Washington natural gas case study, Spokane, Washington. November 2026
Spokane-area natural gas capacity: the utility's plan needs no new transportation for firm loads
The Washington Utilities and Transportation Commission (UTC) acknowledged Avista's 2025 gas plan in September 2025. Avista says no new transportation is needed for firm loads and forecasts a Washington-area peak day of 238.13 thousand dekatherms (Dth) for 2026.
Metro used: the Spokane-Spokane Valley, WA metropolitan statistical area, as delineated by the federal government in OMB Bulletin No. 23-01 (July 21, 2023). Avista Corporation (Avista), doing business as Avista Utilities, is the one gas distribution utility named in the record, and its 2025 plan covers Washington, Idaho and Oregon, so the Washington figures below are the most local available.1
Key takeaways
- The UTC's letter, served September 26, 2025, says Avista's plan, filed March 31, 2025, complies with the gas planning rule; it is not a determination of prudency.5
- Avista says it is still long on transport rights, consistent with prior plan expectations, and needs no new fuel transportation for firm loads; both statements cover its whole system.6
- The Washington-area peak day load forecast falls about 5.6% from 2026 to 2029, by our calculation from the plan's two figures.3
- Avista says its pipeline contracts expire on different dates and it can renew all; Northwest Pipeline TF-1 is 157,869 Dth per day of Avista North's winter firm transportation.4
- Several industrial customers are considering Airway Heights, in Spokane County, but the plan lists the reinforcement with cost and timing as TBD, so it shows no date or budget.7
- EIA's September 2026 inventory lists no planned gas-fired generator in either county, and no Federal Energy Regulatory Commission (FERC) pipeline-certificate notice since January 1, 2025 names them.8
What is the outlook for Spokane gas capacity through 2029?
Discovery Energy rates the outlook for Spokane-area natural gas capacity through 2029 as Stable (confidence: Medium): Avista's 2025 gas plan, which the UTC acknowledged, says no new transportation is needed for firm loads.6 Its Washington-area peak day forecast falls about 5.6% from 2026 to 2029, by our calculation.3 These figures cover Avista's Washington area or its whole system, not the two metro counties alone. Documented risk factors: none. We do not treat the Airway Heights reinforcement as an open need: Avista's plan states no capacity or pressure shortfall at Airway Heights today, and the reinforcement is for industrial growth.7 Three developments would change the assessment: Avista's next gas IRP and any change to its transportation rights or capacity releases; the Airway Heights high pressure reinforcement, which has no date or budget in the filed plan, and any named industrial load there; the Commission's recommendations for Avista's future plans and any decision on gas planning.
Outlook levels, from least to most concern: Stable, Watch, Elevated, High, Severe. Levels describe the public record of capacity and supply risk; confidence is reported separately. They are qualitative assessments, not forecasts of outages.
Who serves the Spokane area?
Avista serves both metro counties. Its plan names communities in each, and no other gas utility in the two counties is identified in the record.1 Its Kettle Falls high pressure line serves Addy, Chewelah, Colville, Deer Park and Kettle Falls, and its Airway Heights main supplies a major regulator station supporting the Downtown Spokane neighborhoods.7
The peak day forecast below covers Avista's Washington area, which includes communities outside the two counties, and the transportation and storage totals cover Avista North, which is part of Avista's system. System context: the plan does not split them by county, so they are not metro figures. Idaho and Oregon loads are outside the metro. Northwest Pipeline, Gas Transmission Northwest and Jackson Prairie storage supply Avista's system; the plan does not say where they lie relative to the two counties.14
How much spare gas capacity does Spokane have on the coldest day?
In words: what the map shows
- Pipelines labeled: Northwest Pipeline; Gas Transmission Northwest.
- Metro counties outlined (2): Spokane County; Stevens County.
- Cities and towns labeled include: Spokane; Spokane Valley; Coeur d'Alene; Moses Lake.
- Highways are drawn for orientation. A small state locator map sits in a corner.
