Energy procurement in North Carolina: buying electricity and natural gas for business
How commercial and industrial companies in North Carolina buy natural gas and manage electricity costs: which utilities serve each county, which grid sets wholesale prices, how gas supply contracts are structured, and the rate cases and rulings that move prices, updated weekly.
North Carolina businesses cannot choose an electricity supplier: each site buys power from its local utility under a regulated tariff. Natural gas is different. Larger commercial and industrial users can buy gas from a marketer under the utility's transportation service, priced off NYMEX and local basis (Transco Zone 5 South, Henry Hub). Discovery Energy Utility Audits buys natural gas for multi-site companies with sites in North Carolina, audits electric and gas bills against the North Carolina tariffs, and tracks every contract and tariff change in TaraBase.
01 / 08
North Carolina at a glance
| Business electricity choice | No (regulated utility supply) |
|---|---|
| Natural gas supplier choice | Yes for larger commercial and industrial users (utility transportation service) |
| Grid operator (wholesale market) | No ISO (Duke Energy); PJM in the northeast |
| Default electricity service | Duke Energy Carolinas, Duke Energy Progress, Dominion (NC), municipal utilities and cooperatives |
| Capacity costs | No capacity market (PJM capacity for Dominion's northeast NC customers) |
| Regulator | North Carolina Utilities Commission (NCUC) |
| Broker and supplier licensing | No retail electricity choice |
| Gas pricing points | Transco Zone 5 South, Henry Hub |
02 / 08
Electricity in North Carolina: regulated supply, choices inside the tariff
North Carolina has no retail electricity choice. Duke Energy Carolinas and Duke Energy Progress serve most businesses; Dominion Energy serves the northeast corner (in PJM); municipal utilities and cooperatives serve the rest. Large new loads and the state's carbon plan are driving large rate increases and new large-load terms.
Duke's Green Source Advantage and Clean Energy Impact programs let large customers buy renewable energy; rate selection, hourly pricing and demand response are the other levers.
03 / 08
How energy contracts are structured in North Carolina
What a buyer in North Carolina actually signs, and the terms that decide the final cost:
- Electricity: tariffs, hourly pricing schedules and renewable programs.
- Natural gas: Piedmont Natural Gas and Enbridge Gas North Carolina offer transportation for large C&I; gas is priced at Transco Zone 5 South, which can spike well above Henry Hub in winter.
Each structure is explained in energy contract structures, and how capacity, transmission and ancillary costs differ by grid is in charges by market.
04 / 08
Buying natural gas for business in North Carolina
Piedmont Natural Gas (Duke Energy) serves Charlotte and the Piedmont, Enbridge Gas North Carolina (formerly PSNC) the Raleigh area and eastern and western regions, and Frontier Natural Gas the northwest. Larger users transport gas bought from marketers. Discovery rates winter capacity in its Charlotte and Raleigh outlooks.
How transportation service, balancing and NYMEX plus basis pricing work is explained in natural gas procurement.
| Utility | Area | Supplier option |
|---|---|---|
| Piedmont Natural Gas (Duke Energy) | Charlotte, Greensboro, Winston-Salem | Transportation for large C&I |
| Enbridge Gas North Carolina | Raleigh, Durham, eastern and western NC | Transportation for large C&I |
| Frontier Natural Gas | Northwest North Carolina | Transportation for large C&I |
05 / 08
Electric utilities in North Carolina and where supplier choice is open
North Carolina has 108 retail electric utilities in the U.S. electric utility directory. None of them offers retail supplier choice to existing customers, so the tariff, and checking that each account is billed on the right one, is what a business can manage.
