Utah natural gas case study, Salt Lake City area, Utah. November 2026

Salt Lake City area gas capacity: key gate stations are projected at their limits

Enbridge Gas Utah projects its Riverton gate station at 100 percent of capacity in 2026-27; expansion is due in 2029. Sunset and Eagle Mountain are limited by upstream pipelines. Business customers should watch large-load requests and interruption terms.

1.30 MMDthEnbridge Gas Utah's forecast firm sales demand on the 2026-27 design day, company-wide (June 2026 plan)
100%Riverton gate station's projected use of its own capacity, 214.0 of 214.0 MMcfd, 2026-27 (utility projection)
2 of 3Gate stations limited by upstream pipelines that are inside the four counties (Sunset and Eagle Mountain)
17 and 3Data-center or onsite-generation inquiries and signed agreements, Enbridge Gas Utah, June 2026

Metro used: the Salt Lake City area, Utah: Salt Lake, Tooele, Davis and Utah counties. The federal definition of the Salt Lake City metropolitan area (CBSA 41620) lists Salt Lake and Tooele counties. Davis and Utah counties are added because Enbridge Gas Utah serves all four from one integrated system and its plan names gate stations in each of them.1

Key takeaways

  • In February 2025 Enbridge Gas Utah covered a same-day supply shortfall from its Magna LNG plant; its filings do not say whether any customer lost service.6
  • The utility says its supplies, contracts and gate stations are adequate for its coldest planning day; the Commission has not yet acted on the 2026-27 plan.2
  • Riverton is projected at its full station capacity in 2026-27, three heating seasons before its expansion is due to begin construction.3
  • Upstream pipeline limits, not the stations, constrain Sunset in Davis County and Eagle Mountain in Utah County, where upstream capacity is 9.5 MMcfd against 25.4 assumed.4
  • The utility states no gas volume for any signed large-load agreement; a February 2026 air permit application proposes 17 gas-fired turbines at Eagle Mountain for a nearby data center.14
  • The December 2025 rate case order kept interruptible customers out of design-day costs and closed the discounted TBF class to new customers pending a large-load study.8
  • The Riverton gate station projection, the February 2025 supply event and the upstream limits are the documented reasons for the outlook.3

What is the outlook for Salt Lake City-area gas capacity through 2029?

Discovery Energy rates the outlook for Salt Lake City-area natural gas capacity through 2029 as High (confidence: High): the utility's own projections put the Riverton gate station in southwest Salt Lake County at full capacity in 2026-27, three heating seasons before its expansion is due to begin in 2029.37 Two more documented problems add to this. In February 2025 the utility had to use its Magna LNG plant to cover a supply shortfall. The utility also says two of its gate stations in the four counties are limited by upstream pipelines. Documented risk factors: a recent supply event (a shortfall in supply that actually happened), since MountainWest Pipeline notified Enbridge Gas Utah in February 2025 that demand at its gate stations was exceeding the supply available, the utility called on its Magna LNG plant and its Key Accounts group told customers to limit usage.6 The second is an upstream limit (a limit on the pipeline that feeds a gate station), since the utility says the Sunset gate station in Davis County is limited by upstream limitations on MountainWest's system.4 It says the Eagle Mountain gate station in Utah County is limited upstream of its handover point with Kern River; both stations are inside the four counties.13 Three developments would change the assessment: a Commission order or utility filing stating a design-day shortfall or a customer interruption on the Salt Lake, Tooele, Davis or Utah County systems; the Riverton 2029 date slipping or projected use rising above 100 percent in a later plan, or Riverton and Porter Lane work brought forward or use falling below 80 percent, or the utility reporting that the Sunset or Eagle Mountain upstream limits have been lifted; the large-load study due by the end of 2026, or the utility's load-scenario analysis, naming a constraint in the four counties.

Outlook levels, from least to most concern: Stable, Watch, Elevated, High, Severe. Levels describe the public record of capacity and supply risk; confidence is reported separately. They are qualitative assessments, not forecasts of outages.

Other dates to watch: the Commission's order on the 2026-27 plan, the storage decision, and any federal filing on the MountainWest interconnect transfer expected in 2027.12

Who serves the Salt Lake City area?

Questar Gas Company, doing business as Enbridge Gas Utah, serves all four counties from one integrated system, and its plan names gate stations by location. It names Davis County only through the city of Sunset.1 The table classifies each item against the four counties; where the plan names no county, the item is unclear and is not placed inside.1

Item Place named Classification Basis
Riverton gate station Southwest Salt Lake County Inside County named in the plan
Hunter Park gate station Supplies the Salt Lake valley Inside Plan describes the Salt Lake valley
Porter Lane and Westport gate stations County not stated Unclear No county in the plan
Rose Park gate station Wasatch Front Unclear Plan names a region, not a county
Sunset gate station Sunset, Davis County Inside Davis County's city list includes Sunset
Eagle Mountain gate station Utah County Inside County named in the plan
Feeder lines FL 35 and FL 41 Tooele County Inside County named in the plan
Magna LNG plant Salt Lake County Inside County named in the plan
West Side large-load requests West Jordan, west side of the Salt Lake valley Inside City named in the plan; county assigned manually
Central gate station St. George area Outside, system context Not in the four counties
Rockport gate station Summit and Wasatch counties Outside, system context Not in the four counties
Ruby Pipeline tap gate station Near Brigham City Outside, system context North of the four counties

Classification of items in Enbridge Gas Utah's 2026-27 plan against the four counties; unclear items are not placed inside.

The plan's figures are company-wide or station-by-station, and the plan does not split them by county, so they describe the whole system. Stations outside the four counties are shown because the same pipelines feed them; Central's capacity, for example, is set by Kern River's delivery pressure, and Kern River also hands gas over at Eagle Mountain.4

Has the Salt Lake City area had gas supply problems since 2020?

