Colorado natural gas case study, Denver, Colorado. November 2026
Denver-area natural gas capacity: Commission declined to certify the utility's supply project
Public Service says its Speer Canal Interconnects Project is needed for forecasted supply constraints and a 2027 supply closure. The Colorado Public Utilities Commission (PUC) declined to certify any component in a decision adopted April 15, effective June 4, 2026.
Metro used: the Denver-Aurora-Centennial, CO metropolitan statistical area, as delineated in OMB Bulletin No. 23-01 (July 21, 2023). The principal gas distribution utility in the record is Public Service Company of Colorado (Public Service), which does business as Xcel Energy. Its 2025-2030 Gas Infrastructure Plan covers the whole company, so project figures below are labeled by their geography.1
Key takeaways
- Public Service describes the project as five interrelated projects tied to the anticipated closure of Supply Point A in the 2027 timeframe.4
- The decision, adopted April 15, 2026 and effective June 4, 2026, says Public Service must provide additional data to document and justify the need before a certificate is granted.4
- Public Service's table shows the project needed in 2026 under its Base forecast, and it said the project is required under all forecast scenarios.3
- Public Service said Supply Point A gas on numerous occasions did not meet quality specifications and was not accepted into the Northern Gas System; the decision gives no dates.4
- Public Service adds no reserve margin to its capacity planning and gives no design-day demand against capacity for Denver, so the coldest-day margin is not shown.2
- Part of the project's cost, an electric generation component, would be covered by Public Service's electric operations.5
What is the outlook for Denver gas capacity through 2029?
Discovery Energy rates the outlook for Denver-area natural gas capacity through 2029 as Elevated (confidence: Medium): Public Service says its Speer Canal Interconnects Project is needed to address forecasted supply constraints and the anticipated closure of Supply Point A in 2027.4 In a decision adopted April 15 and effective June 4, 2026, the Colorado PUC declined a certificate for every component and named a path forward through an updated application.4 The record we reviewed shows no refiled application, so the need has no approved fix; the records are for Public Service's Denver and Northern Gas Systems, not the metro alone.3 Documented risk factors: none found in the record we reviewed beyond the unresolved supply need itself. Three developments would change the assessment: Public Service's updated application for the Speer Canal Interconnects Project and the Commission's decision on it; any notice giving the date or volume of the closure of Supply Point A; Public Service's next Gas Infrastructure Plan with its Design Day method updated as the Commission directed.
Outlook levels, from least to most concern: Stable, Watch, Elevated, High, Severe. Levels describe the public record of capacity and supply risk; confidence is reported separately. They are qualitative assessments, not forecasts of outages.
Who serves the Denver area?
Public Service, which does business as Xcel Energy, is the principal gas distribution utility named in the record. Atmos Energy, Black Hills Energy and Colorado Natural Gas also serve parts of Colorado, and which of them serve parts of the ten counties is not shown.1
Public Service said its Denver, Northern Colorado, Mountain, Pueblo and Western gas systems are physically interconnected but each operates as an independent system on Design Day, the coldest day its system is planned to serve.1 The table below places each project it names by geography; the Aurora non-pipeline alternative serves about 1,600 customers.3
| Where | Item in the record |
|---|---|
| Inside the metro | Speer Canal Interconnects (Greater Denver Area; Denver and Northern Gas Systems), F-715 (Centennial), F-866 (Thornton), F-3 and its non-pipeline alternative (Aurora) |
| Outside the metro, whole-system record | Ute Highway reinforcement (Longmont, Boulder County); Louisville to Rollins Pass; the Mountain Energy Project |
| Unclear | Atmos Energy, Black Hills Energy and Colorado Natural Gas service in Douglas, Elbert, Park, Clear Creek and Gilpin counties; the Eastern Mountain Gas System, whose towns the record we reviewed does not name |
Items in Public Service's 2025-2030 Gas Infrastructure Plan and the Commission's decision, by whether they fall inside the Denver metro (OMB delineation). Source: Attachment JJP-1, Table 22; Decision No. C26-0371.1
The Northern Gas System also serves places outside the ten counties. The plan does not name the towns the Eastern Mountain Gas System serves, so whether they lie inside the ten counties is not shown. The plan does not allocate system figures to either system, so those figures cover the whole system, not the metro alone. Pipelines outside the ten counties still feed Public Service's system, and the Speer Canal project adds interconnections with two of them.4
How much spare gas capacity does Denver have on the coldest day?
