and Peoples' next design-day supply plan, including any approved or scheduled capacity addition or any change to its stated margin; whether Columbia Gas PA renews or adds capacity for the Warrendale and Bradford Woods delivery points and replaces the Newcastle contract that expires in October 2029; any data center or power generation agreement signed with a service date and county.
Outlook levels, from least to most concern: Stable, Watch, Elevated, High, Severe. Levels describe the public record of capacity and supply risk; confidence is reported separately. They are qualitative assessments, not forecasts of outages.
Who serves the Pittsburgh area?
Peoples' filed tariff lists 18 counties. Eight of them are the Pittsburgh metro's eight counties, so the serving utility is identified for the whole metro; the filings do not show how much of each county Peoples serves.5
Columbia Gas PA's tariff also lists all eight metro counties, along with more counties across Pennsylvania. It says it is certified to serve in all cities, boroughs and townships in Allegheny, Beaver, Fayette and Washington counties, and lists named municipalities in Armstrong, Butler, Lawrence and Westmoreland counties. A certificate of this kind does not show where Columbia Gas PA has customers, and the filings reviewed give no customer count by county, so its share of the metro is not shown.10
| Where | Counties in Peoples' tariff territory |
|---|---|
| Inside the metro, in both Peoples' and Columbia Gas PA's tariffs (8) | Allegheny, Armstrong, Beaver, Butler, Fayette, Lawrence, Washington, Westmoreland |
| Outside the metro, in Peoples' tariff, system context (10) | Blair, Cambria, Clarion, Clearfield, Greene, Indiana, Jefferson, Mercer, Somerset, Venango |
Counties in Peoples' and Columbia Gas PA's tariff territories, by whether they are in the Pittsburgh metro (OMB delineation). Sources: Peoples tariff, R-2026-3060855; Columbia Gas PA tariff, Gas - Pa. P.U.C. No. 9.5
Every design-day and peak-day figure on this page is for a utility's whole system, Peoples-wide or Columbia Gas PA-wide, and the record does not allocate any of it to the eight metro counties. Peoples plans its supply for the whole system, but it says some areas, such as Grove City, are not physically interconnected with its main facilities, and others, most notably Punxsutawney in Jefferson County (outside the metro), need support from specific interstate delivery points.6
How much spare gas capacity does Pittsburgh have on the coldest day?
In words: what the map shows
- Pipelines labeled: Tennessee Gas Pipeline; Eastern Gas Transmission and Storage; Columbia Gas Transmission; Texas Eastern; Equitrans; National Fuel Gas Supply; Rover Pipeline.
- Underground gas storage fields marked: Donegal; Heard.
- Metro counties outlined (8): Allegheny County; Armstrong County; Beaver County; Butler County; Fayette County; Lawrence County; Washington County; Westmoreland County.
- Cities and towns labeled include: Pittsburgh; Canton; Altoona; Warren; Stow.
- Other gas pipelines in the area are drawn in gray and are not labeled.
- Highways are drawn for orientation. A small state locator map sits in a corner.
Peoples uses a regression model with a design-day average temperature of minus 9°F and, using send-out data for the four years ended May 2024, calculated the total system peak-day design requirement shown in the table.1
| Design-day item | MMcf per day |
|---|---|
| Total system design-day requirement | 1,487.6 |
| Peoples' own supply: local gas 8.9, on-system storage 55.3, interstate delivered gas 1,127.9 | 1,192.1 |
| Delivered by customers that buy from suppliers and are not Priority One (NP-1) | 294.8 |
| Requirement minus the two supply lines (our calculation, illustrative) | 0.7 |
Peoples' design-day requirement and supply, system-wide, from its March 2026 testimony. The last row is our subtraction of the two supply lines (1,192.1 plus 294.8) from the requirement.2
Peoples said its design-day supply assets will be "within 0.73 MMcf of its design day requirements". The testimony does not say whether that is above or below, and a margin this small is below Discovery Energy's 5% thin-margin threshold. It also does not show a need date, a shortfall year or a project.2
Interstate delivered gas comes from Equitrans, Eastern Gas Transmission and Storage, Tennessee Gas Pipeline, Texas Eastern Transmission Company, Columbia Gas Transmission and National Fuel Gas Supply, according to Peoples. The testimony gives one combined figure.3
What is driving new natural gas demand?