Avista's table of peak day design temperatures gives Spokane a coldest day on record of -17 degrees F, a 99th percentile coldest day forecast of -24 and a 2045 design day of -14. For the 2025 plan Avista further evolved its design day method by taking the coldest day on record for each area and adjusting it for expected temperature change.2
Avista's peak day load forecast for its Washington area, net of energy efficiency, follows.
| Year | Washington area peak day load (thousand Dth) |
|---|---|
| 2026 | 238.13 |
| 2029 | 224.69 |
Avista's peak day load forecast, Washington area, thousand Dth, net of energy efficiency, per Avista. Source: 2025 Natural Gas Integrated Resource Plan, Table 3.7.3
Avista says it is still long on transport rights and is not proposing any change to them.6 The plan's table shows contracted firm transportation of 349,674 Dth per day in winter for Avista North, including 157,869 Dth per day on Northwest Pipeline.4
The plan's resource charts are images, and its text gives no reserve margin for Spokane or Stevens County, so we have no margin for the coldest day and have not estimated one.
What is driving new natural gas demand?
We found no documented new gas load with a service date in the two counties.
Avista says several industrial customers are considering the Airway Heights location in Spokane County for new facilities or expansion, but the plan names no customer, load or service date.7 EIA's September 2026 generator inventory lists no planned natural gas-fired generator in the two counties, and a search of FERC pipeline-certificate notices in the Federal Register since January 1, 2025, and of all FERC notices from July 31 to October 29, 2026, found none naming either county.8 EIA lists existing Avista gas-fired electric generators in both counties; the one with a planned retirement is the Northeast combustion turbine in Spokane County, in December 2035.11
Data centers: As of October 29, 2026, we found no data center gas load in the two counties. Avista's web page, updated September 2026, says it has paused processing of large data center applications for at least 12 months; the page concerns electric service and names no site.9 In June 2026 the Spokane City Council passed a one-year moratorium on building permits for new data centers, which concerns permits and not gas.10
Nearby: The Northwest Pipeline and Gas Transmission Northwest filings we found since August 2026 are rate, fuel and standards filings, and none names a county or a new gas load.12
Are upgrades arriving in time?
Avista's plan shows no capacity need for transportation. For the Airway Heights high pressure main, Avista says a reinforcement will provide additional capacity for industrial growth and reliable pressure at the end of the main, but its project table lists the growth-driven reinforcement with cost and timing as TBD, which is neither an approved nor a scheduled project.7
For the Kettle Falls line in Stevens County, Avista says design begins in 2026-27 with construction anticipated in 2027-28, and describes it as an integrity project, not a capacity project.7 The UTC's letter does not determine the prudency of any course of action in the plan; it said it will conduct prudency reviews in future rate proceedings.5
Winter and market context
NOAA's Climate Prediction Center said on October 15, 2026 that its November 2026 to January 2027 temperature outlook favors above-normal temperatures for, among other areas, the northern tier from the Pacific Northwest eastward, a discussion that names regions and not counties.B1 The national inventory, El Nino and liquefied natural gas export figures from EIA and NOAA do not bear on Avista's system, so they sit in a note.18
Northwest Pipeline posted a notice on March 12, 2026 saying the operator of Jackson Prairie storage had reported a malfunctioning component that prevented injections, and it declared a Stage II (8%) underrun entitlement for parties north of its Kemmerer compressor station from March 14, 2026.13 Avista's plan ties its firm storage to Jackson Prairie.14 The notice does not name Avista or any delivery to it, and it describes a limit on injections into storage, not a reduction in deliveries, so we did not count it as a supply event affecting Avista.13 Later Northwest Pipeline notices and any Gas Transmission Northwest postings are not covered here, so we do not know when the entitlement ended.
Winter weather and NOAA's outlook
Heating degree days, a measure of how much heating the weather called for, ran below the 1991-2020 normal at the Spokane International Airport station in each of the last three winters.15 NOAA's Climate Prediction Center outlook issued October 15, 2026 gives the Spokane area at least a 50% chance of above-normal temperatures for November 2026 to January 2027 and for December 2026 to February 2027.16 The airport is one station standing in for the metro, and NOAA's figures are probabilities for a three-month average, not a forecast of specific days.17
| Winter (November to March) | Heating degree days | 1991-2020 normal | Difference from normal |
|---|---|---|---|
| 2023-24 | 4466 | 4745 | -5.9% |
| 2024-25 | 4516 | 4745 | -4.8% |
| 2025-26 | 4058 | 4745 | -14.5% |
Heating degree days at the Spokane International Airport station, base 65 degrees F, against the 1991-2020 normal. Source: NOAA Regional Climate Centers.