In February 2025 Enbridge Gas Utah called on its Magna LNG plant to cover a same-day supply shortfall. In a presentation to the Commission in April 2025 the utility said actual temperatures were dramatically colder than forecast, that the upstream pipeline called for matching demand and supply but too late in the day to buy more, and that it called on the plant for an additional 70,000 Dth of same-day supply. Supply began flowing in 15 minutes and reached the full requested rate in 1.5 hours. The utility's 2025 resource plan names the pipeline: MountainWest Pipeline notified the utility that demand at the gate stations it serves exceeded the supply available.6

The utility's Key Accounts group notified customers to limit usage to match their scheduled supply. The filings do not say which customers were notified, how many, or whether any customer lost service. The Commission's January 2026 order records the event in one footnote and made no finding on cause. The same quarter was otherwise warmer than the plan forecast for December 2024 through February 2025.6

Discovery Energy's classification: a one-day upstream supply and balancing event after a forecast miss, met by on-system LNG. It shows a reliability exposure at the pipeline interface, not a chronic shortage of local delivery capacity. The record is the utility's own; no pipeline notice from February 2025 survives, because the pipelines post only about 90 days. The utility says other major supply events since 2020 occurred elsewhere and did not have a major impact on its physical supply. Winter 2025-26 was warmer than normal, with 45 colder-than-normal days and 137 warmer-than-normal days in the utility's count.69

How much spare gas capacity does the Salt Lake City area have on the coldest day?

Pipelines supplying the Salt Lake City area N Kern River Kern River Ruby Pipeline Ruby Pipeline MountainWest Pipeline (Questar) MountainWest Pipeline (Questar) Ruby Pipeline Ruby Pipeline MountainWest Pipeline (Questar) MountainWest Pipeline (Questar) Kern River Kern River MountainWest Pipeline (Questar) MountainWest Pipeline (Questar) Northwest Pipeline Northwest Pipeline Northwest Pipeline Northwest Pipeline Salt Lake City Salt Lake City West Valley City West Valley City West Jordan West Jordan Provo Provo Davis County Davis County Salt Lake County Salt Lake County Tooele County Tooele County Utah County Utah County Lehi Lehi Orem Orem Ogden Ogden Layton Layton Eagle Mountain Eagle Mountain Taylorsville Taylorsville Spanish Fork Spanish Fork Riverton Riverton Bountiful Bountiful Springville Springville Magna Magna Payson Payson I-80 I-80 I-15 I-15 Box Elder County Box Elder County Carbon County Carbon County Duchesne County Duchesne County Elko County Elko County Juab County Juab County Millard County Millard County Summit County Summit County Uinta Co. Uinta Co. White Pine County White Pine County Pipelines supplying the Salt Lake City area Other gas pipelines Highways Salt Lake City metro area (4 counties) County lines Cities and towns
Figure 1. Major natural gas pipelines serving Salt Lake City. Simplified, not to scale. Discovery Energy illustration from EIA and U.S. Census data. Coastline, lakes and highways: Natural Earth (public domain).

In words: what the map shows

  • Pipelines labeled: Northwest Pipeline; MountainWest Pipeline (Questar); Ruby Pipeline; Kern River.
  • Metro counties outlined (4): Davis County; Salt Lake County; Tooele County; Utah County.
  • Cities and towns labeled include: Salt Lake City; West Valley City; West Jordan; Provo; Lehi; Orem; Ogden; Layton.
  • Other gas pipelines in the area are drawn in gray and are not labeled.
  • Highways are drawn for orientation. A small state locator map sits in a corner.

Enbridge Gas Utah plans for a design day of 70 heating degree days in the Salt Lake region, 9.5 mph mean wind and a day that is not a Friday, Saturday, Sunday or winter holiday. For that day it forecasts firm sales demand of 1.29 MMDth at the city gates for 2025-26 and 1.30 MMDth for 2026-27, company-wide figures. Its modeling shows adequate supplies to meet that demand, and it says contracted transportation is adequate. Volumes above its firm rights on MountainWest's no-notice service are provided "on a best-efforts basis" and could be interrupted unless firm peaking service is used.2

These are utility forecasts. The Commission "acknowledged" the 2025 plan in January 2026 as generally complying with its standards and made no finding that capacity is adequate. The 2026-27 plan was filed in June 2026; the Division of Public Utilities and the Office of Consumer Services filed comments in September 2026 and the utility replied in October 2026. No order has been issued.2

The plan also projects each gate station's coldest-day flow against that station's capacity. Where a gate station is near its capacity, the utility starts a review of when to upgrade it once projected use reaches 80 percent.3

Station Place and classification Maximum design-day flow (MMcfd) Station capacity (MMcfd) Projected use, 2026-27 Capacity minus flow (MMcfd, calculated) Same measure in the 2025-26 plan
Riverton Southwest Salt Lake County; inside 214.0 214.0 100% 0.0 90%
Porter Lane County not stated; unclear 130.0 136.7 95% 6.7 73%
Hunter Park Supplies the Salt Lake valley; inside 367.0 400.0 92% 33.0 92%
Westport County not stated; unclear 21.2 36.2 58% 15.0 53%
Rose Park Wasatch Front; unclear 100.0 400.0 25% 300.0 26%
Sunset Davis County; inside; limited by the upstream pipeline 50.0 92.8 54% 42.8 65%
Eagle Mountain Utah County; inside; limited upstream of the handover point 8.3 9.5 88% 1.2 89%

Selected gate stations in Enbridge Gas Utah's 2026-27 plan inside or unclear against the four counties: coldest-day projections (utility projections, not measured flows).3

System context: Central in the St. George area, outside the four counties, is projected at full capacity, with flow of 75.1 MMcfd above its capacity of 47.5 MMcfd set by Kern River's guaranteed delivery pressure. Rockport, in Summit and Wasatch counties, is projected at 90 percent (15.0 of 16.7 MMcfd).3

Each percentage is one station's projected maximum flow divided by its own capacity; the margins should not be added together. Riverton has no margin in the projection. The utility says it can shift gas between Salt Lake-area stations, but that "with population growth and large industrial customers coming onto the system, this flexibility is becoming more limited", and that there is a particular need to send more gas into Tooele County through two feeder lines from Riverton. Hunter Park is not expected to need more capacity soon, the utility says, because of its remaining margin, the nearby Rose Park station and the planned Riverton expansion.3

Stations limited by the upstream pipeline

Two stations inside the four counties are limited by the pipeline that feeds them rather than by the station itself. The utility says Sunset's capacity is limited "not by the facility, but due to upstream limitations on MWP's system", and that at Eagle Mountain the capacity upstream of the transfer of custody with Kern River is only 9.5 MMcfd, well below the 25.4 MMcfd it had assumed. Sunset is in Davis County and Eagle Mountain in Utah County.4

The Magna LNG plant adds a cushion. Its send-out rate of 150,000 Dth per day is described by the utility as about 10 percent of Wasatch Front design-day load; against the 1.294 MMDth design-day total in its 2025-26 supply plan the rate is 11.6 percent by our calculation. The tank was full in July 2026. The utility's filings forecast about $2.2 million of gas and $0.9 million of electricity to fill the tank for 2025-26. The filings reviewed do not say how those costs are recovered from customers, or what the February 2025 send-out cost.9

What is driving new natural gas demand?

