New York natural gas case study, Albany, New York. November 2026
Albany-area natural gas capacity: pressure on the Albany Loop, and a paused backup project
Staff's consultant says National Grid's models show Albany Loop pressures dropping after winter 2026-27. The planned fix, ETS2, is paused after National Grid accepted East Gate city gate peaking; the record does not show whether that resolves the need.
Metro used: the Albany-Schenectady-Troy, NY metropolitan statistical area, as delineated in OMB Bulletin No. 23-01 (July 21, 2023). The gas utility identified in the record is Niagara Mohawk Power Corporation d/b/a National Grid (National Grid), whose East Gate division serves the Albany, Troy and Schenectady areas. Whether any gas utility serves Schoharie County, or whether New York State Electric & Gas Corporation serves any part of the metro, is not shown. Upstate-wide figures below are labeled system context.6
Key takeaways
- Staff's consultant, using National Grid's hydraulic models, said that absent reinforcement the Albany Loop may not deliver adequate gas supplies on a design day.1
- On National Grid's design day forecast, the consultant said the loop will not give adequate deliveries to its regulator stations without ETS2 by the 2027-28 winter.2
- The Commission's September 2025 order summarized the plan as needing ETS2 for winter 2027/28, with operation then scheduled for winter 2026/27; the 2026 update says the project is paused.3
- National Grid's 2026 update lists a forecasted East Gate supply shortfall; the East Gate division serves the Albany, Troy and Schenectady areas, inside the metro. Its plan says no gaps appear under two other scenarios.4
- National Grid said that during Winter Storm Fern in January 2026 interruptible customers were activated, firm service was reliable and the peak day was warmer than design day.5
- The consultant cited the GlobalFoundries expansion as potential East Gate demand growth, with no volume or service date.7
What is the outlook for Albany gas capacity through 2029?
Discovery Energy rates the outlook for Albany-area natural gas capacity through 2029 as Elevated (confidence: Medium): Staff's consultant said National Grid's models show Albany Loop delivery pressures dropping after winter 2026-27. The planned fix, a second compressed natural gas site near Troy known as ETS2, is paused, and the record we reviewed shows no approved substitute. National Grid has accepted 10,000 Dth/day of East Gate city gate peaking from December 2027 and proposed a reliability assessment, but the record does not show whether either one resolves the need. Documented risk factors: none beyond the facts stated above. Three developments would change the assessment: National Grid's decision on ETS2 or an alternative for the East Gate and the outcome of the East Gate Reliability Assessment; the 2027 annual long-term plan update, including any change to the East Gate city gate agreement running through March 2033; a signed gas load expansion with a service date, such as the GlobalFoundries expansion.
Outlook levels, from least to most concern: Stable, Watch, Elevated, High, Severe. Levels describe the public record of capacity and supply risk; confidence is reported separately. They are qualitative assessments, not forecasts of outages.
Who serves the Albany area?
National Grid supplies gas in parts of Albany, Rensselaer, Saratoga and Schenectady counties, and the consultant does not list Schoharie County; how much of each county National Grid serves is not shown.6 Its East Gate division serves the Albany, Troy and Schenectady areas, and its Albany Loop pipeline serves significant demand in Albany and Troy.
The upstate figures below cover National Grid's whole upstate system, not Albany alone. Whether the East Gate reaches places outside the five metro counties is not shown. The West Gate and the Empire Pipeline sit outside the area, and the record says new Empire capacity would not help the East Gate.
| Where | Item in the record |
|---|---|
| Inside the metro | East Gate (Albany Loop, Troy, Schenectady, Moreau) |
| Outside the metro, system context | West Gate (Syracuse, Utica, Watertown); Empire Pipeline capacity; Upstate-wide 2030/31 gap |
| Unclear | Schoharie County; any NYSEG territory |
National Grid's upstate divisions and the record items tied to them, by whether they fall inside the Albany metro (OMB delineation). Sources: DPS Staff consultant's final report, Sections 1.1 and 4.4.1.6
Has the Albany area had gas supply problems since 2020?