In words: what the map shows
- Pipelines labeled: Colorado Interstate Gas (also labeled CIG).
- Compressor stations marked: Watkins.
- Metro counties outlined (10): Adams County; Arapahoe County; Broomfield County; Clear Creek County; Denver County; Douglas County; Elbert County; Gilpin County; Jefferson County; Park County.
- Cities and towns labeled include: Denver; Colorado Springs; Lakewood; Thornton; Arvada; Greeley; Pueblo; Centennial.
- Other gas pipelines in the area are drawn in gray and are not labeled.
- Highways are drawn for orientation. A small state locator map sits in a corner.
Public Service's table of Design Day temperatures by weather zone gives its Denver zone -25 degrees F and its Mountain zone -39 degrees F, set at a 1-in-30-year level from historical minimum daily temperatures.2 Public Service said a 1-in-25-year method with data from 2001 through 2025 gives -24 degrees F and would not change the project's need; the Commission directed it to update its Design Day method with weather data from 2000 to present, a 1-in-25-year probability, a new peak hour estimate and a diversity factor for regional temperature differences.4
Public Service said its capacity modeling adds no reserve margin of capacity on a pipe by pipe or regional basis. The plan's text gives no design-day demand compared with capacity for the Denver system or for the ten counties, so we have no margin for the coldest day and have not estimated one.2
What is driving new natural gas demand?
We found no documented data center gas load in the ten metro counties, and the only planned load tied to Public Service's system with a stated size is the Company-owned turbine project described below.18
The decision describes the Speer Canal project as driven in part by the anticipated loss of a major gas supplier into the Northern Gas System, forecasted peak hour load growth in the Northern and Denver Gas Systems, and the need to supply planned gas-fired generation. It says the project would support 400 MW of new Company-owned gas combustion turbines approved in decisions C24-0052 and C25-0024, with no location or service date, so they are not a documented load with a service date.5
EIA's September 2026 generator inventory lists no planned natural gas-fired generator in the ten metro counties.7 Two earlier Federal Energy Regulatory Commission notices, from December 2025 and July 2026, name Adams, Arapahoe or Elbert County for the Rockies Express project to Colorado Springs Utilities, and none ties it to a gas load or to Public Service's system.19 EIA lists a planned December 2028 retirement of Public Service's Cherokee unit 4 in Adams County, a 380.8 MW gas steam turbine that is an electric generator.9
Data centers: As of October 29, 2026, we found no data center gas load in the ten counties. State air permit records for two metro data centers cover diesel engines, not gas equipment: nineteen diesel-fired emergency engines proposed for EdgeConneX in Douglas County in January 2026, and fourteen diesel-fueled engines permitted for CoreSite in Denver County in July 2025.8
Crossing the metro: Rockies Express Pipeline's proposed lateral to Colorado Springs would run through Adams, Arapahoe and Elbert counties, three metro counties, but it would serve Colorado Springs Utilities, and no record we reviewed ties it to Public Service's system.11
Are upgrades arriving in time?