We found one documented gas-fired generation project in the four counties and no filing gives a gas volume for it or for any signed large-load agreement. The utility's own count of large-load requests is the main evidence of growth.5

Enbridge Gas Utah says "Since the early 2020s the Company has been seeing an increase in the number of large industrial service requests", largely associated with data centers and general power generation, with a higher concentration on the west side of the Salt Lake valley, specifically West Jordan. Large power-generation customers earlier ran at a partial contract load until paid pipeline improvements were completed, which is why the utility corrected its 2025 design-day growth figure to 1.1 percent. Across the whole system, design-day demand has grown about 1.3 percent a year and customers about 2.1 percent a year over five years.5

Item Figure Source and date
Inquiries for data-center or onsite electric generation service 17 Utility resource plan, June 2026
Signed agreements for this type of facility 3: two in service, the third expected in the fourth quarter of 2026 (the utility's expectation, not a confirmed service date) Utility resource plan, June 2026
Expected service type Firm transportation customers; customers pay for system improvements upfront; no Company-owned gas supply Reply comments, September 2025; resource plan, June 2026
Time from signing to construction Generally at least 18 months Utility resource plan, June 2026
Gas volume of any signed agreement Not stated No reviewed filing gives it

Large-load requests at Enbridge Gas Utah (utility statements to the Commission; counts only).5

The utility says it is unlikely that all inquiries will be built, since some prospective customers declined to contract after learning the estimated costs. Whether the in-service agreements are for data centers or for other onsite generation is not stated; the utility describes them as "for this type of facility". It also expects growth on the west side of Salt Lake City to require a new Kern River gate station in the mid-to-long term, with no date or cost given.5

The utility says data-center or power-generation growth there could accelerate that station with cost support from the new customers. The Office of Consumer Services says all incremental costs to serve new large loads should be assigned to those customers and asked in September 2026 for a load-scenario sensitivity analysis. The utility replied in October 2026 that it can do the analysis and wants to agree the study design first.5

Data centers: As of October 29, 2026, we found one proposed gas-fired plant for a data center in the four counties. In February 2026 Will-Power UT, LLC submitted a Notice of Intent to the Utah Division of Air Quality to build a power generation facility at 1499 N Pony Express Parkway, Eagle Mountain, in Utah County, with 17 natural gas-fired simple cycle turbines to provide primary power exclusively and directly to a nearby, separately owned and operated data center.14

The application says the turbines would use pipeline-quality natural gas but names no pipeline, utility, gas volume or service date, so the record does not show whether the plant would draw on Enbridge Gas Utah's system. An exhibit filed with the Commission in May 2026 (see note 14) lists Will-Power UT, LLC's power generation air permit, UDEQ Site ID 16322, as pending, and it also states no in-service date, pipeline or gas volume.14

Will-Power's November 2025 notice to the Commission describes Project Aquila, the project in that exhibit, as generation of up to 286 megawatts at Eagle Mountain with a 20-mile service pipeline that Will-Power would build, own and operate, but does not say what gas source would feed that pipeline, which leaves open whether this is a bypass of the utility.18 On October 26, 2026 Will-Power told the Commission its application was complete, and Rocky Mountain Power's declaration repeats Will-Power's statement that the plant would be isolated from its electric system.19

Elsewhere in the four counties: EIA's September 2026 generator inventory lists no planned natural gas-fired generator in Salt Lake, Tooele, Davis or Utah County.14 Our Federal Register search since January 1, 2025 found four FERC notices that name Utah County, all on Magnum Gas Storage's 2025 Amendment Project, a gas storage project with facilities in Millard, Juab and Utah Counties; none names Enbridge Gas Utah or ties the project to a gas load.24 EIA lists US Magnesium's three 16 MW gas turbines in Tooele County as retired in December 2025, and no gas unit in the four counties with a planned retirement; these are electric generators, not a loss of gas supply.22

Are upgrades arriving in time?

Item Status as stated by the utility Date stated What the filing does not say
Magna LNG plant, Salt Lake County Operating; built September 2022; 15,000,000 gallon tank full in July 2026; used in February and March 2025 In service Any use rule beyond the Commission's January 2026 request for a statement of principles
Riverton gate station expansion Early planning; property secured; cost not yet estimated Construction 2029 (also 2029 in the 2025 plan) Any interim relief before 2029
Hunter Park gate station No expansion planned; capacity increase not expected soon None What happens if projected use rises above 92 percent
New Kern River gate station, west side of Salt Lake City Expected to be needed in the mid-to-long term; possible acceleration with cost support from new large customers No date Cost, site, or who commits to pay
Added storage Request for proposals for up to 23 Bcf; responses received April 2026; no contract; price terms and decision to be presented later Service no later than April 2031 Whether any proposal is selected
New Kern River transportation contract New contract per the July 2026 utility slide Begins November 2026 Volume and delivery point for the Wasatch Front
MountainWest interconnect ownership transition Under review with MountainWest; needs FERC approval Closing not expected before 2027 Effect on capacity

Remedies operating, planned or proposed (dates are utility plans stated in filings, not Commission approvals of each project).10

Timing is the issue the filings leave open. Riverton's expansion is not expected to begin construction until 2029, three heating seasons after the 2026-27 projection (calculated from the utility's dates). Between the utility's July 2025 and July 2026 presentations, the Central gate station project moved from 2028 to 2030 and the Eagle Mountain project from 2029 or 2030 to 2031; Riverton held at 2029. The Eagle Mountain project is the station whose upstream capacity is limited, and its date moved later.10

A new large customer that signed in late 2026 would not be built before 2027 or 2028 on the utility's timeline of at least 18 months. The utility links a possible new Kern River gate station to growth on the west side of Salt Lake City in general, not to a named customer. No filing links any specific remedy to a named new load, and this page does not either.5 Kern River told a Utah legislative committee in June 2026 that new capacity "is not immediately available", needs federal approval that may take two years or more, and must be funded by its project customers.10

What does this mean for business gas costs?