The record we reviewed documents one event. In Winter Storm Fern, National Grid said non-firm interruptible customers and demand response were activated multiple times in upstate and downstate New York to protect firm customers.5 The record shows no firm-customer curtailment, and the filings we reviewed do not cover events from 2020 to 2025.
How much spare gas capacity does Albany have on the coldest day?
In words: what the map shows
- Pipelines labeled: Tennessee Gas Pipeline; Eastern Gas Transmission and Storage; Iroquois Gas Transmission.
- Compressor stations marked: Wright.
- Gas-fired power plants marked: Albany Medical Ctr Cogen Plant; Bethlehem Energy Center.
- Metro counties outlined (5): Albany County; Rensselaer County; Saratoga County; Schenectady County; Schoharie County.
- Cities and towns labeled include: Springfield; Schenectady; Utica; Chicopee; Troy; Pittsfield; Amherst Town; Torrington.
- Other gas pipelines in the area are drawn in gray and are not labeled.
- Highways are drawn for orientation. A small state locator map sits in a corner.
National Grid models upstate gas requirements on a design day, a very cold day used to size the system, with an average temperature of minus 10 degrees Fahrenheit at the Albany and Syracuse airports.8
For the East Gate, the record gives a pressure test rather than a supply-and-demand balance. The consultant's reading of the company's models is that the Albany Loop's delivery pressures decline after winter 2026-27 and that deliveries to downstream regulator stations then become insufficient absent reinforcement.1
System context: for its whole Upstate system, National Grid's Reference Case projects a gap of 0.06 MDt/day in 2030/31, attributed to growing East Gate demand. The consultant found no Upstate shortfall at any point in the study period under National Grid's Clean Energy Vision and Accelerated Electrification forecasts.4
What is driving new natural gas demand?
We found no documented new gas load with a service date in the five metro counties. The one possible exception, the Wright entry described below, is an electric load at a pipeline compressor station and we did not count it as a gas load.
The consultant says GlobalFoundries and Micron have published plans to expand operations that could affect their gas demand, and cites potential demand growth from the GlobalFoundries expansion in discussing the East Gate. The record gives no volume or service date, and does not locate either plant.7
EIA's September 2026 generator inventory lists no planned natural gas-fired generator in the five counties.9 Our Federal Register search since January 1, 2025 found five FERC notices that name Schoharie County, all on the Constitution Pipeline and Iroquois's Wright Interconnect project; four are petitions to reissue the certificates, a scoping notice and a review schedule.21 The fifth, of August 26, 2026, is FERC's environmental assessment, which adds 22,000 horsepower of compression at the Wright Compressor Station and upgrades the delivery meter to the Tennessee Gas Pipeline.13 These are pipeline supply projects, not a gas load, and none of the five notices ties them to National Grid's East Gate.
The New York Independent System Operator (NYISO) queue of September 30, 2026 has one natural gas entry in the metro, a request about the capacity rights of the Bethlehem Energy Center in Albany County that states no megawatts and shows no new gas supply or service date.10
The load list also has an entry named IGTS Wright EMD Compressor in Schoharie County, 14.38 MW, with initial backfeed proposed for November 2028; the entry is an electric load at a pipeline compressor station, not a gas load, and it does not say what it changes on the pipeline.10 EIA lists a 4.3 MW natural gas turbine at the Albany Medical Center cogeneration plant in Albany County as retired in October 2024, which ended a gas load.12
Data centers: As of October 29, 2026, we found no data center gas load in the five counties. NYISO's load list has one data center entry, the Kenwood Tech Center in Albany County, at 180 MW of electric load with initial backfeed proposed for December 2028; it records electric load and does not say whether natural gas serves it.11
Nearby: The filings by Eastern Gas Transmission and Storage, which supplies the Albany Loop, in notices we reviewed since August 2026 are rate, compliance and annual adjustment filings, and none names a county or a new load.19
Are upgrades arriving in time?