We found no data center gas load on the systems of Peoples or Columbia Gas PA in the metro as of October 29, 2026. Peoples said that data center and power generation inquiries have grown recently, that it has added no such project since its last rate case, and that no project has a signed agreement. It proposes no special treatment for these loads in this case and calls any specific request premature, and its own record contains no service date for any new large load.7
Planned load in the metro: the Shippingport Lateral. On August 29, 2025, National Fuel filed a request with FERC, in docket CP25-541-000, to build about 7.26 miles of 24-inch pipeline, a delivery point and a tie-in in Beaver and Mercer counties, to provide 205,000 Dth per day of incremental firm transportation to a new interconnection with the Shippingport Power Station; Beaver County is one of the eight metro counties and Mercer is not.17 National Fuel's project page says pipeline construction began in March 2026 and gives a target in-service date of fall 2026.27
The project's owner, Frontier Group of Companies, says Shippingport Power Station will be a coal-to-gas conversion generating 2,550 MW for the PJM grid, with the National Fuel lateral anticipated to be complete by November 2026 and the conversion complete in the fourth quarter of 2028 or first quarter of 2029; these are owner statements, not filings.18 The same page says the plant will support the PJM grid and on-site data center campus demands, and it names no data center customer or load.28
National Fuel Gas Supply is one of the six interstate pipelines Peoples named, but the filings reviewed do not say that this load draws on gas that Peoples or Columbia Gas PA contracts, and they give no figure comparing it with either utility's design-day margin, so this page states no effect on either margin.3 The record we reviewed includes no state air permit for the plant; the owner's page lists an air permit as "to be submitted."29
Data centers: The one data center link we found is the Shippingport plant in Beaver County, a gas plant that the National Fuel lateral is to serve; the filings reviewed do not show a connection to either utility's system. EIA's September 2026 generator inventory lists no planned natural gas-fired generator in the eight metro counties, and PJM's Transition Cycle 1 Phase III list shows eight Pennsylvania projects, all solar or solar with storage.19
Nearby: System context: in Indiana County, outside the metro, DEP issued a final air plan approval on November 18, 2025 (number in Note 19) for seven combined-cycle and ten simple-cycle gas turbines at the former Homer City station, and EIA's inventory lists planned operation from July 2028; DEP's memo does not name the pipeline that will supply it.30 The FERC notices we found for the pipelines serving the metro since July 31, 2026 concern storage and pipeline abandonments, listed under What's new, and none names a new gas load in the metro.31
Our Federal Register search since January 1, 2025 found twelve FERC notices that name a metro county for pipeline or storage projects (ten are listed in Note 36 and two in Note 24 and Note 25); none names Peoples or Columbia Gas PA, and one names a producer shipper, Range Resources-Appalachia, with no gas load for either utility.36
The other change Peoples describes is on the supply side: conventional-well gas delivered into its systems fell from about 37.1 Bcf in 2020 to about 26.2 Bcf in 2025, and it does not expect a reversal.4
What does the record show for Columbia Gas of Pennsylvania, the metro's second gas utility?
Columbia Gas PA's February 2026 gas supply filing sets firm peak-day capacity against the design-day demand of its Sales and CHOICE customers, which it says are about 76% of its total design-day demand; the rest is delivery service demand, which the table does not compare with capacity.11
| Contract year | Total firm demand (MDth per day) | Net capacity (MDth per day) | Printed "Difference: Capacity less Demand" |
|---|---|---|---|
| 2026-27 | 635.5 | 652.3 | 18.1 |
| 2027-28 | 637.4 | 656.0 | 18.5 |
| 2028-29 | 639.6 | 658.0 | 18.4 |
| 2029-30 | 641.4 | 658.0 | 16.6 |
Columbia Gas PA's firm peak-day capacity and demand by contract year, system-wide, from Exhibit 5, Table 4 of its February 2026 filing, in MDth per day.
Every year in the table is below Discovery Energy's 5% thin-margin threshold. For 2026-27 the printed difference does not match the table's own net capacity less total demand, which is 16.8, and for 2027-28 it is 0.1 above that subtraction (18.6); the table does not explain the differences. The table shows no negative balance.11
Three items are specific to the Pittsburgh area. First, Columbia Gas PA said the market served by its Eastern Gas Transmission and Storage Warrendale delivery point and its Tennessee Gas Pipeline Bradford Woods (also called Pitt Terminal) delivery point needs additional capacity to supply the design day demand. It contracted 10,500 Dth per day of winter-only firm capacity from November 1, 2025 through March 31, 2026, which may be renewed or replaced by other options; the filing does not say what applies for winter 2026-27.12
Bradford Woods Borough is listed under Allegheny County in a municipal population table in Columbia Gas PA's rate filing, and the tariff certifies service in all cities, boroughs and townships in Allegheny County; the U.S. Geological Survey's Geographic Names Information System lists Warrendale as a populated place in Allegheny County, also inside the metro.16
Columbia Gas PA also said it is subject to hourly flow restrictions on the Eastern Gas Transmission and Storage pipeline and continues to evaluate capacity and supply options in its Warrendale and State College markets to address the hourly demand requirements on that pipeline.32
Second, Columbia Gas PA said its two Tennessee Gas Pipeline contracts serve portions of its Newcastle and Pittsburgh area markets, and that it renewed the 16,000 Dth per day contract for the Newcastle market with a new expiration date of October 31, 2029. New Castle is in Lawrence County, inside the metro, and the record shows no replacement after that date.12
Discovery Energy counts an expiring contract as a risk only if it is key: 10% or more of design day, or 10% or more of the utility's firm interstate pipeline capacity. By our calculation from Table 4, 16,000 Dth per day is 2.5% of the 635.5 MDth per day of firm design-day demand (Sales and CHOICE customers plus a maximum-hour adjustment) and 7.3% of the 220.2 MDth per day of firm transportation capacity, net of releases, for 2026-27, and no more than that in any of the four contract years in the table. Both are below 10%, so we did not count the contract as a risk; it stays a development to watch.33
Third, Columbia Gas PA said it received no bids to replace a Texas Eastern contract of 14,835 Dth per day for markets it names as Delmont, Rockwood and Pleasant Gap, and renewed it through October 31, 2026. The record does not locate those markets by county, so we do not apply the item to the Pittsburgh metro.34
What does this mean for business gas costs?