Who pays has been decided for now, with a large-load study still open

The Commission's December 2025 order in Enbridge Gas Utah's rate case (note 8) approved an increase of about $60.2 million in distribution rates, on a stipulated revenue requirement of $604 million. On cost allocation, Enbridge Gas Utah spreads capacity-related costs using a factor weighted 60 percent to design-day demand and 40 percent to throughput. Position by party, as the order reports them: Nucor Steel-Utah asked to keep 60/40 but measure throughput by winter months; the Federal Executive Agencies asked for 60 percent excess demand and 40 percent throughput; the Utah Association of Energy Users asked for 66/34; the Division of Public Utilities asked to keep 60/40 but base the load factor on actual peaks. The Commission kept 60/40.8

No party recommended changing the utility's practice of excluding interruptible customers from design-day costs, and the Commission affirmed it. The Commission also temporarily closed the TBF class, a discounted transportation class, to new customers pending a study of new large loads, including data centers, due by the end of 2026. The Office of Consumer Services said it was concerned that new large customers on the discounted rate could burden residential and small commercial ratepayers; the utility agreed the class needed study.8

The order also observes that the utility may have added TBF customers without required Commission approval and directs it to file a list. The order does not state the effect of these allocations on any other customer class, and this page does not either. Amounts above are approved amounts; nothing here shows what any customer was billed or paid.8

Service terms matter before rates change

Interruptible customers carry the exposure. Tariff section 3.01 says they are "solely responsible for all financial and other consequences" of failing to interrupt, and section 3.02 sets a $40 per dekatherm penalty plus a move to firm service for three years. These are tariff terms; the filings reviewed do not show that any penalty was assessed.11

Who gets gas first in a shortage?

Enbridge Gas Utah's tariff PSCU 800 puts interruptible customers first. Section 3.02, Periods of Interruption, reads:

  • "subject to temporary periods of interruption upon notice by the Company whenever the Company determines interruption is required"
  • "no later than two hours from the issuance of the notice to discontinue use"
  • "will incur a $40-per-dekatherm penalty for all interruptible volumes utilized during the course of an interruption"
  • "interruptible transportation and sales customers will be required to interrupt partially on a pro rata basis based on representative daily use levels"

11

Termination priority Customers
1st Interruptible Service. All use
2nd Firm commercial and industrial service using more than 3,000 Dth per month
3rd Firm commercial and industrial service using at least 2,250 and no more than 3,000 Dth per month
4th Firm commercial and industrial service using at least 1,500 and no more than 2,249 Dth per month
5th Residential and all remaining commercial and industrial service

Emergency restrictions in a major disaster or pipeline break: order of restriction in tariff section 7.03.11

The tariff states that "restrictions will be made in the following order", to the extent practicable and prudent. Section 5.07 adds that firm sales service has priority over interruptible sales and all transportation service, and that firm transportation has priority over interruptible transportation. The tariff states no ranked order among interruptible customers. The utility's design-day models assume interruptible demand is curtailed. Its 2025 interruption analysis estimates the temperature at which curtailment of interruptible customers becomes likely at -6 degrees F for the zones covering southern Salt Lake County, northern Salt Lake County and Tooele County; these are utility estimates. The filings do not say whether any interruption notice was issued in February 2025.11

Winter and market context

We found no Kern River or MountainWest critical notice that names an Enbridge Gas Utah delivery point, but both pipelines keep only about 90 days of postings, so February 2025 and winter 2025-26 cannot be reviewed. The Kern River capacity form needs a browser to open, so it is not covered here.21

Winter weather and NOAA's outlook

Heating degree days, a measure of how much heating the weather called for, ran below the 1991-2020 normal at the Salt Lake City International Airport station in each of the last three winters, and 2025-26 was the mildest.15 NOAA's Climate Prediction Center outlook issued October 15, 2026 shows equal chances of above-, near- and below-normal temperatures for December 2026 to February 2027 and a lean toward above-normal for November 2026 to January 2027.16 The airport is one station standing in for the metro, and NOAA's figures are probabilities for a three-month average, not a forecast of specific days.17

Winter (November to March) Heating degree days 1991-2020 normal Difference from normal
2023-24 3753 4147 -9.5%
2024-25 3786 4147 -8.7%
2025-26 3020 4147 -27.2%

Heating degree days at the Salt Lake City International Airport station, base 65 degrees F, against the 1991-2020 normal. Source: NOAA Regional Climate Centers.

What's new (as of October 29, 2026)

On October 26, 2026 Will-Power told the Utah Commission its application for a private power contract for Project Aquila, its Eagle Mountain plant, was complete, which it says starts a 60-day review.19 The Commission's docket for the 2026-27 plan shows reply comments on October 6, 2026 and no order as of October 29.20 Kern River, MountainWest and Ruby Pipeline filings published from August 6 to September 15, 2026 are standards, fuel and rate filings that name no county or load.21

What should Salt Lake City-area manufacturers check now?

  • Tariffs and charges, through a utility audit. Confirm each account is on the right rate class and tariff, and that riders, demand charges and capacity-related charges are billed correctly. Over 70% of the clients Discovery Energy has audited were billed incorrectly. An audit verifies tariffs and charges and recovers overcharges before winter costs rise.
  • Your actual service election. Confirm whether each meter is firm sales, firm transportation or interruptible, and which class you are in (TBF, TSS, TSM, TSL or IS). The emergency restriction order in section 7.03 and the priority in section 5.07 depend on it.
  • Interruption and penalty terms. Interruptible customers must stop within two hours of notice, face a $40 per dekatherm penalty and a three-year move to firm service if they fail, and bear their own losses. Check your contact details on file, because notice can go out by text or email.
  • Backup arrangements. Interruptible customers must keep a backup system or be able to fully interrupt. Test it, and check fuel supply for the length of a winter event.
  • Large-load and rate case developments. If you plan new or increased load, tariff section 9.02 lets the utility approve service only when it will not impair service to existing customers. Watch the TBF large-load study due by the end of 2026 and the Commission's order on the 2026-27 plan.

What to check in your contracts

Area What to check
Winter price spikes Whether the gas is priced on a daily or a monthly index, how large the local basis (the gap between the local price and the national benchmark) has been in cold weather, and how much of your winter use is covered by fixed-price volumes.
Delivery constraints Whether your transportation is firm, what delivery obligations your supplier carries and what happens if it cannot deliver, and what the curtailment provisions say about who is cut first.
Operational flow orders What balancing obligations the contract places on you, and whether penalties that a pipeline or utility charges under an operational flow order are passed through to you.
Expansion plans Where a utility or pipeline plans added capacity, whether the utility has confirmed in writing the incremental hourly and daily capacity available to your site, and from what date.