- Investor-owned utility
- Cooperative
- Municipal or public power
Each North Carolina county is shaded by the utility most likely to serve most of it (most customers per county served). Electricity supply here is regulated, so the map shows who sets your tariff; hover or tap a county to see every utility serving it.
| Utility | Type | Customers | Counties | Supplier choice |
|---|---|---|---|---|
| Duke Energy Carolinas | Investor-owned | 2,005,333 | 44 | Regulated (no choice) |
| Duke Energy Progress | Investor-owned | 1,411,441 | 56 | Regulated (no choice) |
| EnergyUnited Elec Member Corp | Cooperative | 129,872 | 19 | Regulated (no choice) |
| Dominion Energy Virginia / North Carolina | Investor-owned | 121,085 | 25 | Regulated (no choice) |
| Brunswick Electric Member Corp | Cooperative | 93,154 | 4 | Regulated (no choice) |
| Fayetteville Public Works Commission | Municipal | 81,991 | 1 | Regulated (no choice) |
| Union Electric Membership Corp - (NC) | Cooperative | 77,041 | 5 | Regulated (no choice) |
| Blue Ridge Elec Member Corp - (NC) | Cooperative | 76,261 | 7 | Regulated (no choice) |
| Jones-Onslow Elec Member Corp | Cooperative | 75,645 | 6 | Regulated (no choice) |
| Rutherford Elec Member Corp | Cooperative | 70,153 | 10 | Regulated (no choice) |
| Greenville Utilities Comm | Municipal | 67,704 | 1 | Regulated (no choice) |
| Lumbee River Elec Member Corp | Cooperative | 61,427 | 5 | Regulated (no choice) |
| Wake Electric Membership Corp | Cooperative | 45,235 | 7 | Regulated (no choice) |
| South River Elec Member Corp | Cooperative | 44,701 | 5 | Regulated (no choice) |
| Town of High Point | Municipal | 41,398 | 4 | Regulated (no choice) |
| Carteret-Craven El Member Corp | Cooperative | 40,467 | 4 | Regulated (no choice) |
| French Broad Elec Member Corp | Cooperative | 37,240 | 4 | Regulated (no choice) |
| City of Wilson | Municipal | 34,496 | 7 | Regulated (no choice) |
| Four County Elec Member Corp | Cooperative | 32,725 | 6 | Regulated (no choice) |
| Piedmont Electric Member Corp | Cooperative | 32,113 | 7 | Regulated (no choice) |
| Randolph Electric Member Corp | Cooperative | 31,994 | 5 | Regulated (no choice) |
| City of Concord - (NC) | Municipal | 31,298 | 1 | Regulated (no choice) |
| City of Rocky Mount - (NC) | Municipal | 27,992 | 2 | Regulated (no choice) |
| City of Gastonia - (NC) | Municipal | 27,963 | 1 | Regulated (no choice) |
| Surry-Yadkin Elec Member Corp | Cooperative | 27,063 | 5 | Regulated (no choice) |
The table shows the 25 largest by customers. All 108, with the counties each serves, are in the North Carolina electric utility directory.
06 / 08
North Carolina energy market and regulatory feed
Rate cases, commission orders, grid operator decisions, legislation and Discovery research that move electricity and natural gas prices in North Carolina, checked every Saturday. Items with a grid or national label apply to the whole region. Machine-readable: state-feeds.json.
Last item ; 12 shown, newest first.
NCUC approves Duke Carolinas resource plan: 3,841 MW of new gas, some coal retirements delayed to 2040
NCUC approved near-term actions in Duke Energy's Carbon Plan and Integrated Resource Plan. The order adds 3,841 MW of gas generation between 2030 and 2033 and delays some coal retirements until 2040. It also adds solar, batteries and nuclear development work. Duke's next plan is due in fall 2027.
Why it matters for buyers: The plan sets the generation build that future Duke rates will recover, so long-term budgets should assume continued increases. New gas plants also add to utility gas demand in the Carolinas, which bears on Transco Zone 5 South basis.
Source: Axios Raleigh
PJM asks FERC to cut data center grid connection studies from 24 to 12 months
PJM filed a 1,067-page proposal at FERC on Nov. 16 for a combined study of generators, transmission upgrades and large loads. It would cut study time from 24 to 12 months. PJM wants a ruling within 120 days, which points to about mid-March 2027.
Why it matters for buyers: Large new loads in PJM may get faster energization if they bring generation or can curtail. That changes how multi-site buyers should time expansions and what they assume about upgrade cost allocation. Watch for new large-load tariff terms to audit.