The record gives no dollar or bill figure for capacity costs by customer class, so none is given here. These are the positions and rules on file:
- Peoples asked in March 2026 for a general rate increase of approximately $163.2 million per year.8
- The administrative law judges' recommended decision, which is not a Commission order, would produce an annual revenue increase of about $105.4 million (8.90%) if the Commission agrees, with tariffs effective December 26, 2026, and it recommends adopting the Office of Consumer Advocate's cost-of-service study and its allocation of the increase among the classes; the record we reviewed shows no class-level effect.35
- Under Peoples' tariff, essential-human-needs (Priority One) customers who buy from a supplier get design-day capacity from Peoples and pay for it through a capacity charge per Mcf; non-Priority One transportation customers, generally its largest, acquire their own design-day assets and pay a balancing charge per Mcf.1
The most recent Columbia Gas PA base rate case we reviewed for this page is its 2024 case (the Recommended Decision in the Peoples case cites a later Columbia Gas PA case, Docket No. R-2025-3053499, decided December 9, 2025, which is not among the filings we reviewed): on November 21, 2024 the Commission approved, without modification, a partial settlement allowing $74 million a year in additional base rate revenue, instead of the $124.1 million first requested. This is a 2024 case, system-wide, and this page does not cover the class allocation.13
Who bears the cost of any future capacity addition is not decided in this record.
Who gets gas first in a shortage?
Peoples' tariff Rule 17 covers an emergency in which firm demand exceeds the gas or capacity lawfully available and threatens service to Priority One customers. It allows the company to require each commercial and industrial customer that is not Priority One to reduce consumption, with the reduction set "without regard to priorities of use". The authorized volume is the minimum firm volume needed to prevent damage to plant equipment.9
Takes above authorized consumption during an emergency curtailment are penalized: above 103% and up to 110%, the higher of $10 per Mcf or 110% of the highest-cost gas supply purchased that month; above 110%, the higher of $25 per Mcf or 125%. Tariff exposure, no penalty shown assessed.9
Columbia Gas PA's tariff says that, if time permits, before requiring reductions it will use reasonable efforts to interrupt all interruptible services, issue operational flow and matching orders and alerts, and call for voluntary reductions. If it then curtails commercial and industrial customers that are not Priority 1, the curtailment is made "without regard to priorities of use", does not go below plant protection use, and lasts no more than five business days unless the Commission extends it.14
Winter and market context
NOAA's Climate Prediction Center said on October 15, 2026 that its November 2026 to January 2027 temperature outlook favors above-normal temperatures for regions it calls the Ohio Valley and mid-Atlantic, a discussion that names regions and not Pennsylvania counties.B1 The national inventory, El Niño and liquefied natural gas export figures from EIA and NOAA do not bear on either utility's system, so they sit in a note.23
Winter weather and NOAA's outlook
Heating degree days, a measure of how much heating the weather called for, ran below the 1991-2020 normal at the Pittsburgh International Airport station in the winters of 2023-24 and 2024-25 and slightly above it in 2025-26.20 NOAA's Climate Prediction Center outlook issued October 15, 2026 gives the Pittsburgh area at least a 40% chance of above-normal temperatures for November 2026 to January 2027 and for December 2026 to February 2027.21 The airport is one station standing in for the metro, and NOAA's figures are probabilities for a three-month average, not a forecast of specific days.22
| Winter (November to March) | Heating degree days | 1991-2020 normal | Difference from normal |
|---|---|---|---|
| 2023-24 | 3603 | 4490 | -19.8% |
| 2024-25 | 4123 | 4490 | -8.2% |
| 2025-26 | 4541 | 4490 | +1.1% |
Heating degree days at the Pittsburgh International Airport station, base 65 degrees F, against the 1991-2020 normal. Source: NOAA Regional Climate Centers.
What's new (as of October 29, 2026)
On September 14, 2026 FERC published Columbia Gas Transmission's proposal to abandon three storage fields in Marshall County, West Virginia and Greene and Washington counties, Pennsylvania, which Columbia says are no longer required to meet its current firm service obligations; FERC's environmental assessment is due November 30, 2026.24 On October 20, 2026 FERC published Equitrans' request to plug and abandon one storage well in Greene and Washington counties to meet federal storage-well requirements, with protests due December 14, 2026.25 Parties filed exceptions on October 14, 2026 (made public October 15) and reply exceptions on October 22 and 23, 2026 on the recommended decision in Peoples' rate case, and the docket shows no Commission order yet.26
What should Pittsburgh-area facilities check now?
- Tariffs and charges, through a utility audit. Confirm each account is on the right rate class and tariff, and that riders, demand charges and capacity-related charges are billed correctly. Over 70% of the clients Discovery Energy has audited were billed incorrectly. An audit verifies tariffs and charges and recovers overcharges before winter costs rise.
- Which utility, and which rate class. Confirm whether each site is served by Peoples or Columbia Gas PA, since both list every county in the metro.
- Priority One or not. Confirm whether each account is Priority One or a commercial or industrial account that Rule 17 (Peoples) or Rule 2.3 (Columbia Gas PA) can curtail, and who is responsible for design-day gas on transportation accounts.
- Firm or interruptible, and the terms. Know the notice, authorized-volume and penalty terms in Rule 17 before the first cold snap.
- Backup plans and fuel. Check that alternate-fuel and curtailment plans are current and feasible, and that fuel inventories and resupply arrangements are in place before December.
- Upcoming proceedings. Track the Commission's final order in the Peoples rate case, with new rates proposed for December 26, 2026, and find out whether the 10,500 Dth per day Warrendale and Bradford Woods capacity applies this winter.
What to check in your contracts
| Area | What to check |
|---|---|
| Winter price spikes | Whether the gas is priced on a daily or a monthly index, how large the local basis (the gap between the local price and the national benchmark) has been in cold weather, and how much of your winter use is covered by fixed-price volumes. |
| Delivery constraints | Whether your transportation is firm, what delivery obligations your supplier carries and what happens if it cannot deliver, and what the curtailment provisions say about who is cut first. |
| Operational flow orders | What balancing obligations the contract places on you, and whether penalties that a pipeline or utility charges under an operational flow order are passed through to you. |
| Expansion plans | Where a utility or pipeline plans added capacity, whether the utility has confirmed in writing the incremental hourly and daily capacity available to your site, and from what date. |
Checks for gas supply and transportation contracts. They are questions to put to your supplier or utility, not financial advice.