Checks for gas supply and transportation contracts. They are questions to put to your supplier or utility, not financial advice.

Frequently asked questions

Is the Salt Lake City area running out of natural gas capacity?

No shortfall is stated in the filings reviewed, but the utility's own projection puts the Riverton gate station at its station capacity and the Commission has not yet acted on the 2026-27 plan. See 'How much spare gas capacity does the Salt Lake City area have on the coldest day?'

Which counties does this page cover, and why?

It covers Salt Lake, Tooele, Davis and Utah counties. Davis and Utah counties are added because Enbridge Gas Utah serves all four from one integrated system, and its plan names gate stations in each. See 'Who serves the Salt Lake City area?'

What happened with Salt Lake City-area gas supply in February 2025?

The utility says temperatures were much colder than forecast and the upstream pipeline called for balancing too late to buy more gas, so it used its Magna LNG plant. The filings do not say whether any customer lost service. See 'Has the Salt Lake City area had gas supply problems since 2020?'

Who loses gas first if supply is short in the Salt Lake City area?

Under tariff PSCU 800, interruptible service is interrupted first, then firm commercial and industrial customers, starting with the largest. The tariff states no ranked order among interruptible customers. See 'Who gets gas first in a shortage?'

Are data centers adding to Salt Lake City-area gas demand?

The utility reports inquiries and signed agreements but no gas volume, and a proposed gas-fired plant at Eagle Mountain names no gas supplier or service date, so the effect on capacity is not shown. See 'What is driving new natural gas demand?'

Who pays for new gas capacity in the Salt Lake City area?

The Commission kept its cost allocation factor and kept interruptible customers out of design-day costs, and closed the discounted TBF class to new customers until a large-load study. See 'What does this mean for business gas costs?'

Discovery Energy publishes gas capacity case studies for other metros, using the same method and outlook scale.

All gas capacity ratings by U.S. metro

Background for commercial and industrial energy buyers: Utility cost intelligence

Understand your capacity exposure

Discovery Energy reviews service elections, interruption terms and regulatory proceedings for organizations across the U.S. and Canada, so capacity changes are understood before they reach the bill.

Schedule a review

What this page does not cover

  • Exactly which parts of each of the four counties Enbridge Gas Utah serves. The extent of the service territory in each county is not confirmed from a tariff map.
  • Whether the Commission has found Enbridge Gas Utah's capacity adequate. The record we reviewed has no such finding.
  • What customers would experience in a shortage. The record we reviewed gives no customer-level impacts.