What's new (as of October 29, 2026)
In September 2026 Avista paused processing of large data center applications for at least 12 months; its page concerns electric service, not gas.9 On October 15, 2026 Gas Transmission Northwest, a pipeline on which Avista holds firm transportation, filed a petition for approval of a settlement, and the notice does not give its terms.19
What should Spokane-area facilities check now?
- Tariffs and charges, through a utility audit. Confirm each account is on the right rate class and tariff, and that riders, demand charges and capacity-related charges are billed correctly. Over 70% of the clients Discovery Energy has audited were billed incorrectly. An audit verifies tariffs and charges and recovers overcharges before winter costs rise.
- Which service. Confirm whether each site takes firm or interruptible service from Avista; the plan says Avista does not make firm commitments to serve interruptible customers and assumes those loads would be curtailed on a peak day to serve firm customers.
- Backup plans and fuel. Check that alternate-fuel and curtailment plans are current and feasible, and that fuel inventories and resupply arrangements are in place before December.
- Upcoming proceedings. Track Avista's next gas IRP and its Airway Heights reinforcement if the site is in that area.
What to check in your contracts
| Area | What to check |
|---|---|
| Winter price spikes | Whether the gas is priced on a daily or a monthly index, how large the local basis (the gap between the local price and the national benchmark) has been in cold weather, and how much of your winter use is covered by fixed-price volumes. |
| Delivery constraints | Whether your transportation is firm, what delivery obligations your supplier carries and what happens if it cannot deliver, and what the curtailment provisions say about who is cut first. |
| Operational flow orders | What balancing obligations the contract places on you, and whether penalties that a pipeline or utility charges under an operational flow order are passed through to you. |
| Expansion plans | Where a utility or pipeline plans added capacity, whether the utility has confirmed in writing the incremental hourly and daily capacity available to your site, and from what date. |
Checks for gas supply and transportation contracts. They are questions to put to your supplier or utility, not financial advice.
Frequently asked questions
Will Spokane businesses face natural gas shortages this winter?
The record does not show a shortage, and this page makes no prediction about outages. See 'How much spare gas capacity does Spokane have on the coldest day?'
Is there spare gas capacity in the Spokane area on the coldest day?
Avista says it is still long on transport rights, but its plan gives no reserve margin for Spokane or Stevens County, so the margin is not shown. See 'How much spare gas capacity does Spokane have on the coldest day?'
Did the Washington UTC approve Avista's gas plan?
The Commission acknowledged the plan in a letter served September 26, 2025 and found that it complies with its gas resource planning rule. It did not determine prudency; see 'Are upgrades arriving in time?'
Is new industrial demand driving gas use in Spokane?
Several industrial customers are considering Airway Heights, but the plan names no customer, load or service date, and we found no data center gas load. See 'What is driving new natural gas demand?'
Who is cut first if Avista must curtail service?
The plan says Avista assumes interruptible loads would be curtailed on a peak day to serve firm customers. This page does not cover the tariff's interruption sequence.
Related case studies
Discovery Energy publishes gas capacity case studies for other metros, using the same method and outlook scale.
- Seattle natural gas capacity case study (outlook: Elevated)
- Portland area natural gas capacity case study (outlook: Elevated)
- Boise natural gas capacity case study (outlook: Watch)
- Salt Lake City area natural gas capacity case study (outlook: High)
All gas capacity ratings by U.S. metro
Background for commercial and industrial energy buyers: Utility cost intelligence
Understand your capacity exposure
Discovery Energy reviews service elections, interruption terms and regulatory proceedings for organizations across the U.S. and Canada, so capacity changes are understood before they reach the bill.
Schedule a reviewWhat this page does not cover
- Supply events affecting Avista since January 1, 2020. We found none in an official record.
- How Avista shares costs among customer classes, and its order of service interruption. We did not find these in the sources we used.
- When Avista's pipeline contracts expire. The plan text we reviewed does not give the dates.
- Any reserve margin for Spokane or Stevens County.
- Whether any new large gas load appears only in state air permits, interconnection queues or federal filings. Washington Department of Ecology and Spokane Regional Clean Air Agency permits, Avista and Northwest Pipeline interconnection queues and FERC filings are not covered here.