Frequently asked questions
Will Pittsburgh businesses face natural gas shortages this winter?
The record does not show a shortage, and this page makes no prediction about outages. See 'How much spare gas capacity does Pittsburgh have on the coldest day?' for what Peoples said about its stated design-day margin.
How much natural gas does Peoples need on its coldest day?
Peoples said its total system peak-day design requirement is 1,487.6 MMcf per day, a utility statement for its whole 18-county system, not a Commission finding and not the metro alone. See 'How much spare gas capacity does Pittsburgh have on the coldest day?'
Which pipelines supply Pittsburgh's gas utility?
Peoples named six interstate pipelines: Equitrans, Eastern Gas Transmission and Storage, Tennessee Gas Pipeline, Texas Eastern, Columbia Gas Transmission and National Fuel Gas Supply. It gave one combined design-day figure of 1,127.9 MMcf, so the split is not shown. See 'How much spare gas capacity does Pittsburgh have on the coldest day?'
Who is cut first if Peoples must curtail service?
Under Rule 17 of its tariff, Peoples may require commercial and industrial customers that are not Priority One to reduce consumption, set without regard to priorities of use, to protect Priority One service. Penalties apply to takes above authorized consumption. See 'Who gets gas first in a shortage?'
Is a data center driving gas demand in Pittsburgh?
Peoples said in March 2026 that no data center or power project has a signed agreement. A National Fuel pipeline to the Shippingport Power Station in Beaver County is under construction; the filings do not name a data center customer, though its owner says the plant will support an on-site campus. See 'What is driving new natural gas demand?'
How much spare gas capacity does Columbia Gas PA have on its coldest day?
Exhibit 5 of Columbia Gas PA's February 2026 filing printed a difference of 18.1 MDth per day between net firm capacity and firm design-day demand for 2026-27, below 5% of demand. That is a whole-system utility schedule, not the metro alone. See 'What does the record show for Columbia Gas of Pennsylvania, the metro's second gas utility?'
Related case studies
Discovery Energy publishes gas capacity case studies for other metros, using the same method and outlook scale.
- York natural gas capacity case study (outlook: Elevated)
- Philadelphia area natural gas capacity case study (outlook: Elevated)
- Poughkeepsie-Newburgh area natural gas capacity case study (outlook: High)
- Pennsylvania UGI Gas territory natural gas capacity case study (outlook: High)
- Albany natural gas capacity case study (outlook: Elevated)
All gas capacity ratings by U.S. metro
Background for commercial and industrial energy buyers: Utility cost intelligence
Understand your capacity exposure
Discovery Energy reviews service elections, interruption terms and regulatory proceedings for organizations across the U.S. and Canada, so capacity changes are understood before they reach the bill.
Schedule a reviewWhat this page does not cover
- Columbia Gas PA's customer counts or load by Pittsburgh-area county.
- Whether Columbia Gas PA renewed its Warrendale and Bradford Woods capacity for winter 2026-27, and where Delmont, Rockwood and Pleasant Gap lie in relation to the metro.
- The terms of Columbia Gas PA's 2026 settlement. The Commission's order approves it but does not address capacity.15
- Supply events since 2020, remedies, capacity projects and any change in design-day standard for Peoples. The testimony reviewed names no supply event, remedy or capacity project, and Peoples' earlier rate case is not covered here.
- Whether state air approvals, PJM's 2026 interconnection applications or federal pipeline decisions confirm new gas-fired loads such as Shippingport Power Station, or where Homer City would get its gas. Some of these records are not published in a form we could save.
- Whether any pipeline serving the metro has had a pressure restriction since 2020, or whether any storage withdrawal cap, permit or court delay for a fix, or choice supplier default applies. None showed up in the records this page draws on.
- One holder's share of a pipeline's firm capacity. The pipelines' customer lists are not covered here.
