Energy procurement in Indiana: buying electricity and natural gas for business
How commercial and industrial companies in Indiana buy natural gas and manage electricity costs: which utilities serve each county, which grid sets wholesale prices, how gas supply contracts are structured, and the rate cases and rulings that move prices, updated weekly.
Indiana businesses cannot choose an electricity supplier: each site buys power from its local utility under a regulated tariff. Natural gas is different. Smaller businesses can pick a gas supplier through a choice program, and larger commercial and industrial users can buy gas from a marketer under the utility's transportation service, priced off NYMEX and local basis (Chicago Citygate, REX Zone 3, Michcon, Texas Gas Zone 1). Discovery Energy Utility Audits buys natural gas for multi-site companies with sites in Indiana, audits electric and gas bills against the Indiana tariffs, and tracks every contract and tariff change in TaraBase.
01 / 08
Indiana at a glance
| Business electricity choice | No (regulated utility supply) |
|---|---|
| Natural gas supplier choice | Yes: choice programs reach small businesses; large users take transportation service |
| Grid operator (wholesale market) | MISO (PJM in the east and north) |
| Default electricity service | Duke Energy Indiana, AES Indiana, NIPSCO, I&M, CenterPoint and cooperatives by tariff |
| Capacity costs | MISO Planning Resource Auction; PJM capacity for Indiana Michigan Power |
| Regulator | Indiana Utility Regulatory Commission (IURC) |
| Broker and supplier licensing | No retail electricity choice; NIPSCO Choice gas suppliers approved by the IURC |
| Gas pricing points | Chicago Citygate, REX Zone 3, Michcon, Texas Gas Zone 1 |
02 / 08
Electricity in Indiana: regulated supply, choices inside the tariff
Indiana has no retail electricity choice. Duke Energy Indiana, AES Indiana, NIPSCO and CenterPoint Energy Indiana South sit in MISO, while Indiana Michigan Power (AEP) sits in PJM, so the same company can pay very different capacity costs at two Indiana plants. Discovery's briefing on Indiana's two capacity markets explains what AES Indiana's Rider 24 and PJM mean for a bill.
Large customers choose among industrial rate schedules, interruptible and demand response options, and negotiate terms for large new loads; data center growth has led utilities to file large-load tariffs.
03 / 08
How energy contracts are structured in Indiana
What a buyer in Indiana actually signs, and the terms that decide the final cost:
- Electricity: tariff and rider choices; large new loads sign service agreements with minimum demand terms.
- Natural gas: NIPSCO Choice lets residential and commercial customers buy from approved suppliers; larger customers of NIPSCO, CenterPoint Indiana North (25,000 therms a year and up) and South, and Citizens Energy Group take transportation service.
- Gas is priced at Chicago Citygate, Michcon or Rockies Express (REX) Zone 3 delivery points, or NYMEX plus basis.
Each structure is explained in energy contract structures, and how capacity, transmission and ancillary costs differ by grid is in charges by market.
04 / 08
Buying natural gas for business in Indiana
NIPSCO's CHOICE program has let residential and commercial customers in northern Indiana pick a gas supplier since the late 1990s. Elsewhere, choice is for larger users: CenterPoint Energy Indiana North offers transportation service to non-residential customers using 25,000 therms a year or more, and CenterPoint Indiana South, Citizens Energy Group (Indianapolis) and others have their own transport tariffs.
How transportation service, balancing and NYMEX plus basis pricing work is explained in natural gas procurement.
| Utility | Area | Supplier option |
|---|---|---|
| NIPSCO (NiSource) | Northern Indiana | CHOICE program; transportation for large C&I |
| CenterPoint Energy Indiana North | Central Indiana (51 counties) | Transportation at 25,000 therms a year and up |
| CenterPoint Energy Indiana South | Evansville and southwest Indiana | Transportation for large C&I |
| Citizens Energy Group | Indianapolis | Transportation for large C&I |
05 / 08
Electric utilities in Indiana and where supplier choice is open
Indiana has 122 retail electric utilities in the U.S. electric utility directory. None of them offers retail supplier choice to existing customers, so the tariff, and checking that each account is billed on the right one, is what a business can manage.