For the East Gate, the plan changed between filings. The Commission's September 2025 order summarized National Grid's plan: ETS2, a second compressed natural gas site near Troy, was needed for winter 2027/28 and scheduled for winter 2026/27. In its 2026 annual update, National Grid said it accepted 10,000 Dth/day of city gate peaking at its East Gate from December 2027 through March 2033, extending its current agreement for six years, and with it paused construction of the second site to investigate possible alternatives. The same update lists a forecasted East Gate supply shortfall and localized gate imbalances among its constraints.3
National Grid proposed an East Gate Reliability Assessment to determine how to alleviate the need for additional supply, and the 2025 Niagara Mohawk rate order permits it to defer up to $7.7 million of the assessment's costs if the Commission directs it in another proceeding. The record we reviewed does not show that the assessment has been ordered.3
The record does not show whether a city gate peaking agreement of this size addresses the Albany Loop pressure need, so whether upgrades arrive in time is not shown.
What does this mean for business gas costs?
The record gives no dollar or bill figure for capacity costs by customer class, so none is given here. The only cost item on file is the deferral allowance above, and who bears the cost of any future East Gate capacity addition is not decided in this record.3
Winter and market context
NOAA's Climate Prediction Center said on October 15, 2026 that its November 2026 to January 2027 outlook gives the highest odds of warmer than normal conditions to, among other areas, the Great Lakes and interior Northeast, a discussion that names regions and not New York counties.B1 The national inventory, El Nino and liquefied natural gas export figures from EIA and NOAA do not bear on National Grid's system, so they sit in a note.16
Winter weather and NOAA's outlook
Heating degree days, a measure of how much heating the weather called for, ran below the 1991-2020 normal at the Albany International Airport station in the winters of 2023-24 and 2024-25 and above it in 2025-26.17 NOAA's Climate Prediction Center outlook issued October 15, 2026 gives the Albany area at least a 40% chance of above-normal temperatures for November 2026 to January 2027 and at least 50% for December 2026 to February 2027.18 The airport is one station standing in for the metro, and NOAA's figures are probabilities for a three-month average, not a forecast of specific days.20
| Winter (November to March) | Heating degree days | 1991-2020 normal | Difference from normal |
|---|---|---|---|
| 2023-24 | 4310 | 5046 | -14.6% |
| 2024-25 | 4866 | 5046 | -3.6% |
| 2025-26 | 5325 | 5046 | +5.5% |
Heating degree days at the Albany International Airport station, base 65 degrees F, against the 1991-2020 normal. Source: NOAA Regional Climate Centers.
What's new (as of October 29, 2026)
On August 26, 2026 FERC published its environmental assessment of the Constitution Pipeline and Iroquois's Wright Interconnect project in Schoharie County, and the notice does not tie it to National Grid's East Gate.13 FERC's schedule notice of June 24, 2026 lists November 19, 2026 as the federal authorization decision deadline for the projects.14 The newest filing on the Commission's list for National Grid's long-term gas plan case is dated May 15, 2026, so we found no new filing on the East Gate in the past 90 days.15
What should Albany-area facilities check now?
- Tariffs and charges, through a utility audit. Confirm each account is on the right rate class and tariff, and that riders, demand charges and capacity-related charges are billed correctly. Over 70% of the clients Discovery Energy has audited were billed incorrectly. An audit verifies tariffs and charges and recovers overcharges before winter costs rise.
- Which utility, and which service class. Confirm whether each site is served by National Grid and whether it takes firm or interruptible service, since interruptible customers were activated in January 2026.
- Standby and firm-capacity terms. Know the terms of any standby or large-customer service election, since National Grid said a supply-demand imbalance could be worsened by expanding standby service for large industrial customers.
- Backup plans and fuel. Check that alternate-fuel and curtailment plans are current and feasible, and that fuel inventories and resupply arrangements are in place before December.
- Upcoming proceedings. Track National Grid's decision on the East Gate, its 2027 annual update, and any order on the East Gate Reliability Assessment.