Notes

  1. Scope and boundary: the gas distribution system of Enbridge Gas Utah. The metro crosswalk for CBSA 41620 lists Salt Lake and Tooele counties; Davis and Utah counties are added to the metro crosswalk list as part of this page's boundary. The extent of the service territory in each county is not confirmed from a tariff map; the plan names gate stations in all four. Davis County: the county's own city list includes Sunset (Davis County, Cities page, accessed October 2026). West Jordan is assigned to Salt Lake County manually. Our classification of each item against the four counties is kept in our working files. Periods covered: 2025 to October 2026. The record read gives no customer-level impacts and no Commission finding on capacity adequacy. The utility says its ability to shift gas between gate stations in the Salt Lake area counties is becoming more limited, and its gate station table names stations in Davis County (Sunset) and Utah County (Eagle Mountain). Items are classified inside, outside or unclear using the place names in the utility's plan; items outside the four counties are shown as system context. ↩
  2. Utility forecast: Enbridge Gas Utah 2026-27 resource plan, docket 26-057-02, PDF 5 and 6; Commission order of January 2026 in docket 25-057-02, PDF 1 and 7. Company-wide figures; the Commission "acknowledged" the plan and made no finding that capacity is adequate. ↩
  3. Gate-station projections come from Table 4.2 of the 2025-26 and 2026-27 resource plans (stations with an expected maximum design-day flow above 5 MMcfd; 28 rows each year). Percentages are printed in the plan and were recomputed by us; Central's flow exceeds its capacity and is printed as 100 percent. The capacity-minus-flow column is calculated here and is illustrative. A seventh station above 80 percent, Evanston South in Wyoming, is outside the four counties and not shown. The 2025-26 plan's table prints Riverton at 90 percent while its text calls Riverton "listed as 100% utilization". ↩
  4. Upstream-limited stations: 2026-27 resource plan, PDF 47 and 48 (Sunset, Central, Eagle Mountain). The plan states no county for Sunset; Davis County is from the county's city list (note 1). Eagle Mountain's county is stated in the plan. Utility statements, not Commission findings. Counted as an upstream pipeline limit under Discovery Energy's outlook scale because both stations are inside the four counties. ↩
  5. Data-center figures: this page uses counts only. The September 2025 reply comments give a total of 1,038 mmcf/day if all inquiries then pending were built and describe requested daily volumes of 2 to 240 mmcf/day per inquiry; the June 2026 plan gives about 4 Bcf/day if all 17 were built without saying whether the figure is requested, peak, annual or contracted volume. The second total is 3.85 times the first with fewer inquiries, and no document explains the change, so the units and basis could not be confirmed. Inquiries are not operating demand. No generator size or heat rate appears in the reviewed filings, so no gas-burn calculation was run. ↩
  6. February 2025 event: Enbridge Gas Utah presentation to the technical conference of April 2025, PDF 19; 2025 resource plan, PDF 143; Commission order of January 2026, footnote 7; third quarter variance report, docket 24-057-04. Utility statements. ↩
  7. Riverton expansion: 2026-27 resource plan, PDF 62 and 66; utility slide of July 2026, PDF 6. Cost not yet estimated. ↩
  8. Rate case: Commission order of December 2025 and Order Altering of April 2026 in docket 25-057-06; party positions are as the order reports them, not findings. The order's class tables are not reproduced here because the order states no class-level bill effect. Storage-cost allocation was not addressed in the order text reviewed. ↩
  9. Context and calculations are illustrative: the 11.6 percent LNG rate is 150,000 Dth per day divided by 1,294,000 Dth, the design-day total in the 2025-26 supply plan, whose chart labels it in thousand Dth; the three heating seasons for Riverton are the years from 2026-27 to the 2029 construction start. LNG tank figures: 2026 resource plan, PDF 145; utility slide of July 2026, PDF 15. The 11.6 percent is 150,000 divided by 1,294,000. ↩
  10. Remedy dates are utility plans from its July 2025 and July 2026 presentations and its June 2026 plan, not Commission approvals of each project; Kern River statement: slides to the Utah legislative interim committee, June 2026. ↩
  11. Tariff PSCU 800 text is from the compliance tariff filed in January 2026 and acknowledged by the Commission in February 2026; later corrections concerned only the volumetric rates for one class. Utah has no separate gas curtailment-priority rule that we found; the administrative rules on gas service were not read. Penalty provisions are exposure, not evidence that any penalty was assessed or paid. For example, by our calculation a plant using 1,000 Dth a day that kept using interruptible gas through a notice would face about $40,000 in penalties for each day of unauthorized use. ↩
  12. Pipeline postings: the Kern River and MountainWest capacity postings cover about 90 days. Tested in October 2026: the first day with real scheduled flows on the MountainWest page was July 2026. Winter 2025-26 and February 2025 are therefore not available, and no utilization figure for a delivery point is given on this page. The Kern River capacity form requires a browser; the MountainWest page can be read without one. Critical notices on both sites reach back only to mid-2026 and name no Enbridge Gas Utah delivery point. ↩
  13. Risk factors in Discovery Energy's outlook scale: a recent supply event and an upstream pipeline limit are counted (notes 6 and 4). Concentration, expiring supply and new load ahead of a fix are not counted: no filing states a single source's share of the design day (Magna LNG is described as about 10 percent of Wasatch Front design-day load with no defined denominator), no key contract is named as ending without a decided replacement, and no new load has a filing-confirmed service date (the fourth quarter of 2026 for the third signed agreement is the utility's expectation, not a confirmed service date). A more likely design day and LNG supply availability stress are not documented. The upstream limit for Central is not counted because the station is outside the four counties. ↩
  14. EIA-860M September 2026 Planned sheet filtered by county and Federal Register FERC notices since January 2025 searched by county for pipeline (CP) dockets, both our own calculation; Utah Division of Air Quality Notice of Intent, Will-Power UT, LLC, Eagle Mountain, February 2026 (PDF 4, 5 and 7), an applicant filing as submitted, not an agency decision. The air permit application states no in-service date. The Commission's docket 26-2660-01, Exhibit E (Will-Power UT, LLC, Project Aquila permits, PDF 2, dated May 7, 2026 by its file name), a regulator docket exhibit as filed, shows the power generation air permit, UDEQ Site ID 16322, as pending. ↩
  15. NOAA Regional Climate Centers, Applied Climate Information System (ACIS) StnData web service, monthly heating degree days (base 65 degrees F) and 1991-2020 normals, November to March of winters 2023-24 to 2025-26, accessed October 29, 2026: Salt Lake City International Airport (station USW00024127). Sums are our calculation. Heating degree days behind the percentages: 3753 in 2023-24, 3786 in 2024-25 and 3020 in 2025-26, against a 1991-2020 normal of 4147. ↩
  16. NOAA Climate Prediction Center, seasonal temperature outlook issued October 15, 2026 (shapefiles from ftp.cpc.ncep.noaa.gov/GIS/us_tempprcpfcst/seastemp_202610.zip), read at the Salt Lake City location. For November 2026 to January 2027 the map favors above-normal in the lowest probability band, which we read as at least 33% above, about 33.3% near-normal and no more than 33.7% below-normal; for December 2026 to February 2027 it shows equal chances, about 33% for each category (NOAA's explanation keeps the middle category near 33.3%). ↩
  17. The station is Salt Lake City International Airport; one airport station is not a measurement of the whole metro. The outlook figures are NOAA's probabilities for a three-month average and do not rule out cold days. ↩
  18. Will-Power UT, LLC, Notice of Registration as a Large-Scale Generation Provider, dated November 24, 2025, Utah Public Service Commission docket 25-266-01, PDF 3 (paragraph 10: Project Aquila in Eagle Mountain, generation of up to 286 megawatts, a twenty-mile service pipeline, co-located with the customer's industrial property) and PDF 4 (paragraph 14: wholly separate from facilities of any electric utility). Applicant filing, accessed October 29, 2026. The notice names no gas supplier and does not name the customer. ↩
  19. Williams Companies, cover letter dated October 26, 2026 for Will-Power UT, LLC, Utah Public Service Commission docket 26-2660-01 (docket entry October 27, 2026), PDF 1: the filing completes the application, and Will-Power understands that the 60-day review period under Utah Code 54-26-302(4) starts with it; Declaration of Jacob Barker for Rocky Mountain Power, PDF 2, repeating Will-Power's representation that the generation facility is completely isolated from Rocky Mountain Power's transmission and distribution systems. The 60-day statement is Will-Power's understanding, not a Commission finding; the docket page lists no Commission order. ↩
  20. Utah Public Service Commission docket page for 26-057-02, accessed October 29, 2026: entries for the Division of Public Utilities and Office of Consumer Services initial comments (September 10, 2026), Enbridge Gas Utah's reply comments (October 6, 2026) and a Wexpro forward curve report (October 13, 2026) as the latest entry, with no order listed; Scheduling Order issued July 9, 2026, PDF 1, which sets reply comments for October 6, 2026 and no later step. ↩
  21. Federal Register, FERC Combined Notices of Filings: document 2026-15976 (August 6, 2026; Ruby Pipeline docket RP26-1026-000, fuel and power cost rate adjustment filed July 31, 2026), document 2026-17475 (August 27, 2026; Kern River docket RP26-1071-000, standards compliance filing of August 24, 2026) and document 2026-18842 (September 15, 2026; MountainWest Pipeline docket RP26-1101-001, amended standards compliance filing of September 9, 2026). Our Federal Register search of FERC notices from July 31 to October 29, 2026 found no notice naming Tooele, Davis or Utah County, Questar Pipeline, Enbridge Gas Utah or Eagle Mountain; the one Salt Lake County hit was a PacifiCorp hydropower notice. Pipeline postings themselves were not reviewed beyond note 12. ↩
  22. U.S. Energy Information Administration, EIA-860M Preliminary Monthly Electric Generator Inventory, September 2026, Retired sheet: US Magnesium, Tooele County, industrial combined heat and power, three natural gas combustion turbines of 16 MW each retired in December 2025 (rows 84 to 86); Payson City Corporation, Utah County, two natural gas engines of 2.0 and 2.5 MW retired in 2024. Our filter of the Operating sheet found no natural gas unit in Salt Lake, Tooele, Davis or Utah County with a planned retirement date. ↩
  23. NOAA's Climate Prediction Center said on October 15, 2026 that its November 2026 to January 2027 outlook favors above-normal seasonal mean temperatures for the northern tier and western third of the contiguous United States, a discussion that names regions and not counties (source A1). The U.S. Energy Information Administration said on October 6, 2026 that it expects U.S. natural gas inventories to enter the winter heating season 2% above the previous five-year average (source A2), and its October 2026 Short-Term Energy Outlook says prolonged periods of cold weather could increase withdrawals beyond its forecast (source A3). These are national and regional facts, not statements about Enbridge Gas Utah's system, and none of them is used to set the outlook on this page.
  24. Federal Register, Federal Energy Regulatory Commission notices that name Utah County, Utah, found by our search of notices since January 1, 2025 for county names in the singular and the plural; we saved the text of each notice. (a) Magnum Gas Storage, LLC; Notice of Amendment Application and Establishing Intervention Deadline and Request for Extension of Time, document 2025-07874, published May 6, 2025, 90 FR 19194 to 19196 (docket CP25-233-000): Magnum's amendment application of April 21, 2025: redesign the two authorized caverns for 5.2 billion cubic feet (Bcf) of working gas each and build two more caverns of the same size (the four together keep the authorized 21 Bcf), one more brine pond and two new interconnections, with Kern River and the Intermountain Power Plant; the existing authorization already includes interconnections with Kern River and Questar Pipeline. (b) Magnum Gas Storage, LLC ; Notice of Scoping Period Requesting Comments on Environmental Issues for the Proposed 2025 Amendment Project, document 2025-11482, published June 23, 2025, 90 FR 26576 to 26578 (docket CP25-233-000): notice opening environmental scoping for the 2025 Amendment Project. (c) Magnum Gas Storage, LLC; Notice of Schedule for the Preparation of an Environmental Assessment for the 2025 Amendment Project, document 2025-12260, published July 1, 2025, 90 FR 28740 to 28741 (docket CP25-233-000): notice of the schedule for the environmental assessment of the 2025 Amendment Project, described as 20.8 Bcf of working gas storage capacity in Millard, Juab and Utah Counties. (d) Mangum Gas Storage LLC; Notice of Availability of the Environmental Assessment for the Proposed 2025 Amendment Project, document 2025-23948, published December 30, 2025, 90 FR 61131 to 61132 (docket CP26-233-000): notice of availability of the environmental assessment, which places the end of the 61.5-mile header pipeline near Goshen in Utah County and describes two interconnection options to the Kern River Delta Lateral; Magnum says its purpose includes new firm and interruptible storage, hub and wheeling services in the western United States. None names Enbridge Gas Utah (Questar Gas) or a gas load; the storage site itself is near Delta in Millard County. We read the notices but not Magnum's application. ↩