- Investor-owned utility
- Municipal or public power
Each Indiana county is shaded by the utility most likely to serve most of it (most customers per county served). Electricity supply here is regulated, so the map shows who sets your tariff; hover or tap a county to see every utility serving it.
| Utility | Type | Customers | Counties | Supplier choice |
|---|---|---|---|---|
| Duke Energy Indiana | Investor-owned | 830,270 | 71 | Regulated (no choice) |
| AES Indiana (formerly Indianapolis Power & Light) | Investor-owned | 495,352 | 20 | Regulated (no choice) |
| NIPSCO (NiSource) | Investor-owned | 471,891 | 20 | Regulated (no choice) |
| Indiana Michigan Power (AEP) | Investor-owned | 465,774 | 25 | Regulated (no choice) |
| CenterPoint Energy Indiana South (formerly Vectren/SIGECO) | Investor-owned | 142,453 | 7 | Regulated (no choice) |
| City of Anderson - (IN) | Municipal | 35,602 | 1 | Regulated (no choice) |
| South Central Indiana REMC | Cooperative | 33,758 | 7 | Regulated (no choice) |
| Hendricks County Rural E M C | Cooperative | 32,411 | 4 | Regulated (no choice) |
| Northeastern Rural E M C | Cooperative | 30,700 | 6 | Regulated (no choice) |
| Tipmont Rural Elec Member Corp | Cooperative | 27,671 | 8 | Regulated (no choice) |
| Southeastern Indiana R E M C | Cooperative | 27,156 | 7 | Regulated (no choice) |
| Johnson County Rural E M C | Cooperative | 27,144 | 4 | Regulated (no choice) |
| City of Mishawaka | Municipal | 26,836 | 1 | Regulated (no choice) |
| Jackson County Rural E M C - (IN) | Cooperative | 24,597 | 10 | Regulated (no choice) |
| Clark County Rural E M C - (IN) | Cooperative | 24,502 | 5 | Regulated (no choice) |
| Harrison County Rural E M C | Cooperative | 23,235 | 5 | Regulated (no choice) |
| City of Richmond - (IN) | Municipal | 21,106 | 1 | Regulated (no choice) |
| Kankakee Valley Rural E M C | Cooperative | 20,936 | 7 | Regulated (no choice) |
| Utilities Dist-Western IN REMC | Cooperative | 19,029 | 11 | Regulated (no choice) |
| Kosciusko County Rural E M C | Cooperative | 18,325 | 4 | Regulated (no choice) |
| Heartland REMC | Cooperative | 17,508 | 8 | Regulated (no choice) |
| Western Indiana Energy REMC | Cooperative | 16,947 | 8 | Regulated (no choice) |
| NineStar Connect | Cooperative | 15,151 | 4 | Regulated (no choice) |
| Carroll-White REMC | Cooperative | 14,649 | 9 | Regulated (no choice) |
| Boone County Rural EMC | Cooperative | 14,619 | 5 | Regulated (no choice) |
The table shows the 25 largest by customers. All 122, with the counties each serves, are in the Indiana electric utility directory.
06 / 08
Indiana energy market and regulatory feed
Rate cases, commission orders, grid operator decisions, legislation and Discovery research that move electricity and natural gas prices in Indiana, checked every Saturday. Items with a grid or national label apply to the whole region. Machine-readable: state-feeds.json.
Last item ; 12 shown, newest first.
DOE orders Michigan's Campbell coal plant kept available through Feb. 12, 2027; costs spread across MISO
DOE issued its seventh emergency order on Nov. 13 for the J.H. Campbell plant. Consumers Energy expects to seek $303 million in net costs through Sept. 30 from FERC, to be spread across MISO's North and Central regions. FERC allowed that allocation in August 2025, and MISO's revised tariff filing is still awaiting FERC approval.
Why it matters for buyers: Buyers in MISO North/Central states may see an uplift charge through the transmission or wholesale pass-through lines on their bills, with timing depending on FERC. Audit these lines for the new cost recovery, and note the order's three-month scope when budgeting through winter.
Source: MLQ.ai (citing DOE and CMS Energy 10-Q)
PJM asks FERC to cut data center grid connection studies from 24 to 12 months
PJM filed a 1,067-page proposal at FERC on Nov. 16 for a combined study of generators, transmission upgrades and large loads. It would cut study time from 24 to 12 months. PJM wants a ruling within 120 days, which points to about mid-March 2027.