Notes
- Avista Corporation, 2025 Natural Gas Integrated Resource Plan (filed March 31, 2025; Washington UTC docket UG-240207), PDF 254 and PDF 255 (Chapter Ten) and PDF 85 (Table 3.7). Utility statements. The metro counties are Spokane and Stevens, from the OMB Bulletin No. 23-01 delineation. The match of towns to counties is general geography, not a quotation. ↩
- Same plan, Chapter Three, PDF 76 and PDF 77 (Table 3.4). ↩
- Same plan, Chapter Three, PDF 85 (Table 3.7, Washington column). The decline from 2026 to 2029 is our calculation (illustrative): 224.69 divided by 238.13 less one. ↩
- Same plan, Chapter Five, PDF 125 (Table 5.3, contracted firm transportation as filed). Northwest Pipeline TF-1 is 45.1% of Avista North's winter firm transportation by our calculation (illustrative; a share of contracts, not of design day). ↩
- Washington Utilities and Transportation Commission, Revised Commission Acknowledgment Letter re Avista Gas IRP, Docket UG-240207, served September 26, 2025, PDF 1 (the rule cited is Washington Administrative Code 480-90-238); docket document list, accessed October 25, 2026. Commission letter. ↩
- Same plan, Chapter Two, PDF 31 and PDF 39. ↩
- Same plan, Chapter Ten, PDF 254 and PDF 255; Chapter Two, PDF 31 (interruptible customers). ↩
- EIA-860M inventory for September 2026 (Planned sheet, operator-reported planned dates), filtered to Spokane and Stevens counties by us, and Federal Register searches by county phrase (FERC pipeline-certificate notices, docket numbers beginning CP, since January 1, 2025; all FERC notices from July 31 to October 29, 2026), both our own calculation. A notice that spells a place differently would be missed. ↩
- Avista Corporation, "Data Centers and Your Energy" web page, status section last updated September 2026, accessed October 29, 2026: "Avista has paused the processing of large data center applications" and "The pause began in September 2026 and is expected to last at least 12 months." The page is about electric service to data centers, and the part we read names no county, site or gas load. ↩
- City of Spokane, City Council news release "Spokane City Council Passes One-Year Moratorium on Data Centers," dated June 23, 2026, first paragraph (Ordinance C36887, passed at the Monday legislative session before that date), accessed October 29, 2026. It covers building permit applications for new computer data centers. ↩
- U.S. Energy Information Administration, EIA-860M Preliminary Monthly Electric Generator Inventory, September 2026, Operating sheet, row 6277 (the Northeast (WA) entry), plant ID 6210 (operator Avista Corp, 61.8 MW natural gas combustion turbine, in service December 1978, planned retirement December 2035); the Planned sheet lists no planned gas unit in Spokane or Stevens County. The Operating sheet also lists Avista's Kettle Falls Generating Station unit 2 in Stevens County (7.2 MW natural gas combustion turbine, row 934) and six 4.1 MW natural gas engines at Boulder Park in Spokane County (rows 8050 to 8055), none with a planned retirement. ↩
- Federal Register, FERC Combined Notices of Filings, documents 2026-17846 (September 1, 2026), 2026-18036 (September 3, 2026), 2026-20747 (October 9, 2026), 2026-17633 (August 28, 2026) and 2026-21490 (October 21, 2026), found by a Federal Register search of FERC notices published July 31 to October 29, 2026 for "Northwest Pipeline" and "Gas Transmission Northwest" (the search for Spokane County, Stevens County and Spokane returned none). The Northwest Pipeline filings are a NAESB standards compliance filing (RP26-1099), a 2026 winter fuel filing (RP26-1161) and a rate filing on non-conforming service agreements (RP27-2); the Gas Transmission Northwest filings are NAESB compliance filings and the settlement petition in note 19. ↩
- Northwest Pipeline LLC, Northwest Notice 26-038, critical maintenance notice posted March 12, 2026, Notice Text (from Northwest Pipeline's own posting site, northwest.williams.com; accessed October 29, 2026). The notice names Puget Sound Energy as operator of Jackson Prairie storage; we paraphrase it. The notice says the operator reported a "malfunctioning component at JP Storage currently preventing injection capability". ↩
- Avista Corporation, 2025 Natural Gas Integrated Resource Plan, Chapter Five, PDF 125 (Table 5.3 lists Jackson Prairie max deliverability of 346,667 Dth per day for Avista North, tied to Avista's one-third ownership rights) and PDF 126 (Northwest Pipeline's Spokane, Coeur d'Alene and Lewiston laterals serve Washington and Idaho load). The plan's design day sits in other tables, so we have not computed a share of design day for Jackson Prairie. ↩