Market and weather sources

Official public sources accessed October 25, 2026. They are separate from the record notes above.

  1. A1. NOAA Climate Prediction Center, Prognostic Discussion for Long-Lead Seasonal Outlooks, October 15, 2026. Link
  2. A2. U.S. Energy Information Administration, press release, "EIA expects a mixed picture for winter fuel costs this year," October 6, 2026. Link
  3. A3. U.S. Energy Information Administration, Short-Term Energy Outlook, October 2026. Link

Sources

  1. Utah Public Service Commission, Order, Enbridge Gas Utah Integrated Resource Plan for plan year June 2025 to May 2026, docket 25-057-02, January 2026 (Commission order).
  2. Enbridge Gas Utah, Integrated Resource Plan for plan year June 2026 to May 2027, docket 26-057-02, filed June 2026 (utility filing, not yet acted on by the Commission).
  3. Enbridge Gas Utah, Integrated Resource Plan for plan year June 2025 to May 2026, docket 25-057-02, filed June 2025 (utility filing).
  4. Enbridge Gas Utah, Reply comments, docket 25-057-02, September 2025 (utility filing).
  5. Enbridge Gas Utah, Presentations to technical conferences, docket 25-057-02: April 2025 and July 2025; docket 26-057-02: May 2026 and July 2026 (utility presentations).
  6. Enbridge Gas Utah, Third quarter variance report, December 2024 through February 2025, docket 24-057-04, filed May 2025 (utility filing).
  7. Division of Public Utilities; Office of Consumer Services; Enbridge Gas Utah, Initial comments (September 2026) and reply comments (October 2026), docket 26-057-02 (party comments).
  8. Utah Public Service Commission, Order, application of Enbridge Gas Utah to increase distribution rates, docket 25-057-06, December 2025, and Order Altering, April 2026 (Commission order).
  9. Enbridge Gas Utah, Utah Natural Gas Tariff PSCU 800, compliance filing, docket 25-057-06, January 2026; Commission acknowledgment letter, February 2026 (effective tariff).
  10. Kern River Gas Transmission, Slides to the Utah Public Utilities, Energy, and Technology Interim Committee, June 2026 (pipeline statement).
  11. Kern River Gas Transmission; MountainWest Pipeline, Public informational postings and notices, accessed October 2026 (pipeline notices).
  12. Will-Power UT, LLC, Notice of Intent to the Utah Division of Air Quality, Eagle Mountain, Utah, February 2026 (applicant filing); the Commission's docket 26-2660-01, Exhibit E, Will-Power, UT LLC, Project Aquila Permits (file dated May 7, 2026); Davis County, Utah, Cities page (county government); U.S. Energy Information Administration, EIA-860M Preliminary Monthly Electric Generator Inventory, September 2026, and Federal Register notices of the Federal Energy Regulatory Commission searched by county.
  13. Will-Power UT, LLC (filing by Parsons Behle & Latimer) with the Utah Public Service Commission, Notice of Registration as a Large-Scale Generation Provider, dated November 24, 2025 (Docket 25-266-01). Link
  14. Williams Companies (for Will-Power UT) with the Utah Public Service Commission, Cover letter dated October 26, 2026 submitting the Declaration of Jacob Barker, Docket 26-2660-01 (docket entry October 27, 2026). Link
  15. Rocky Mountain Power (PacifiCorp) with the Utah Public Service Commission, Declaration of Jacob Barker on behalf of Rocky Mountain Power, Docket 26-2660-01 (October 2026). Link
  16. Utah Public Service Commission, Docket No. 26-2660-01, Application of Will-Power UT, LLC for Approval of a Closed Private Generation Contract (docket page). Link
  17. Utah Public Service Commission, Scheduling Order, Docket 26-057-02, issued July 9, 2026. Link
  18. Federal Register (FERC Combined Notice of Filings), Combined Notice of Filings, Federal Register document 2026-17475, published August 27, 2026 (Kern River RP26-1071). Link
  19. Federal Register (FERC Combined Notice of Filings), Combined Notice of Filings, Federal Register document 2026-18842, published September 15, 2026 (MountainWest RP26-1101-001 and RP26-1102-001). Link
  20. Federal Register (FERC Combined Notice of Filings), Combined Notice of Filings, Federal Register document 2026-15976, published August 6, 2026 (Ruby Pipeline RP26-1026-000). Link
  21. U.S. Energy Information Administration, EIA-860M Preliminary Monthly Electric Generator Inventory, September 2026, Retired and Operating sheets. Link
  22. NOAA Regional Climate Centers (ACIS web service), Monthly heating degree days base 65F and 1991-2020 normals, station USW00024127. Link
  23. Utah Public Service Commission, Gas dockets 2026 list (page). Link
  24. Federal Register (FERC notice), Magnum Gas Storage, LLC; Notice of Amendment Application and Establishing Intervention Deadline and Request for Extension of Time (FR 2025-07874, May 6, 2025). Link
  25. Federal Register (FERC notice), Magnum Gas Storage, LLC ; Notice of Scoping Period Requesting Comments on Environmental Issues for the Proposed 2025 Amendment Project (FR 2025-11482, June 23, 2025). Link
  26. Federal Register (FERC notice), Magnum Gas Storage, LLC; Notice of Schedule for the Preparation of an Environmental Assessment for the 2025 Amendment Project (FR 2025-12260, July 1, 2025). Link
  27. Federal Register (FERC notice), Mangum Gas Storage LLC; Notice of Availability of the Environmental Assessment for the Proposed 2025 Amendment Project (FR 2025-23948, December 30, 2025). Link