The project's two new supply interconnections are with Tallgrass and with CIG High Plains, and it also relocates the CIG First Creek Meter Station (the decision uses the abbreviation CIG).4 Public Service's table gives spending of $1.0 million in 2025, $19.3 million in 2026 and $22.4 million in 2027.3 Public Service said construction was expected to begin in August 2026 for an estimated in-service date of May 2027, in time for the 2027-2028 heating season.4
The Commission declined a certificate for any component, citing concerns about Public Service's forecasting, support for electric generation infrastructure whose cost the electric system partly bears, and vague details on the ongoing unavailability of Supply Point A. It said the joint stipulation's approach, an updated application under a revised CHP-Aligned forecast, could provide a path forward. The record we reviewed shows no refiled application or new decision, so the project is neither approved nor scheduled in the sense of Discovery Energy's outlook scale.4
Public Service's plan also lists a non-pipeline alternative for about 1,600 customers in Aurora, its desired plan to avoid the planned F-3 reinforcement, and said the constraint behind that project remains fundamentally the same.3 A separate certificate for the Mountain Energy Project, LNG and CNG installations for the Eastern Mountain Gas System, was granted in Decision No. C25-0840 and covers mountain towns that are not part of the metro.4
What does this mean for business gas costs?
The Commission declined to approve the plan in its entirety, and it declined a presumption of prudence for the Louisville to Rollins Pass cost estimate, leaving its prudency to a future rate case. According to the company, a $9.7 million electric generation component would be covered by Public Service's electric operations as a transportation demand charge. The record we reviewed gives no allocation of project costs among gas customer classes, and this page states no bill impact.4
Who gets gas first in a shortage?
Public Service said interruptible customers use available capacity, if it exists, that firm customers are not using at a specific time, and that it does not use interruptible customers' estimated peak hour load to set the capacity needed on Design Day. This page does not cover the tariff's interruption sequence.3
Winter and market context
Colorado Interstate Gas (CIG) posted a force majeure notice on February 12, 2026 for repairs on its 2B Line east of the Watkins compressor station in Adams County, with a pressure restriction on its Watkins East segment, and lifted it on February 27, 2026 after repairs.10 CIG's own posting site and any CIG posting after July 10, 2026 are not covered here, nor are other pipelines' postings.
Winter weather and NOAA's outlook
Heating degree days, a measure of how much heating the weather called for, ran below the 1991-2020 normal at the Denver International Airport station in each of the last three winters, and 2025-26 was the mildest of the three.14 NOAA's Climate Prediction Center outlook issued October 15, 2026 gives the Denver area equal chances of above-normal, near-normal and below-normal temperatures for November 2026 to January 2027 and for December 2026 to February 2027.15 The airport is one station standing for the metro, and NOAA's figures are probabilities for a three-month average, not a forecast of days.16
| Winter (November to March) | Heating degree days | 1991-2020 normal | Difference from normal |
|---|---|---|---|
| 2023-24 | 4131 | 4479 | -7.8% |
| 2024-25 | 4315 | 4479 | -3.7% |
| 2025-26 | 3271 | 4479 | -27.0% |
Heating degree days at the Denver International Airport station, base 65 degrees F, against the 1991-2020 normal. Source: NOAA Regional Climate Centers.
What's new (as of October 29, 2026)
On October 8, 2026, FERC staff issued an environmental assessment of the Rockies Express Pipeline project that would bring gas to Colorado Springs Utilities, and the record does not tie it to Public Service's system.11 On August 13, 2026, CIG asked FERC to move the filing date of its next system-wide rate case from September 30 to December 31, 2026; the petition concerns rates, and the filings we reviewed do not include FERC's decision.12 Xcel's filings page lists no new filing on the Speer Canal project after the June 2026 decision.13
What should Denver-area facilities check now?
- Tariffs and charges, through a utility audit. Confirm each account is on the right rate class and tariff, and that riders, demand charges and capacity-related charges are billed correctly. Over 70% of the clients Discovery Energy has audited were billed incorrectly. An audit verifies tariffs and charges and recovers overcharges before winter costs rise.
- Which service. Confirm whether each site takes firm or interruptible service from Public Service; the plan says interruptible customers use capacity that firm customers are not using at that time.
- Backup plans and fuel. Check that alternate-fuel and curtailment plans are current and feasible, and that fuel inventories and resupply arrangements are in place before December.