Why it matters for buyers: Large new loads in PJM may get faster energization if they bring generation or can curtail. That changes how multi-site buyers should time expansions and what they assume about upgrade cost allocation. Watch for new large-load tariff terms to audit.
Source: PJM Interconnection (Fast Energization, Members Committee, Nov. 5, 2026)
FERC to take up Sabine Pass Stage 5 LNG expansion and pipeline at its Nov. 19 open meeting
FERC's Nov. 19 agenda, set by the Nov. 12 sunshine notice, includes Cheniere's Sabine Pass Stage 5 expansion. The project adds three liquefaction trains and a 55.6-mile pipeline to deliver up to 3.6 Bcf/d to the terminal.
Why it matters for buyers: If approved and built, it would add a large new block of feedgas demand on the Gulf Coast. That supports Henry Hub and Gulf basis over the long term, so it matters for multi-year gas contract terms.
Source: Lexology (FERC meeting agenda summary)
MISO files FERC large-load plan with new transmission service options and anti-cost-shift agreements
On Nov. 16, MISO filed its response to FERC's large-load show-cause order. It includes a Large Load Project Review process, new transmission service options, and standard cost-recovery agreements. A separate filing proposes Grid Responsive Integration Transmission Service for large loads that can curtail at certain price and reliability conditions.
Why it matters for buyers: Sites above 50 MW, such as data centers and big plants, may face new interconnection steps and a curtailable service option that changes what they pay. Buyers with expansion plans should track the FERC ruling before signing supply or service terms.
Source: Utility Dive (via Yahoo News)
PJM files ride-through rules at FERC for data centers and other loads of 50 MW or more
On Nov. 16 PJM filed a proposal with FERC creating a Large Computational Load category for sites of 50 MW or more. These loads would have to stay connected during voltage and frequency disturbances. The filing follows a July 22 event in which about 3.9 GW of data center load dropped off the grid.
Why it matters for buyers: New technical conditions may attach to interconnection and service for large sites. Buyers with data center or other large computational load should check them against site plans and utility service agreements before signing new capacity or supply commitments.
Source: PJM Inside Lines
MISO board committee advances $14.7B MTEP 26 transmission plan, over half driven by large loads
A MISO board committee cleared the 2026 Transmission Expansion Plan, which covers 532 projects and $14.7 billion. More than half of the cost comes from new large loads. Stakeholders are asking for consumer protections against cost shifting.
Why it matters for buyers: Transmission spending flows into delivery charges, usually as pass-through riders that are hard to hedge in fixed-price supply deals. Buyers should budget for higher transmission line items and check them when auditing bills.
Source: RTO Insider
EIA: Lower 48 gas storage reaches 3,862 Bcf after 61 Bcf injection, 75 Bcf above five-year average
EIA's Nov. 13 report for the week ending Nov. 6 showed a 61 Bcf injection. Inventories rose to 3,862 Bcf, 2% above the five-year average. The five-year average build for the week was about 40 Bcf, and December Henry Hub futures settled down 3.3% at $3.23/MMBtu.
Why it matters for buyers: Storage is above normal heading into winter, which backs the soft Henry Hub outlook. Buyers with index-based gas or pass-through supply contracts can see lower near-term costs. Those considering fixed-price deals have less pressure to lock in now.
Source: fxempire / Finimize (citing EIA Weekly Natural Gas Storage Report)
Blackcomb pipeline enters service, adding up to 2.5 Bcf/d of Permian takeaway as Waha cash holds near $1.87
The Blackcomb pipeline began service in November, with volumes to ramp up through 2027. It joins the Gulf Coast Express expansion and Hugh Brinson Phase 1 for up to about 4.57 Bcf/d of added Permian capacity. Waha cash traded around $1.87/MMBtu on Nov. 10–13.
Why it matters for buyers: Added Permian egress moves more gas toward the Gulf Coast and LNG demand. That narrows Waha's discount and can shift Texas and Southwest basis, which matters when pricing index-based gas and renewals.
Source: EBC Financial Group (citing IEA data); Aegis Hedging
PJM's market monitor says data center load added about $30 billion to capacity costs
Monitoring Analytics, PJM's independent market monitor, said in its state-of-the-market report that including forecast data center demand in the capacity market has raised capacity costs for all customers by close to $30 billion across recent auctions, and recommended excluding forecast data center load and requiring large new loads to bring their own generation.