- NOAA Regional Climate Centers, Applied Climate Information System (ACIS) StnData web service, monthly heating degree days (base 65 degrees F) and 1991-2020 normals, November to March of winters 2023-24 to 2025-26, accessed October 29, 2026: Spokane International Airport (station USW00024157). Sums are our calculation. Heating degree days behind the percentages: 4466 in 2023-24, 4516 in 2024-25 and 4058 in 2025-26, against a 1991-2020 normal of 4745. ↩
- NOAA Climate Prediction Center, seasonal temperature outlook issued October 15, 2026 (shapefiles from ftp.cpc.ncep.noaa.gov/GIS/us_tempprcpfcst/seastemp_202610.zip), read at the Spokane location. The map gives the favored category and the lower edge of its probability band; NOAA's explanation keeps near-normal at 33.3% and gives the opposite category the rest, so for both periods Spokane has at least a 50% chance of above-normal temperatures, about 33% near-normal and no more than 17% below-normal. ↩
- The station is Spokane International Airport; one airport station is not a measurement of the whole metro. The outlook figures are NOAA's probabilities for a three-month average and do not rule out cold days. ↩
- EIA said on October 6, 2026 that it expects U.S. natural gas inventories to enter the winter heating season 2% above the previous five-year average, and its October 2026 Short-Term Energy Outlook says prolonged periods of cold weather could increase withdrawals beyond its forecast (sources A1 and A2). EIA lists U.S. liquefied natural gas gross exports of 15 billion cubic feet per day in 2025, 18 in 2026 and 19 in 2027. NOAA's Climate Prediction Center puts the probability of at least a strong El Nino continuing through January to March 2027 at 80%. These are national and regional facts, not statements about Avista's system. ↩
- Federal Register, FERC Combined Notice of Filings, document 2026-21490, published October 21, 2026, page 66555: Gas Transmission Northwest LLC, docket RP27-45-000, "Compliance filing: Petition for Approval and Stipulation and Agreement of Settlement," filed October 15, 2026. Plan Table 5.3 lists Avista's GTN T-1 firm transportation; we did not read the settlement terms. ↩
Market and weather sources
Public web sources, as of October 25, 2026. They are context, separate from the regulatory record cited in the Notes. The Climate Prediction Center issues its seasonal outlook once each month near mid-month; this section is refreshed on the publication date.
- A1. U.S. Energy Information Administration, press release, "EIA expects a mixed picture for winter fuel costs this year," October 6, 2026. Link
- A2. U.S. Energy Information Administration, Short-Term Energy Outlook, October 2026 (natural gas storage). Link
- B1. NOAA Climate Prediction Center, Prognostic Discussion for Long-Lead Seasonal Outlooks, issued October 15, 2026. Link ↩
Sources
- Avista Corporation, 2025 Natural Gas Integrated Resource Plan. Link
- Washington Utilities and Transportation Commission, docket UG-240207, Revised Commission Acknowledgment Letter, September 26, 2025. Link
- Office of Management and Budget, OMB Bulletin No. 23-01, Revised Delineations of Metropolitan Statistical Areas, Micropolitan Statistical Areas, and Combined Statistical Areas, July 21, 2023.
- U.S. Energy Information Administration, EIA-860M Preliminary Monthly Electric Generator Inventory, September 2026. Link
- Federal Register, API search of Federal Energy Regulatory Commission notices by county. Link
- Avista Corporation (Avista Utilities), Data Centers and Your Energy (company web page). Link
- City of Spokane, City Council, News release: Spokane City Council Passes One-Year Moratorium on Data Centers, June 23, 2026. Link
- Federal Register (FERC Combined Notice of Filings), Combined Notice of Filings, Federal Register document 2026-21490, published October 21, 2026. Link
- Northwest Pipeline LLC (own informational postings), Northwest Notice 26-038, March 12, 2026 (critical, maintenance). Link
- NOAA Regional Climate Centers (ACIS web service), Monthly heating degree days base 65F and 1991-2020 normals, station USW00024157. Link
Corrected November 9, 2026: the earlier page said the transportation and storage totals cover Avista North or the whole company; the plan's Table 5.3 gives them for Avista North only.