What to check in your contracts
| Area | What to check |
|---|---|
| Winter price spikes | Whether the gas is priced on a daily or a monthly index, how large the local basis (the gap between the local price and the national benchmark) has been in cold weather, and how much of your winter use is covered by fixed-price volumes. |
| Delivery constraints | Whether your transportation is firm, what delivery obligations your supplier carries and what happens if it cannot deliver, and what the curtailment provisions say about who is cut first. |
| Operational flow orders | What balancing obligations the contract places on you, and whether penalties that a pipeline or utility charges under an operational flow order are passed through to you. |
| Expansion plans | Where a utility or pipeline plans added capacity, whether the utility has confirmed in writing the incremental hourly and daily capacity available to your site, and from what date. |
Checks for gas supply and transportation contracts. They are questions to put to your supplier or utility, not financial advice.
Frequently asked questions
Will Albany businesses face natural gas shortages this winter?
The record does not show a shortage, and this page makes no prediction about outages. See 'How much spare gas capacity does Albany have on the coldest day?'
What is the Albany Loop?
It is the pipeline in the eastern part of National Grid's East Gate system that serves significant customer demand in the Albany and Troy areas and receives gas from Eastern Gas Transmission and Storage and Tennessee Gas Pipeline. See 'Who serves the Albany area?'
Is the second gas storage site near Troy still planned?
National Grid said in its 2026 annual update that the second compressed natural gas site project is currently paused while it investigates alternatives. See 'Are upgrades arriving in time?'
Is there a gas supply gap for upstate New York?
National Grid's Reference Case projects a gap for its whole Upstate system in 2030/31, a company projection and not a Commission finding. See 'How much spare gas capacity does Albany have on the coldest day?'
Is a data center or chip plant driving gas demand near Albany?
The consultant cited potential GlobalFoundries demand growth, with no volume or service date. We found no data center gas load; NYISO's one data center entry is an electric load. See 'What is driving new natural gas demand?'
Related case studies
Discovery Energy publishes gas capacity case studies for other metros, using the same method and outlook scale.
- Pennsylvania UGI Gas territory natural gas capacity case study (outlook: High)
- Brooklyn, Queens, Staten Island and Long Island natural gas capacity case study (outlook: Elevated)
- Boston natural gas capacity case study (outlook: High)
- Rochester natural gas capacity case study (outlook: Elevated)
- New York City and Westchester natural gas capacity case study (outlook: Elevated)
All gas capacity ratings by U.S. metro
Background for commercial and industrial energy buyers: Utility cost intelligence
Understand your capacity exposure
Discovery Energy reviews service elections, interruption terms and regulatory proceedings for organizations across the U.S. and Canada, so capacity changes are understood before they reach the bill.
Schedule a reviewWhat this page does not cover
- Who would be cut first if National Grid had to curtail gas. The tariff's curtailment and interruption priorities are not shown in the record we used.
- How much of any East Gate cost would fall on each customer class. The rate case that would settle this is not covered here.
- Whether the East Gate city gate agreement resolves the Albany Loop pressure need. The record we reviewed does not say.
- Whether any other gas utility serves part of the metro. We can't say whether one serves Schoharie County or any New York State Electric & Gas territory in the metro.
- Which new large gas users have asked to be connected. Each utility's own list of large-load requests and county economic development filings were not available to us, so a project could exist that this page does not show.