- Upcoming proceedings. Track the Speer Canal Interconnects Project and Public Service's next Gas Infrastructure Plan, especially for sites in the Front Range corridor north of Denver.
What to check in your contracts
| Area | What to check |
|---|---|
| Winter price spikes | Whether the gas is priced on a daily or a monthly index, how large the local basis (the gap between the local price and the national benchmark) has been in cold weather, and how much of your winter use is covered by fixed-price volumes. |
| Delivery constraints | Whether your transportation is firm, what delivery obligations your supplier carries and what happens if it cannot deliver, and what the curtailment provisions say about who is cut first. |
| Operational flow orders | What balancing obligations the contract places on you, and whether penalties that a pipeline or utility charges under an operational flow order are passed through to you. |
| Expansion plans | Where a utility or pipeline plans added capacity, whether the utility has confirmed in writing the incremental hourly and daily capacity available to your site, and from what date. |
Checks for gas supply and transportation contracts. They are questions to put to your supplier or utility, not financial advice.
Frequently asked questions
Will Denver businesses face natural gas shortages this winter?
The record does not show a shortage, and this page makes no prediction about outages. See 'Are upgrades arriving in time?' for the Speer Canal Interconnects Project and the Commission's decision on it.
Is there spare gas capacity in the Denver area on the coldest day?
Public Service said its modeling adds no reserve margin, and its plan text gives no design-day demand against capacity for the Denver system, so the margin is not shown. See 'How much spare gas capacity does Denver have on the coldest day?'
Did the Colorado PUC approve Public Service's gas infrastructure plan?
No. It declined to approve the plan in its entirety and declined a certificate for all Speer Canal components, naming a path forward through an updated application. See 'Are upgrades arriving in time?'
Is new gas-fired generation driving demand in the Denver area?
The decision says the project would support 400 MW of new Company-owned turbines, with no location or service date; we found no data center gas load. See 'What is driving new natural gas demand?'
Who is cut first if Public Service must curtail service?
Public Service said interruptible customers use capacity that firm customers are not using at the time, and it does not size Design Day capacity on their load. This page does not cover the tariff's interruption sequence. See 'Who gets gas first in a shortage?'
Related case studies
Discovery Energy publishes gas capacity case studies for other metros, using the same method and outlook scale.
- Seattle natural gas capacity case study (outlook: Elevated)
- Las Vegas natural gas capacity case study (outlook: Elevated)
- Portland area natural gas capacity case study (outlook: Elevated)
- Northern California natural gas capacity case study (outlook: Elevated)
All gas capacity ratings by U.S. metro
Background for commercial and industrial energy buyers: Utility cost intelligence
Understand your capacity exposure
Discovery Energy reviews service elections, interruption terms and regulatory proceedings for organizations across the U.S. and Canada, so capacity changes are understood before they reach the bill.
Schedule a reviewWhat this page does not cover
- When the Supply Point A gas-quality problems happened. The Commission's decision gives no dates.
- Which supply point Supply Point A is, how much gas it carries, and when it will close. The public record does not give these.
- How Denver's design-day demand compares with pipeline capacity. Project packets with design-day detail were filed under seal.
- Public Service's order of interruption in a shortage, and how costs are split among customer classes. The public record we reviewed does not give either.