Source: PJM Interconnection (Fast Energization, Members Committee, Nov. 5, 2026)
FERC to take up Sabine Pass Stage 5 LNG expansion and pipeline at its Nov. 19 open meeting
FERC's Nov. 19 agenda, set by the Nov. 12 sunshine notice, includes Cheniere's Sabine Pass Stage 5 expansion. The project adds three liquefaction trains and a 55.6-mile pipeline to deliver up to 3.6 Bcf/d to the terminal.
Why it matters for buyers: If approved and built, it would add a large new block of feedgas demand on the Gulf Coast. That supports Henry Hub and Gulf basis over the long term, so it matters for multi-year gas contract terms.
Source: Lexology (FERC meeting agenda summary)
NCUC approves Duke Energy Carolinas and Progress two-year rate plans, new rates start Jan. 1, 2027
The NC Utilities Commission's Nov. 16 orders approve settlements at a 9.8% return on equity. Revenue increases are about $496 million for Duke Energy Carolinas and $338 million for Duke Energy Progress over two years. Both are well below the requests of $1,002 million and $729 million.
Why it matters for buyers: Base rates are regulated and can't be shopped, so budget for the increases from January 2027. Audit angle: check that January bills reflect the new rate schedules and any riders, and that your rate class is correct.
Source: MLQ.ai (citing Duke Energy 8-K and NCUC orders)
NCUC sets its own Duke data center rate schedule: 50 MW threshold, 10 to 15 year terms, 75% minimum bills
In the Nov. 16 rate orders, NCUC rewrote the large-load tariff settlement. The new schedule applies at 50 MW or more. Contracts run at least 10 years, or 15 years above 100 MW. Customers pay for at least 75% of contracted power. It also covers data centers that have not yet taken service.
Why it matters for buyers: Large new loads in Duke territory face long commitments and take-or-pay minimums, which affects site selection and cost modeling. Other large industrial users should watch whether the schedule is extended beyond data centers.
Source: Business North Carolina
PJM files ride-through rules at FERC for data centers and other loads of 50 MW or more
On Nov. 16 PJM filed a proposal with FERC creating a Large Computational Load category for sites of 50 MW or more. These loads would have to stay connected during voltage and frequency disturbances. The filing follows a July 22 event in which about 3.9 GW of data center load dropped off the grid.
Why it matters for buyers: New technical conditions may attach to interconnection and service for large sites. Buyers with data center or other large computational load should check them against site plans and utility service agreements before signing new capacity or supply commitments.
Source: PJM Inside Lines
North Carolina regulators approve Duke rate increases and a new rate schedule for 50 MW+ data centers
The North Carolina Utilities Commission approved Duke Energy Carolinas' and Duke Energy Progress' rate settlements on Nov 16, 2026, and set a separate rate schedule for data center customers above 50 MW, Duke said on Nov 17. Duke says the orders add upfront payments for dedicated facilities, transmission upgrade…
Source: Data Center Index
EIA: Lower 48 gas storage reaches 3,862 Bcf after 61 Bcf injection, 75 Bcf above five-year average
EIA's Nov. 13 report for the week ending Nov. 6 showed a 61 Bcf injection. Inventories rose to 3,862 Bcf, 2% above the five-year average. The five-year average build for the week was about 40 Bcf, and December Henry Hub futures settled down 3.3% at $3.23/MMBtu.
Why it matters for buyers: Storage is above normal heading into winter, which backs the soft Henry Hub outlook. Buyers with index-based gas or pass-through supply contracts can see lower near-term costs. Those considering fixed-price deals have less pressure to lock in now.
Source: fxempire / Finimize (citing EIA Weekly Natural Gas Storage Report)
Blackcomb pipeline enters service, adding up to 2.5 Bcf/d of Permian takeaway as Waha cash holds near $1.87
The Blackcomb pipeline began service in November, with volumes to ramp up through 2027. It joins the Gulf Coast Express expansion and Hugh Brinson Phase 1 for up to about 4.57 Bcf/d of added Permian capacity. Waha cash traded around $1.87/MMBtu on Nov. 10–13.
Why it matters for buyers: Added Permian egress moves more gas toward the Gulf Coast and LNG demand. That narrows Waha's discount and can shift Texas and Southwest basis, which matters when pricing index-based gas and renewals.