Notes
- Peoples Statement No. 5, Direct Testimony of Edward A. Palombo, Volume VIII, Pa. PUC docket R-2026-3060855, filed March 27, 2026: PDF 114 (design-day temperature, requirement and supply), PDF 115 to 116 (Priority One, NP-1 and cost recovery). Utility statements. The design-day temperature is minus 9°F. ↩
- Same filing, PDF 114 to 116. 1,192.1 plus 294.8 is 1,486.9; 1,487.6 minus 1,486.9 is 0.7 MMcf, or 0.05% of the requirement. Illustrative, our calculation; the testimony's own "within 0.73 MMcf" is the stated figure, and this subtraction of printed lines may not reflect Peoples' own projection of the gap. The two supply lines add to 1,486.9 MMcf, and the 0.7 MMcf gap is 0.05% of the requirement. ↩
- Same filing, PDF 113 (six interstate pipelines) and PDF 114 (1,127.9 MMcf). 1,127.9 divided by 1,487.6 is 75.8%; illustrative. ↩
- Same filing, PDF 117. About 37.1 Bcf in 2020 and about 26.2 Bcf in 2025; 10.9 of 37.1 is 29.4%, shown as 29%. ↩
- Peoples tariff, Gas-Pa. P.U.C. No. 49, Description of Territory (Exhibit KMS-1), Volume VIII PDF 317 to 323: 18 counties, 8 in the metro and 10 outside (our classification of the tariff counties against the metro); county boundaries from OMB Bulletin No. 23-01. Statement No. 1 says 18 counties. The eight metro counties are Allegheny, Armstrong, Beaver, Butler, Fayette, Lawrence, Washington and Westmoreland; Peoples' tariff also lists ten counties outside the metro, and Columbia Gas PA's tariff lists more counties across Pennsylvania. ↩
- Same filing, PDF 113; Punxsutawney is listed under Jefferson County in the tariff, PDF 321. ↩
- Peoples Statement No. 8, Direct Testimony of Luke Ravenstahl, Volume VIII PDF 181 to 182. ↩
- Recommended Decision of the administrative law judges, R-2026-3060855: PDF 27 (finding of fact 1), PDF 386 (ordering paragraph 2), PDF 390 (cost allocation). A recommendation, not a Commission order; exceptions were filed in 2026 and the Commission has not ruled in the record reviewed. ↩
- Peoples tariff Rule 17, Emergency Curtailment, Volume VIII PDF 337 to 340. Tariff exposure, not an assessed penalty. ↩
- Columbia Gas PA tariff, Gas - Pa. P.U.C. No. 9, Description of Territory, as filed in Volume 5 of its March 2024 rate filing (PDF 20 to 23): all eight metro counties are listed (our classification); the tariff says "certified", which is not a customer count. ↩
- Columbia Gas of Pennsylvania, Inc., Docket R-2026-3060762 (gas cost proceeding), 30-day 1307(f) pre-filing dated February 27, 2026, Exhibit No. 5, Table 4 (PDF 171), system-wide, in MDth per day. The printed 2026-27 difference is 18.1; the printed net capacity less printed total demand is 16.8; illustrative, our calculation; the firm transportation subtotal (net of releases) is the Firm Transportation subtotal line of the same table. By our division, 18.1 of 635.5 is 2.8% of demand, and the printed 2029-30 difference is 16.6. ↩
- Same exhibit, Adding or Replacing Capacity and the Texas Eastern and Tennessee Gas Pipeline contracts (PDF 173 and 174); hourly flow restrictions on the Eastern Gas Transmission and Storage pipeline (PDF 172) and the Warrendale and State College markets (PDF 173). ↩
- Joint Petition for Partial Settlement (PDF 7) and Commission Opinion and Order entered November 21, 2024 (PDF 4), Docket R-2024-3046519. ↩
- Columbia Gas PA tariff Rule 2.3.3, Emergency Actions Curtailments, Volume 5 PDF 48. ↩
- Columbia Gas PA: the Commission's order of August 6, 2026 in docket R-2026-3060762 approved without modification a settlement of Columbia Gas PA's purchased gas cost proceeding, and it does not address capacity. ↩
- U.S. Geological Survey, Geographic Names Information System, Domestic Names, Pennsylvania (accessed October 24, 2026), line 13982: Warrendale, Populated Place, Allegheny County (FIPS 42003); Allegheny County is one of the eight metro counties. Bradford Woods Borough, Allegheny County: Columbia Gas of Pennsylvania, Inc., Volume 5 filing file, PDF 344: Exhibit No. 15, Schedule No. 1, Page 7 of 19, a table of 2022 population estimates by county and municipality; the tariff's Description of Territory (PDF 20) states: "certified to serve in all cities, boroughs and townships in Allegheny County." ↩
- Federal Energy Regulatory Commission, Federal Register notice 2025-17571 (90 FR 44056, September 11, 2025), National Fuel Gas Supply Corporation, Docket CP25-541-000 (prior notice request filed August 29, 2025); National Fuel Gas Company, Shippingport Lateral Project page (timeline and target in-service date; accessed October 25, 2026). The notice shows the request, not FERC's action on it; whether FERC authorization has been issued is not shown here, because FERC's eLibrary does not allow automated downloads. ↩
- Frontier Group of Companies, Shippingport Industrial Park page (accessed October 25, 2026): project-owner statements, not filings. ↩
- Pennsylvania Department of Environmental Protection, Homer City Generation Site Redevelopment page and Technical Review Memo for plan approval 32-00457A (November 18, 2025); EIA-860M inventory for September 2026 (Planned sheet, operator-reported planned dates), filtered to the eight metro counties by us; PJM Transition Cycle 1 Phase III project list (Pennsylvania rows; no county column), our calculation. ↩
- NOAA Regional Climate Centers, Applied Climate Information System (ACIS) StnData web service, monthly heating degree days (base 65 degrees F) and 1991-2020 normals, November to March of winters 2023-24 to 2025-26, accessed October 29, 2026: Pittsburgh International Airport (station USW00094823). Sums are our calculation. Heating degree days behind the percentages: 3603 in 2023-24, 4123 in 2024-25 and 4541 in 2025-26, against a 1991-2020 normal of 4490; the 2025-26 winter was 1.1% above normal. ↩