Why it matters for buyers: Capacity is now one of the largest pieces of a PJM supply price. Check whether your contracts fix or pass through capacity, manage peak load contributions before next summer's peaks, and audit capacity tags on every bill.
Source: Pennsylvania Capital-Star
LNG feedgas sets a daily record as December gas futures firm
The American Gas Association's market indicators report U.S. LNG feedgas hit a new daily record on November 7, and December Henry Hub futures settled near $3.22 per MMBtu on a short cold spell, even as EIA raised its 2026 production forecast.
Why it matters for buyers: Record export demand keeps a floor under NYMEX prices; buyers layering winter and 2027 volumes should spread purchases rather than chase one weather-driven week.
Source: American Gas Association
AWS breaks ground on $7B Project Rise campus in Wheatfield, Indiana (watch list)
Amazon Web Services held a ceremonial groundbreaking on Nov 12 for its $7 billion Project Rise data center campus on 304 acres of former NIPSCO land in Wheatfield, Jasper County, Indiana, next to NIPSCO's Schahfer Generating Station; Inside Indiana Business reports more than 350 workers already on site. Jasper County…
Source: Data Center Index
EIA cuts its winter Henry Hub forecast to $2.87 per MMBtu
In its November Short-Term Energy Outlook, EIA lowered its November-to-March Henry Hub spot price forecast by 16% to $2.87 per MMBtu, about 36% below last winter, citing a warm start to November and production growing faster than demand and LNG exports. It expects Henry Hub to average $2.88 in 2027, down from $3.37 in 2026.
Why it matters for buyers: A softer winter strip is a window to fix 2027 and 2028 gas supply for plants on transportation service; basis at constrained citygates can still spike in a cold snap, so lock basis separately where winter delivery is tight.
Source: American Public Power Association (EIA Short-Term Energy Outlook)
07 / 08
How Discovery Energy buys energy for companies in Indiana
Inventory
Every Indiana account: utility, rate schedule, riders, demand and gas service type, with usage and contract dates in one list.
Audit the tariffs
Each electric and gas bill tested against the Indiana tariff: rate class, riders, demand ratchets, power factor and meter setup. See utility bill audits.
Buy the gas
For sites that qualify for transportation service: the cost of utility supply compared with marketer supply, then one RFP to every active marketer, fixed or index, with balancing terms checked. See natural gas procurement.
Track
Every contract and tariff change in TaraBase, with renewals flagged well ahead.
Discovery Energy acts as an energy broker in its procurement work; its energy broker licenses and registrations are held by Energy Auction Exchange, LLC. Its procurement fee is disclosed before any contract is signed (see energy broker fees).
08 / 08
Questions about energy procurement in Indiana
Can businesses choose their electricity supplier in Indiana?
No. Electricity supply in Indiana is regulated: each site buys from its local utility under a tariff. Businesses lower cost by choosing the right rate and riders, using demand response or interruptible options, and auditing bills against the tariff.
How does electricity contracting work for businesses in Indiana?
In Indiana the contract is the utility's tariff, plus any special contract a very large load negotiates. Contracting decisions are about rate schedule, riders and service agreements for new load, and about natural gas supply, which large users can buy from marketers.
How do I buy natural gas for my business in Indiana?
Smaller businesses can pick a gas supplier through the utility's choice program; larger users take transportation service and buy gas from a marketer. Gas is typically priced as NYMEX plus basis at Chicago Citygate, REX Zone 3, Michcon, Texas Gas Zone 1, fixed or index, with the utility's delivery and balancing charges on top.
Which grid operator sets wholesale electricity prices in Indiana?
MISO (PJM in the east and north). The grid operator's energy, capacity and transmission rules decide what a supplier must price into a contract and what a utility passes through its fuel and capacity riders.
Who regulates electricity and natural gas rates in Indiana?
The Indiana Utility Regulatory Commission (IURC) regulates the investor-owned utilities' rates and service rules. Municipal utilities and cooperatives are usually governed by their own boards.
Sources
- Indiana OUCC, NIPSCO natural gas Choice program, how the program works.
- CenterPoint Energy, Indiana North gas transportation, 25,000 therms eligibility.
- U.S. EIA, Indiana state profile, utilities, prices and energy use.
- U.S. EIA, Form EIA-861 (via Discovery's U.S. electric utility directory), utilities, customer counts and counties served.