Figures are as reported in the sources above, as of October 2026. Requested amounts, approved amounts and customer charges are kept separate. - Will-Power UT, LLC (filing by Parsons Behle & Latimer) with the Utah Public Service Commission, Notice of Registration as a Large-Scale Generation Provider, dated November 24, 2025 (Docket 25-266-01). https://pscdocs.utah.gov/electric/25docs/25266001/342811NtcRgstrnLrgSclGnrtnPrvdr11-24-2025.pdf - Williams Companies (for Will-Power UT) with the Utah Public Service Commission, Cover letter dated October 26, 2026 submitting the Declaration of Jacob Barker, Docket 26-2660-01 (docket entry October 27, 2026). https://pscdocs.utah.gov/electric/26docs/26266001/347650CvrLtrDclrtnJacobBarkerRMP10-27-2026.pdf - Rocky Mountain Power (PacifiCorp) with the Utah Public Service Commission, Declaration of Jacob Barker on behalf of Rocky Mountain Power, Docket 26-2660-01 (October 2026). https://pscdocs.utah.gov/electric/26docs/26266001/347651DclrtnJacobBarkerRMP10-27-2026.pdf - Utah Public Service Commission, Docket No. 26-2660-01, Application of Will-Power UT, LLC for Approval of a Closed Private Generation Contract (docket page). https://psc.utah.gov/2026/04/02/docket-no-26-2660-01/ - Utah Public Service Commission, Scheduling Order, Docket 26-057-02, issued July 9, 2026. https://pscdocs.utah.gov/gas/26docs/2605702/3460702605702so7-9-2026.pdf - Federal Register (FERC Combined Notice of Filings), Combined Notice of Filings, Federal Register document 2026-17475, published August 27, 2026 (Kern River RP26-1071). https://www.federalregister.gov/documents/2026/08/27/2026-17475/combined-notice-of-filings - Federal Register (FERC Combined Notice of Filings), Combined Notice of Filings, Federal Register document 2026-18842, published September 15, 2026 (MountainWest RP26-1101-001 and RP26-1102-001). https://www.federalregister.gov/documents/2026/09/15/2026-18842/combined-notice-of-filings - Federal Register (FERC Combined Notice of Filings), Combined Notice of Filings, Federal Register document 2026-15976, published August 6, 2026 (Ruby Pipeline RP26-1026-000). https://www.federalregister.gov/documents/2026/08/06/2026-15976/combined-notice-of-filings - U.S. Energy Information Administration, EIA-860M Preliminary Monthly Electric Generator Inventory, September 2026, Retired and Operating sheets. https://www.eia.gov/electricity/data/eia860m/ - NOAA Regional Climate Centers (ACIS web service), Monthly heating degree days base 65F and 1991-2020 normals, station USW00024127. https://data.rcc-acis.org/StnData - Utah Public Service Commission, Gas dockets 2026 list (page). https://psc.utah.gov/gas/dockets/gas-2026/ - Federal Register (FERC notice), Magnum Gas Storage, LLC; Notice of Amendment Application and Establishing Intervention Deadline and Request for Extension of Time (FR 2025-07874, May 6, 2025). https://www.federalregister.gov/documents/2025/05/06/2025-07874/magnum-gas-storage-llc-notice-of-amendment-application-and-establishing-intervention-deadline-and - Federal Register (FERC notice), Magnum Gas Storage, LLC ; Notice of Scoping Period Requesting Comments on Environmental Issues for the Proposed 2025 Amendment Project (FR 2025-11482, June 23, 2025). https://www.federalregister.gov/documents/2025/06/23/2025-11482/magnum-gas-storage-llc-notice-of-scoping-period-requesting-comments-on-environmental-issues-for-the - Federal Register (FERC notice), Magnum Gas Storage, LLC; Notice of Schedule for the Preparation of an Environmental Assessment for the 2025 Amendment Project (FR 2025-12260, July 1, 2025). https://www.federalregister.gov/documents/2025/07/01/2025-12260/magnum-gas-storage-llc-notice-of-schedule-for-the-preparation-of-an-environmental-assessment-for-the - Federal Register (FERC notice), Mangum Gas Storage LLC; Notice of Availability of the Environmental Assessment for the Proposed 2025 Amendment Project (FR 2025-23948, December 30, 2025). https://www.federalregister.gov/documents/2025/12/30/2025-23948/mangum-gas-storage-llc-notice-of-availability-of-the-environmental-assessment-for-the-proposed-2025

Corrected November 9, 2026: an earlier version said no filing links any remedy to a specific new load and that no new load has a confirmed service date; the utility does link a possible Kern River gate station to west-side growth in general, and the fourth quarter of 2026 for the third signed agreement is the utility's expectation, not a confirmed service date.