Notes
- Public Service Company of Colorado, Attachment JJP-1, 2025-2030 Gas Infrastructure Plan (May 23, 2025; Colorado PUC Proceeding No. 25A-0220G), PDF 15, PDF 16, PDF 93 (Table 22) and PDF 104. Utility statements. The ten metro counties are Adams, Arapahoe, Broomfield, Clear Creek, Denver, Douglas, Elbert, Gilpin, Jefferson and Park, from the OMB Bulletin No. 23-01 delineation (July 21, 2023). The match of towns to counties is general geography, not a quotation. The plan names projects in Greater Denver, Centennial, Thornton and Aurora; these are the most local figures the record has. Atmos Energy, Black Hills Energy and Colorado Natural Gas also serve parts of Colorado; which of them serve parts of the ten counties is not shown. ↩
- Same plan, PDF 95 (capacity planning, no added reserve margin), PDF 99 (Table 24) and PDF 100 (Design Day method). Utility statements. ↩
- Same plan, PDF 93 (Table 22), PDF 95 (footnote 58), PDF 104 and PDF 112 (Table 27). The table also places the F-715 reinforcement at Centennial (Arapahoe County), the F-866 reinforcement at Thornton (Adams County), the Ute Highway reinforcement at Longmont (Boulder County) and the F-3 project at Aurora. The Speer Canal share of the capacity expansion total is our calculation (illustrative): 42.7 divided by 127.5 is 33.5%, a share of dollars, not of capacity. ↩
- Colorado Public Utilities Commission, Decision No. C26-0371 granting in part and denying in part the application, Proceeding No. 25A-0220G (adopted April 15, 2026; issued and effective June 4, 2026), PDF 1, 6, 14, 18, 19, 56, 58 to 62, 92. Commission decision; statements of Public Service within it are utility statements, reported as such. ↩
- Decision No. C26-0371, PDF 59 and PDF 60 (the 400 MW of Company-owned gas combustion turbines, approved in decisions C24-0052 and C25-0024, which were not read). ↩
- Atmos Energy, Black Hills Energy and Colorado Natural Gas service in the outer counties: not shown.
- EIA-860M inventory for September 2026 (Planned sheet, operator-reported planned dates), filtered to the ten metro counties by us, and a Federal Register search of FERC notices since January 1, 2025 by county phrase, both our own calculation. Our first search used the singular form (for example "Arapahoe County") and missed notices that name counties in the plural; a second search of the plural forms found the notices in note 19. A notice that spells a place differently would still be missed. The Federal Register search covered notices since January 1, 2025; the October 2026 notice is in note 11. ↩
- Colorado Department of Public Health and Environment, Air Pollution Control Division: Notice of a Proposed Construction Permit Warranting Public Comment for EdgeConneX, Inc., Denver Campus, Douglas County, notice period beginning January 6, 2026 (draft permit 25DG0038), page 1, which says the applicant proposes a second building and nineteen new diesel-fired emergency engines; and Construction Permit 24DE0836 (Issuance 1), issued July 17, 2025, page 1, for CoreSite DE3 at 4900 North Race Street, Denver County, fourteen diesel-fueled internal combustion engines. Both are outside the past 90 days, and neither names a gas load. ↩
- U.S. Energy Information Administration, EIA-860M Preliminary Monthly Electric Generator Inventory, September 2026, Operating sheet, row 818 (Cherokee, Adams County, Public Service Co of Colorado, unit 4, natural gas steam turbine, 380.8 MW, in service December 1968, planned retirement December 2028). The retirement concerns an electric generator, not a gas delivery facility. ↩
- Colorado Interstate Gas Company, L.L.C., informational postings (Critical Notices on the pipeline's own informational postings site, pipeline2.kindermorgan.com, accessed October 29, 2026; we paraphrase them): Notice 122897, Force Majeure Segment 260 Watkins East, posted February 12, 2026, which said the repairs would reduce capacity on the segment to 204,000 Dekatherms (Dth) per day in one direction and 214,000 in the other; Notice 122933, posted February 27, 2026, which lifted the force majeure and restored capacity to 398,000 Dth per day in one direction and 365,000 in the other from gas day February 28; and Notice 122917, the February 2026 Operations Planning Report, which places Segment 260 in Adams County. A dekatherm is a unit of gas energy. ↩
- Federal Register, FERC notice, document 2026-20581, published October 8, 2026, pages 64360 to 64362 (docket CP25-539-000 and CP25-539-001): Rockies Express Pipeline LLC, Cheyenne Connector, LLC and East Cheyenne Gas Storage, LLC, Notice of Availability of the Environmental Assessment for the Critical Energy Reliability Link Project, page 64361. It describes up to 100,000 Dth per day of firm transportation and 50,000 Dth per day of no-notice service to Colorado Springs Utilities, 153.8 miles of new 24-inch lateral in Weld, Adams, Arapahoe, Elbert and El Paso counties, and comments due November 2, 2026. Adams, Arapahoe and Elbert are metro counties. ↩