- NOAA Climate Prediction Center, seasonal temperature outlook issued October 15, 2026 (shapefiles from ftp.cpc.ncep.noaa.gov/GIS/us_tempprcpfcst/seastemp_202610.zip), read at the Pittsburgh location. The map gives the favored category and the lower edge of its probability band; NOAA's explanation keeps near-normal at 33.3% and gives the opposite category the rest, so for both periods Pittsburgh has at least a 40% chance of above-normal temperatures, about 33% near-normal and no more than 26.7% below-normal. ↩
- The station is Pittsburgh International Airport; one airport station is not a measurement of the whole metro. The outlook figures are NOAA's probabilities for a three-month average and do not rule out cold days. ↩
- EIA said on October 6, 2026 that it expects U.S. natural gas inventories to enter the winter heating season 2% above the previous five-year average, and its October 2026 Short-Term Energy Outlook says prolonged periods of cold weather could increase withdrawals beyond its forecast (sources A1 and A2). EIA lists U.S. liquefied natural gas gross exports of 15 billion cubic feet per day in 2025, 18 in 2026 and 19 in 2027. NOAA's Climate Prediction Center puts the probability of at least a strong El Niño continuing through January to March 2027 at 80%. These are national and regional facts, not statements about either utility's system, and none of them sets the outlook on this page. ↩
- Federal Register, FERC Notice of Schedule for the Preparation of an Environmental Assessment, Columbia Gas Transmission, LLC, Majorsville-Heard Storage Complex Abandonment Project, document 2026-18772, 91 FR 58111 (September 14, 2026), Docket CP26-527-000 (application filed May 21, 2026), Project Description and Schedule for Environmental Review: Columbia proposes to abandon the Heard, Majorsville Shallow and Majorsville Deep storage fields, 57 injection/withdrawal wells and the Majorsville Compressor Station, and says the facilities are "no longer required to meet Columbia's current firm service obligations." The assessment is due November 30, 2026 and the federal authorization deadline is February 28, 2027. The notice does not say whether Peoples or Columbia Gas PA take service from these fields; accessed October 29, 2026. ↩
- Federal Register, FERC Notice of Request Under Blanket Authorization, Equitrans, L.P., Pratt 3647 Plug and Abandonment Project, document 2026-21441, 91 FR 66330 (October 20, 2026), Docket CP27-4-000 (request filed October 7, 2026): one withdrawal storage well and about 485 feet of six-inch pipeline in Greene and Washington counties, estimated cost about $1.2 million, to meet Pipeline and Hazardous Materials Safety Administration requirements regarding storage wells; protests and interventions are due December 14, 2026. Accessed October 29, 2026. ↩
- Pennsylvania Public Utility Commission, docket page R-2026-3060855, Daily Actions, accessed October 29, 2026: Peoples' exceptions received October 14 and made public October 15, 2026 (exceptions by other parties on the same days; PIOGA's on October 21, 2026), Governor's comments October 16, 2026, and reply exceptions October 22 and 23, 2026. No Commission order appears in the entries. ↩
- National Fuel Gas Company, Shippingport Lateral Project page, timeline ("Commenced pipeline construction"; "Target in-service date"), accessed October 29, 2026; the text is unchanged from the October 25, 2026 copy cited in Note 17. ↩
- Frontier Group of Companies, Shippingport Industrial Park page, project timeline, accessed October 29, 2026, quote: "to support the PJM RTO and on site data center campus demands." An owner statement, not a filing. We class the gas supply as outside the two utilities' systems because it comes by a National Fuel Gas Supply lateral, which the owner's page also says is more than 7.2 miles long and under construction, with a gas receiving yard. ↩
- Frontier Group of Companies, Shippingport Industrial Park page, 2025 timeline entry: "Air Permit to be submitted." Same copy as Note 28. ↩
- Same DEP documents as Note 19 (final plan approval for the Homer City station, Indiana County, November 18, 2025, and the EIA-860M planned operation date of July 2028). ↩
- Federal Register API search of FERC notices published July 31 to October 29, 2026 for Peoples Natural Gas, Shippingport, Pittsburgh, each of the eight metro counties, and the six interstate pipelines Peoples names. No notice names Peoples, Shippingport, Pittsburgh or a metro county for gas; the Allegheny and Beaver county notices are hydropower filings. The pipeline notices read were the two in Note 24 and Note 25, other storage-well and pipeline abandonment filings outside the metro, and routine rate and standards filings. ↩
- Same exhibit as Note 12, hourly flow restrictions (PDF 172) and the Warrendale and State College markets (PDF 173). ↩
- Same table as Note 11 (Exhibit No. 5, Table 4, PDF 171) and Note 12 for the 16,000 Dth per day contract; the 10% measure is Discovery Energy's test for an expiring contract. Our calculation. ↩
- Same exhibit as Note 12, Texas Eastern contract of 14,835 Dth per day (PDF 174). ↩
- Same Recommended Decision as Note 8: PDF 27 (finding of fact 1), PDF 386 (ordering paragraph 2), PDF 390 (cost allocation); a recommendation, not a Commission order. ↩