Source: EBC Financial Group (citing IEA data); Aegis Hedging
PJM's market monitor says data center load added about $30 billion to capacity costs
Monitoring Analytics, PJM's independent market monitor, said in its state-of-the-market report that including forecast data center demand in the capacity market has raised capacity costs for all customers by close to $30 billion across recent auctions, and recommended excluding forecast data center load and requiring large new loads to bring their own generation.
Why it matters for buyers: Capacity is now one of the largest pieces of a PJM supply price. Check whether your contracts fix or pass through capacity, manage peak load contributions before next summer's peaks, and audit capacity tags on every bill.
Source: Pennsylvania Capital-Star
LNG feedgas sets a daily record as December gas futures firm
The American Gas Association's market indicators report U.S. LNG feedgas hit a new daily record on November 7, and December Henry Hub futures settled near $3.22 per MMBtu on a short cold spell, even as EIA raised its 2026 production forecast.
Why it matters for buyers: Record export demand keeps a floor under NYMEX prices; buyers layering winter and 2027 volumes should spread purchases rather than chase one weather-driven week.
Source: American Gas Association
Transco Mainline C equipment failure widens Zone 5 South to Station 165 gas spread to $2.565
Transco isolated part of Mainline C during Southeast Supply Enhancement construction. This cut north-south capacity through Compressor Station 160 by about 20%, to 1.80 Bcf/d, for one day. Transco Zone 5 South basis rose 38 cents to plus 83 cents, and the spread to Station 165 reached $2.565/MMBtu as of Nov. 10.
Why it matters for buyers: Gas buyers in the Carolinas, Georgia and Alabama should expect basis to stay volatile while construction continues. Index-priced contracts for Zone 5 South deliveries carry the most exposure. Fixed-price blocks locked before cold snaps look better against this risk.
Source: Natural Gas Intelligence
07 / 08
How Discovery Energy buys energy for companies in North Carolina
Inventory
Every North Carolina account: utility, rate schedule, riders, demand and gas service type, with usage and contract dates in one list.
Audit the tariffs
Each electric and gas bill tested against the North Carolina tariff: rate class, riders, demand ratchets, power factor and meter setup. See utility bill audits.
Buy the gas
For sites that qualify for transportation service: the cost of utility supply compared with marketer supply, then one RFP to every active marketer, fixed or index, with balancing terms checked. See natural gas procurement.
Track
Every contract and tariff change in TaraBase, with renewals flagged well ahead.
Discovery Energy acts as an energy broker in its procurement work; its energy broker licenses and registrations are held by Energy Auction Exchange, LLC. Its procurement fee is disclosed before any contract is signed (see energy broker fees).
08 / 08
Questions about energy procurement in North Carolina
Can businesses choose their electricity supplier in North Carolina?
No. Electricity supply in North Carolina is regulated: each site buys from its local utility under a tariff. Businesses lower cost by choosing the right rate and riders, using demand response or interruptible options, and auditing bills against the tariff.
How does electricity contracting work for businesses in North Carolina?
In North Carolina the contract is the utility's tariff, plus any special contract a very large load negotiates. Contracting decisions are about rate schedule, riders and service agreements for new load, and about natural gas supply, which large users can buy from marketers.
How do I buy natural gas for my business in North Carolina?
Larger commercial and industrial users take the utility's transportation service and buy gas from a marketer; smaller sites usually buy bundled gas from the utility. Gas is typically priced as NYMEX plus basis at Transco Zone 5 South, Henry Hub, fixed or index, with the utility's delivery and balancing charges on top.
Which grid operator sets wholesale electricity prices in North Carolina?
No ISO (Duke Energy); PJM in the northeast. The grid operator's energy, capacity and transmission rules decide what a supplier must price into a contract and what a utility passes through its fuel and capacity riders.
Who regulates electricity and natural gas rates in North Carolina?
The North Carolina Utilities Commission (NCUC) regulates the investor-owned utilities' rates and service rules. Municipal utilities and cooperatives are usually governed by their own boards.
Sources
- North Carolina Utilities Commission, utility regulation.
- U.S. EIA, North Carolina state profile, utilities and prices.
- U.S. EIA, Form EIA-861 (via Discovery's U.S. electric utility directory), utilities, customer counts and counties served.