- Colorado Interstate Gas Company, L.L.C., Petition to Amend Stipulation and Agreement, FERC Docket No. RP22-825, dated August 13, 2026, page 1 (the amendment would give the parties time for settlement talks on its system-wide rate case); Federal Register, FERC Combined Notice of Filings, document 2026-16978, published August 20, 2026, page 53853 (docket RP22-825-003). CIG asked FERC to approve the petition by September 14, 2026; we did not see an order. ↩
- Xcel Energy, gas infrastructure filings web page, read October 29, 2026 (not saved); the Commission's own page, puc.colorado.gov/gas-infrastructure-plans, returned an error to our download, so we could not read the docket's filing list and the docket may hold later filings. ↩
- NOAA Regional Climate Centers, Applied Climate Information System (ACIS) StnData web service, monthly heating degree days (base 65 degrees F) and 1991-2020 normals, November to March of winters 2023-24 to 2025-26, accessed October 29, 2026: Denver International Airport (station USW00003017). Sums are our calculation. Heating degree days behind the percentages: 4131 in 2023-24, 4315 in 2024-25 and 3271 in 2025-26, against a 1991-2020 normal of 4479. ↩
- NOAA Climate Prediction Center, seasonal temperature outlook issued October 15, 2026 (shapefiles from ftp.cpc.ncep.noaa.gov/GIS/us_tempprcpfcst/seastemp_202610.zip), read at the Denver location. The map shows equal chances for both periods: about 33.3% above-normal, 33.3% near-normal and 33.3% below-normal. ↩
- The station is Denver International Airport; one airport station is not a measurement of the whole metro. The outlook figures are NOAA's probabilities for a three-month average and do not rule out cold days. ↩
- NOAA's Climate Prediction Center said on October 15, 2026 that its November 2026 to January 2027 temperature outlook favors above-normal temperatures for, among other areas, the western third of the contiguous United States, a discussion that names regions and not counties, and that the probability of at least a strong El Nino continuing through January to March 2027 is 80% (source B1). EIA said on October 6, 2026 that it expects U.S. natural gas inventories to enter the winter heating season 2% above the previous five-year average, and that prolonged periods of cold weather could increase withdrawals beyond its forecast (sources A1 and A2). EIA lists U.S. liquefied natural gas gross exports of 15 billion cubic feet per day in 2025, 18 in 2026 and 19 in 2027. These are national and regional facts, not statements about Public Service's system.
- No gas-fired generation, fuel cell, pipeline lateral, special contract or large-load filing for a data center in the ten counties was found. News reports of data center moratoria in Denver and Jefferson County and of a planned data center in Adams County are leads only and are not cited. ↩
- Federal Register, Federal Energy Regulatory Commission, two earlier notices on the Critical Energy Reliability Link Project of Rockies Express Pipeline LLC, Cheyenne Connector, LLC and East Cheyenne Gas Storage, LLC (dockets CP25-539-000 and CP25-539-001). (a) Notice of Schedule for the Preparation of an Environmental Assessment, document 2025-22942, published December 16, 2025, pages 58238 and 58239: the project would provide up to 100,000 Dth per day of firm transportation and 50,000 Dth per day of no-notice service to Colorado Springs Utilities; Rockies Express "proposes to construct and operate in Weld, Adams, Arapahoe, Elbert, and El Paso counties, Colorado" about 160 miles of 24-inch pipeline; the schedule gave July 2, 2026 for the environmental assessment, which the October 2026 notice in note 11 shows issued later. (b) Notice of Onsite Environmental Review, document 2026-14079, published July 13, 2026, pages 42958 and 42959: staff visit on July 17, 2026 to areas around West Bijou Creek in Elbert County, Colorado, to look at the route and alternatives in response to concerns raised by Colorado Parks and Wildlife. Adams, Arapahoe and Elbert are metro counties. Neither notice names Public Service or a gas load, and we did not read the filings themselves. ↩
Market and weather sources
Public web sources, as of October 25, 2026. They are context, separate from the regulatory record cited in the Notes. The Climate Prediction Center issues its seasonal outlook once each month near mid-month; this section is refreshed on the publication date.