- Federal Register, Federal Energy Regulatory Commission notices that name Armstrong, Fayette, Washington and Westmoreland Counties, Pennsylvania, found by our search of notices since January 1, 2025 for county names in the singular and the plural; we saved the text of each notice. (a) Eastern Gas Transmission and Storage, Inc.; Notice of Scoping Period Requesting Comments on Environmental Issues for the Proposed Appalachian Reliability Project, document 2025-17408, published September 10, 2025, 90 FR 43597 to 43599 (docket CP25-528-000): scoping notice for Eastern Gas Transmission and Storage's Appalachian Reliability Project, naming Armstrong County for a new receipt point and tap (Roaring Run metering and regulation station) on its TL-474 and LN-19 lines. (b) Eastern Gas Transmission and Storage, Inc.; Notice of Application and Petition for Waiver and Establishing Intervention Deadline, document 2025-15273, published August 12, 2025, 90 FR 38777 to 38779 (docket CP25-528-000, CP25-528-001): Eastern Gas Transmission and Storage's application of July 24, 2025 for the Appalachian Reliability Project (about 3.9 miles of 30-inch pipeline, added compression at two compressor stations and metering changes in Armstrong, Greene and Westmoreland Counties, Pennsylvania, and Monroe County, Ohio) to provide about 550,000 Dth per day of firm transportation, with a petition for waiver. (c) Eastern Gas Transmission and Storage, Inc; Notice of Schedule for the Preparation of an Environmental Assessment for the Appalachian Reliability Project, document 2025-20698, published November 24, 2025, 90 FR 52952 (docket CP25-528-000): notice of the schedule for the environmental assessment of the Appalachian Reliability Project (assessment due February 27, 2026; federal authorization decision deadline May 28, 2026). (d) Eastern Gas Transmission and Storage, Inc.; Notice of Availability of the Environmental Assessment for the Proposed Appalachian Reliability Project, document 2026-04268, published March 4, 2026, 91 FR 10591 to 10592 (docket CP25-528-000): notice of availability of the environmental assessment of the Appalachian Reliability Project, with comments due March 30, 2026. (e) Eastern Gas Transmission and Storage, Inc.; Notice of Request Under Blanket Authorization and Establishing Intervention and Protest Deadline, document 2025-23947, published December 30, 2025, 90 FR 61134 to 61135 (docket CP26-37-000): Eastern Gas Transmission and Storage's prior notice request of December 10, 2025 to build one new horizontal storage injection/withdrawal well, about 405 feet of pipeline and water tanks (North Summit Well Installation Project) in Fayette County, at an estimated cost of $10,615,000, which the company says will optimize the North Summit Field and maintain its storage services for existing customers. (f) Rover Pipeline LLC; Notice of Schedule for the Preparation of an Environmental Assessment for the Rover-Bulger Delivery Meter Station Project, document 2024-31649, published January 6, 2025, 90 FR 636 to 637 (docket CP25-12-000): notice of the environmental assessment schedule for Rover Pipeline's application of October 31, 2024 to expand its Bulger Compressor Station in Washington County (published under the title Rover-Bulger Delivery Meter Station Project; the text calls it the Rover-Bulger Compressor Station and Harmon Creek Meter Station Expansion Project), to ensure delivery of Range Resources-Appalachia's requested transportation quantities at the required pressures. (g) Rover Pipeline LLC; Supplemental Notice of Scoping Period Requesting Comments on Environmental Issues for the Proposed Rover-Bulger Compressor Station and Harmon Creek Meter Station Expansion Project, document 2025-01427, published January 22, 2025, 90 FR 7692 to 7694 (docket CP25-12-000): supplemental scoping notice for the same Rover Bulger Compressor Station and Harmon Creek Meter Station expansion, naming Smith Township, Washington County, and one new 2,750-horsepower compressor. (h) Columbia Gas Transmission, LLC; Notice of Request for Extension of Time, document 2026-02873, published February 13, 2026, 91 FR 6839 to 6840 (docket CP25-35-001): Columbia Gas Transmission's request of February 2, 2026 for an extension of time, until May 1, 2026, to complete one new injection/withdrawal well and connecting pipeline at its Donegal Storage Field in Washington County. (i) Columbia Gas Transmission, LLC; Notice of Request Under Blanket Authorization and Establishing Intervention and Protest Deadline, document 2026-09066, published May 7, 2026, 91 FR 24861 to 24863 (docket CP26-291-000): Columbia Gas Transmission's prior notice request of April 24, 2026 for its Line 9260 and Line 9230 Make Piggable Project: an in-line inspection launcher and receiver and changes to storage well pipelines at thirty-four points in the Donegal Storage Field, Washington County. (j) Columbia Gas Transmission, LLC; Notice of Scoping Period Requesting Comments on Environmental Issues for the Proposed Majorsville-Heard Storage Complex Abandonment Project, document 2026-13600, published July 6, 2026, 91 FR 41007 to 41009 (docket CP26-527-000): scoping notice for Columbia's Majorsville-Heard Storage Complex Abandonment Project, naming Washington County; the schedule notice for the same project is in Note 24. None names Peoples, Columbia Gas PA, a shipper or a gas load. The Appalachian Reliability Project notices say it would provide about 550,000 Dth per day of firm transportation to points on the interstate grid in Ohio and Pennsylvania; they do not name the customers. We read the notices but not the underlying applications. ↩
- National Fuel Gas Supply Corporation, Prior Notice Application, Shippingport Lateral Project, Volume 1 Public Information (filed at FERC August 29, 2025; docket CP25-541-000), page 9, Part IV.B, delivery point: "Currently the end-user is not served by a local distribution company". A company filing. The Outlook Scale treats a load that connects directly to an interstate pipeline as context that is never counted. ↩
Market and weather sources
Public web sources, as of October 25, 2026. They are context, separate from the regulatory record cited in the Notes. The Climate Prediction Center issues its seasonal outlook once each month near mid-month; this section is refreshed on the publication date.