Notes
- Final Report of National Grid's Final Long-Term Gas Plan, prepared by PA Consulting for Department of Public Service Staff, Case 24-G-0248, Section 4.4.1: PDF 68 and 69 (Albany Loop pressures), PDF 14 (counties). Staff analysis of the company's models. ↩
- Same report, PDF 68. ETS2 and the three citygates. ↩
- Commission Order Regarding Long-Term Natural Gas Plan and Requiring Further Actions, Case 24-G-0248 (session September 18, 2025), PDF 15 and 16 (company's plan as summarized by the Commission; not a Commission finding); National Grid Annual Long-Term Plan Update Report (2026), PDF 22 and 24; consultant's report PDF 52. Utility statements. ↩
- Same order, PDF 15 and 16; National Grid 2026 annual update, PDF 24; consultant's report PDF 58. The Upstate gap is a whole-system figure (system context). ↩
- National Grid 2026 annual update, Sections 4.6 and 5.1, PDF 23 and 24. Utility statement. ↩
- Consultant's report PDF 14, 68. The metro's five counties are Albany, Rensselaer, Saratoga, Schenectady and Schoharie, from the OMB delineation. The match of Albany, Troy and Schenectady to counties is general geography, not a quotation. ↩
- Consultant's report PDF 27 and 69. ↩
- National Grid LTP Demand Forecast Update and Report, PDF 11. ↩
- EIA-860M inventory for September 2026 (Planned sheet, operator-reported planned dates), filtered to Albany, Rensselaer, Saratoga, Schenectady and Schoharie counties by us, and a Federal Register search of FERC notices since January 1, 2025 by county phrase, both our own calculation. A notice that spells a place differently would be missed, and that first search missed the August 26, 2026 notice in note 13, which lists "Schoharie Counties" in the plural; a later search that also reads the plural form found the four other notices in note 21. ↩
- New York Independent System Operator, Interconnection Queue (September 30, 2026), sheets Interconnection Queue, Cluster Projects and Load Projects, filtered by county by us (our list names each entry). The entry for the Bethlehem Energy Center is a capacity-rights-only request (queue CR24-1003); the load entries are electric loads. ↩
- New York Independent System Operator, Interconnection Queue (September 30, 2026), Load Projects sheet, queue number 1754: Kenwood Tech Center, EKG Group LLC, Albany County, end use data center, 180 MW peak load, proposed initial backfeed December 2028. A newer queue was not checked. ↩
- U.S. Energy Information Administration, EIA-860M, September 2026, Retired sheet, Albany Medical Center, Albany Medical Ctr Cogen Plant (plant 59219), natural gas combustion turbine GTG1A, 4.3 MW, retired October 2024. ↩
- Federal Register, Federal Energy Regulatory Commission, Notice of Availability of the Environmental Assessment for the Proposed Constitution Pipeline and Wright Interconnect Projects, document 2026-17399, published August 26, 2026, pages 55089 and 55090 (dockets CP13-499-006 and CP13-502-003). The notice describes about 125 miles of 30-inch pipeline in Susquehanna County, Pennsylvania and Broome, Chenango, Delaware and Schoharie counties, New York, and 22,000 horsepower of added compression at the Wright Compressor Station in Schoharie County. It names no shipper or volume. An undated Iroquois brochure describes up to 650,000 Dth/day of capacity and a proposed in-service date of May 2028; we cite it only as the company's description. ↩
- Federal Energy Regulatory Commission, Notice of Schedule for the Preparation of an Environmental Assessment, Constitution Pipeline and Wright Interconnect Projects, June 24, 2026 (accession 20260624-3023; our copy is the Word file from FERC's eLibrary, accessed October 30, 2026, which has no page numbers), "Schedule for Environmental Review" table ("90-day Federal Authorization Decision Deadline November 19, 2026"; "Issuance of EA August 21, 2026") and opening paragraph (petitions filed December 19, 2025 and February 13, 2026 seeking reissuance of certificates; certificates first issued December 2, 2014 and the projects were not completed). A scheduling date, not a decision. ↩
- New York State Department of Public Service, document list for Case 24-G-0248 (233 filings), accessed October 29, 2026; the newest filing, National Grid's Annual Long-Term Plan Update Report (2026), carries the filing date 05/15/2026 (the date is our reading of the list). ↩
- EIA said on October 6, 2026 that it expects U.S. natural gas inventories to enter the winter heating season 2% above the previous five-year average, and its October 2026 Short-Term Energy Outlook says prolonged periods of cold weather could increase withdrawals beyond its forecast (sources A1 and A2). EIA lists U.S. liquefied natural gas gross exports of 15 billion cubic feet per day in 2025, 18 in 2026 and 19 in 2027. NOAA's Climate Prediction Center puts the probability of at least a strong El Nino continuing through January to March 2027 at 80%. These are national and regional facts, not statements about National Grid's system. ↩