- A1. U.S. Energy Information Administration, press release, "EIA expects a mixed picture for winter fuel costs this year," October 6, 2026. Link
- A2. U.S. Energy Information Administration, Short-Term Energy Outlook, October 2026 (natural gas storage). Link
- B1. NOAA Climate Prediction Center, Prognostic Discussion for Long-Lead Seasonal Outlooks, issued October 15, 2026. Link
Sources
- Public Service Company of Colorado (Xcel Energy), Attachment JJP-1, 2025-2030 Gas Infrastructure Plan, Proceeding No. 25A-0220G. Link
- Colorado Public Utilities Commission, Decision No. C26-0371, Proceeding No. 25A-0220G. Link
- Office of Management and Budget, OMB Bulletin No. 23-01, Revised Delineations of Metropolitan Statistical Areas, Micropolitan Statistical Areas, and Combined Statistical Areas, July 21, 2023.
- U.S. Energy Information Administration, EIA-860M Preliminary Monthly Electric Generator Inventory, September 2026. Link
- Federal Register, API search of Federal Energy Regulatory Commission notices by county. Link
- Federal Register (FERC notice), Rockies Express Pipeline LLC et al.; Notice of Availability of the Environmental Assessment for the Proposed Critical Energy Reliability Link Project, document 2026-20581, October 8, 2026. Link
- Colorado Interstate Gas Company, L.L.C. (filed at FERC by counsel), Petition to Amend Stipulation and Agreement, Docket No. RP22-825, August 13, 2026. Link
- Federal Register (FERC Combined Notice of Filings), Combined Notice of Filings, document 2026-16978, August 20, 2026 (CIG docket RP22-825-003). Link
- Colorado Interstate Gas Company, L.L.C. (own informational postings), CIG Notice 122897, Force Majeure Segment 260 Watkins East, posted February 12, 2026. Link
- Colorado Interstate Gas Company, L.L.C. (own informational postings), CIG Notice 122933, Cancellation FMJ Seg 260 Watkins, posted February 27, 2026. Link
- Colorado Department of Public Health and Environment, Air Pollution Control Division, Notice of a Proposed Construction Permit Warranting Public Comment, EdgeConneX Denver Campus, Douglas County, notice period beginning January 6, 2026. Link
- Colorado Department of Public Health and Environment, Air Pollution Control Division, Construction Permit 24DE0836 (Issuance 1), CoreSite DE3, Denver County, issued 7/17/2025. Link
- NOAA Regional Climate Centers (ACIS web service), Monthly heating degree days base 65F and 1991-2020 normals, station USW00003017. Link
- Federal Energy Regulatory Commission (Federal Register), Federal Register document 2025-22942, 2025-12-16. Link
- Federal Energy Regulatory Commission (Federal Register), Federal Register document 2026-14079, 2026-07-13. Link
- Colorado Interstate Gas Company, L.L.C. (own informational postings), CIG Notice 122917, Operations Planning Report February 2026 (reissued February 18, 2026). Link
Corrected November 9, 2026: The Eastern Mountain Gas System was listed as outside the metro; it is now listed as unclear, because the record we reviewed does not name its towns. The decision was also described as made in April 2026 in one place and June 2026 in another; it was adopted April 15 and became effective June 4, 2026.