- A1. U.S. Energy Information Administration, press release, "EIA expects a mixed picture for winter fuel costs this year," October 6, 2026. Link
- A2. U.S. Energy Information Administration, Short-Term Energy Outlook, October 2026 (natural gas storage). Link
- B1. NOAA Climate Prediction Center, Prognostic Discussion for Long-Lead Seasonal Outlooks, issued October 15, 2026. Link ↩
Sources
- Pennsylvania Public Utility Commission, docket R-2026-3060762, Columbia Gas of Pennsylvania, Inc.: 30-day 1307(f) pre-filing and supporting information, Exhibit No. 5. Link
- Pennsylvania Public Utility Commission, docket R-2024-3046519, Columbia Gas of Pennsylvania, Inc.: Volume 5 (tariff Pa. P.U.C. No. 9), Joint Petition for Settlement and Opinion and Order. Link, Link, Link
- Pennsylvania Public Utility Commission, docket R-2026-3060855, Peoples Natural Gas Company LLC base rate case: Volume VIII, direct testimony Statements 1 to 14, with tariff Gas-Pa. P.U.C. No. 49. Link
- Pennsylvania Public Utility Commission, docket R-2026-3060855, Recommended Decision. Link
- Pennsylvania Public Utility Commission, docket page for R-2026-3060855. Link
- U.S. Geological Survey, U.S. Board on Geographic Names, Geographic Names Information System, Domestic Names, Pennsylvania. Link
- Office of Management and Budget, OMB Bulletin No. 23-01, Revised Delineations of Metropolitan Statistical Areas, Micropolitan Statistical Areas, and Combined Statistical Areas, July 21, 2023.
- Federal Energy Regulatory Commission, Federal Register notice 2025-17571, National Fuel Gas Supply Corporation, Docket CP25-541-000. Link
- National Fuel Gas Company, Shippingport Lateral Project. Link
- Frontier Group of Companies, Shippingport Industrial Park. Link
- Pennsylvania Department of Environmental Protection, Homer City Generation Site Redevelopment. Link
- U.S. Energy Information Administration, EIA-860M Preliminary Monthly Electric Generator Inventory, September 2026. Link
- PJM Interconnection, Transition Cycle 1 Phase III Executive Summary. Link
- Federal Register (FERC), Columbia Gas Transmission, LLC; Notice of Schedule for the Preparation of an Environmental Assessment for the Majorsville-Heard Storage Complex Abandonment Project, document 2026-18772. Link
- Federal Register (FERC), Equitrans, L.P.; Notice of Request Under Blanket Authorization and Establishing Intervention and Protest Deadline, document 2026-21441. Link
- Pennsylvania Public Utility Commission, Order entered August 6, 2026, Docket R-2026-3060762, Columbia Gas of Pennsylvania, Inc. (1307(f) gas cost proceeding). Link
- Federal Register API (FERC notices), Search log: FERC documents published 2026-07-31 to 2026-10-29 for Peoples Natural Gas, Shippingport, six pipelines serving the metro, eight metro counties and Pittsburgh. Link
- NOAA Regional Climate Centers (ACIS web service), Monthly heating degree days base 65F and 1991-2020 normals, station USW00094823. Link
- Federal Register (FERC notice), Eastern Gas Transmission and Storage, Inc.; Notice of Scoping Period Requesting Comments on Environmental Issues for the Proposed Appalachian Reliability Project (FR 2025-17408, September 10, 2025). Link
- Federal Register (FERC notice), Eastern Gas Transmission and Storage, Inc.; Notice of Application and Petition for Waiver and Establishing Intervention Deadline (FR 2025-15273, August 12, 2025). Link
- Federal Register (FERC notice), Eastern Gas Transmission and Storage, Inc; Notice of Schedule for the Preparation of an Environmental Assessment for the Appalachian Reliability Project (FR 2025-20698, November 24, 2025). Link
- Federal Register (FERC notice), Eastern Gas Transmission and Storage, Inc.; Notice of Availability of the Environmental Assessment for the Proposed Appalachian Reliability Project (FR 2026-04268, March 4, 2026). Link
- Federal Register (FERC notice), Eastern Gas Transmission and Storage, Inc.; Notice of Request Under Blanket Authorization and Establishing Intervention and Protest Deadline (FR 2025-23947, December 30, 2025). Link
- Federal Register (FERC notice), Rover Pipeline LLC; Notice of Schedule for the Preparation of an Environmental Assessment for the Rover-Bulger Delivery Meter Station Project (FR 2024-31649, January 6, 2025). Link
- Federal Register (FERC notice), Rover Pipeline LLC; Supplemental Notice of Scoping Period Requesting Comments on Environmental Issues for the Proposed Rover-Bulger Compressor Station and Harmon Creek Meter Station Expansion Project (FR 2025-01427, January 22, 2025). Link
- Federal Register (FERC notice), Columbia Gas Transmission, LLC; Notice of Request for Extension of Time (FR 2026-02873, February 13, 2026). Link
- Federal Register (FERC notice), Columbia Gas Transmission, LLC; Notice of Request Under Blanket Authorization and Establishing Intervention and Protest Deadline (FR 2026-09066, May 7, 2026). Link
- Federal Register (FERC notice), Columbia Gas Transmission, LLC; Notice of Scoping Period Requesting Comments on Environmental Issues for the Proposed Majorsville-Heard Storage Complex Abandonment Project (FR 2026-13600, July 6, 2026). Link
Corrected November 9, 2026: We said Columbia Gas PA's most recent base rate case in the record was its 2024 case; a later case decided December 9, 2025 is cited in the Peoples Recommended Decision and is not among the filings we reviewed, so the page now says the 2024 case is the most recent one we read. We also corrected where the Bradford Woods Allegheny County listing comes from (a population table, with the tariff certifying service in all of Allegheny County) and described the 635.5 MDth per day figure as firm demand of Sales and CHOICE customers, not total design-day demand. The outlook was High on two counted risks, the Shippingport lateral and the Columbia Gas PA flow restriction. We no longer count either: the National Fuel filing says no local distribution company serves the Shippingport plant, and the flow restriction is a whole-system statement that names no gate or take station in the metro. With no counted risk the outlook is Elevated, on the thin margins in both utilities' filings; confidence is unchanged at Medium.