- NOAA Regional Climate Centers, Applied Climate Information System (ACIS) StnData web service, monthly heating degree days (base 65 degrees F) and 1991-2020 normals, November to March of winters 2023-24 to 2025-26, accessed October 29, 2026: Albany International Airport (station USW00014735). Sums are our calculation. Heating degree days behind the percentages: 4310 in 2023-24, 4866 in 2024-25 and 5325 in 2025-26, against a 1991-2020 normal of 5046. ↩
- NOAA Climate Prediction Center, seasonal temperature outlook issued October 15, 2026 (shapefiles from ftp.cpc.ncep.noaa.gov/GIS/us_tempprcpfcst/seastemp_202610.zip), read at the Albany location. The map gives the favored category and the lower edge of its probability band; NOAA's explanation keeps near-normal at 33.3% and gives the opposite category the rest, so the outlook is at least 40% above-normal, about 33% near-normal and no more than 27% below-normal for November 2026 to January 2027, and at least 50%, about 33% and no more than 17% for December 2026 to February 2027. ↩
- Federal Register, FERC Combined Notices of Filings: document 2026-15640 (August 3, 2026; docket RP26-992-000, negotiated agreements), 2026-16323 (August 11, 2026; RP26-939-002, 2026 rate case compliance filing), 2026-17846 (September 1, 2026; RP26-1112-000, NAESB standards compliance), 2026-19662 (September 25, 2026; RP26-1266-000, negotiated agreements) and 2026-20106 (October 1, 2026; RP26-1277-000 and RP26-1278-000, annual EPCA and TCRA adjustments), all filed by Eastern Gas Transmission and Storage, Inc. We did not read Tennessee Gas Pipeline or Iroquois filings for New York items. ↩
- The station is Albany International Airport; one airport station is not a measurement of the whole metro. The outlook figures are NOAA's probabilities for a three-month average and do not rule out cold days. ↩
- Federal Register, Federal Energy Regulatory Commission notices that name Schoharie County, New York, found by our search of notices since January 1, 2025 for county names in the singular and the plural; we saved the text of each notice. (a) Constitution Pipeline Company, LLC; Notice of Petition and Establishing Intervention Deadline, document 2026-00481, published January 13, 2026, 91 FR 1311 to 1313 (docket CP13-499-006, CP18-5-004): Constitution Pipeline Company's petition of December 19, 2025 to reissue the certificate for the Constitution Pipeline, about 125 miles of 30-inch pipeline from Susquehanna County, Pennsylvania through four New York counties including Schoharie, with the Westfall Road meter station at Iroquois's Wright Compressor Station in Schoharie County; the notice says the project is designed to provide 650,000 dekatherms (Dth) per day of firm service from Pennsylvania production areas to markets in New York and New England. (b) Iroquois Gas Transmission System, L.P.; Notice of Petition and Establishing Intervention Deadline, document 2026-03948, published February 27, 2026, 91 FR 9847 to 9849 (docket CP13-502-003): Iroquois's petition of February 13, 2026 to reissue the certificate for its Wright Interconnect Project, a new 21,800 horsepower transfer compressor station, changes to the Wright Compressor Station and metering, all in Schoharie County, creating 650,000 Dth per day of service that Iroquois would lease to Constitution. (c) Constitution Pipeline Company, LLC; Iroquois Gas Transmission System, L.P.: Notice of Scoping Period Requesting Comments on Environmental Issues for the Proposed Constitution Pipeline and Wright Interconnect Projects, document 2026-06767, published April 8, 2026, 91 FR 17798 to 17800 (docket CP13-499-006, CP13-502-003): notice opening the environmental scoping period for reissuing both certificates, naming Schoharie County among the New York counties and describing up to 650,000 Dth per day of added transportation capacity to markets in New York and New England. (d) Constitution Pipeline Company, LLC; Iroquois Gas Transmission System, L.P.: Notice of Schedule for the Preparation of an Environmental Assessment for the Constitution Pipeline and Wright Interconnect Projects, document 2026-13088, published June 29, 2026, 91 FR 39091 (docket CP13-499-006; CP13-502-003): notice of the schedule for the environmental assessment of both projects (assessment due August 21, 2026; federal authorization decision deadline November 19, 2026), naming Schoharie County among the New York counties. None of the four names National Grid, a shipper or a gas load. The fifth notice, document 2026-17399 of August 26, 2026, is cited in note 13. The four were published from January to June 2026. ↩
Market and weather sources
Public web sources, as of October 25, 2026. They are context, separate from the regulatory record cited in the Notes. The Climate Prediction Center issues its seasonal outlook once each month near mid-month; this section is refreshed on the publication date.
- A1. U.S. Energy Information Administration, press release, "EIA expects a mixed picture for winter fuel costs this year," October 6, 2026. Link
- A2. U.S. Energy Information Administration, Short-Term Energy Outlook, October 2026 (natural gas storage). Link
- B1. NOAA Climate Prediction Center, Prognostic Discussion for Long-Lead Seasonal Outlooks, issued October 15, 2026. Link ↩
Sources
- New York State Department of Public Service, Case 24-G-0248, Final Report of National Grid's Final Long-Term Gas Plan. Link
- New York State Public Service Commission, Case 24-G-0248, Order Regarding Long-Term Natural Gas Plan and Requiring Further Actions. Link
- National Grid, Case 24-G-0248, Annual Long-Term Plan Update Report (2026). Link
- National Grid, Case 24-G-0248, LTP Demand Forecast Update and Report. Link
- Office of Management and Budget, OMB Bulletin No. 23-01, Revised Delineations of Metropolitan Statistical Areas, Micropolitan Statistical Areas, and Combined Statistical Areas, July 21, 2023.
- U.S. Energy Information Administration, EIA-860M Preliminary Monthly Electric Generator Inventory, September 2026. Link
- Federal Register, API search of Federal Energy Regulatory Commission notices by county. Link
- New York Independent System Operator, Interconnection Queue, September 30, 2026. Link
- Federal Register (FERC notice), Constitution Pipeline Company, LLC, Iroquois Gas Transmission System, L.P.; Notice of Availability of the Environmental Assessment, FR doc 2026-17399, August 26, 2026. Link
- Federal Energy Regulatory Commission, Notice of Schedule for the Preparation of an Environmental Assessment, Constitution Pipeline and Wright Interconnect Projects, June 24, 2026 (accession 20260624-3023). Link
- NOAA Regional Climate Centers (ACIS web service), Monthly heating degree days base 65F and 1991-2020 normals, station USW00014735. Link
- Federal Register (FERC Combined Notice of Filings), Combined Notice of Filings, FR doc 2026-16323, August 11, 2026 (Eastern Gas Transmission and Storage rate case compliance filing RP26-939-002). Link
- Federal Register (FERC Combined Notice of Filings), Combined Notice of Filings, FR doc 2026-15640, August 3, 2026. Link
- Federal Register (FERC Combined Notice of Filings), Combined Notice of Filings, FR doc 2026-17846, September 1, 2026. Link
- Federal Register (FERC Combined Notice of Filings), Combined Notice of Filings, FR doc 2026-19662, September 25, 2026. Link
- Federal Register (FERC Combined Notice of Filings), Combined Notice of Filings, FR doc 2026-20106, October 1, 2026. Link
- Federal Register (FERC notice), Constitution Pipeline Company, LLC; Notice of Petition and Establishing Intervention Deadline (FR 2026-00481, January 13, 2026). Link
- Federal Register (FERC notice), Iroquois Gas Transmission System, L.P.; Notice of Petition and Establishing Intervention Deadline (FR 2026-03948, February 27, 2026). Link
- Federal Register (FERC notice), Constitution Pipeline Company, LLC; Iroquois Gas Transmission System, L.P.: Notice of Scoping Period Requesting Comments on Environmental Issues for the Proposed Constitution Pipeline and Wright Interconnect Projects (FR 2026-06767, April 8, 2026). Link
- Federal Register (FERC notice), Constitution Pipeline Company, LLC; Iroquois Gas Transmission System, L.P.: Notice of Schedule for the Preparation of an Environmental Assessment for the Constitution Pipeline and Wright Interconnect Projects (FR 2026-13088, June 29, 2026). Link
Corrected November 9, 2026: the earlier version said our Federal Register search found no pipeline notice naming any of the five counties; it found five FERC notices that name Schoharie County, all on the Constitution Pipeline and Iroquois's Wright Interconnect project, none tied to National Grid's East Gate.