Discovery Energy · Data Center Tracking Index

How the Data Center Tracking Index is built

How we size each campus, weight it by build stage, turn its load into grid and gas demand, rate it, and estimate what it adds to large energy users’ bills.

Preview edition (Pass 1), October 28, 2026.

What the index covers

Data center campuses of 100 MW or more in the United States and Canada that entered service since 2021, or are under construction, approved, announced or proposed. Crypto-mining sites converting to AI and high-performance computing are included because their grid load behaves the same way. The preview edition lists 84 campuses, most of them gigawatt-scale. The tier between 100 MW and 1 GW is added region by region.

From announcement to expected load

  1. Normalize the size

    Published megawatts mean different things: IT load, facility load, utility service, on-site generation nameplate or campus potential. Each is converted to facility load. IT load is multiplied by a PUE of 1.2; on-site generation nameplate by 0.8, because plants are built with spare units.

  2. Phase it to 2030

    Campuses up to 1 GW count in full. Campuses of 1 to 3 GW count at 60%, and larger programs at 30%, for the share realistically energized by 2030.

  3. Weight it by build stage

    Announced load is not built load. Each status carries a probability, calibrated to observed attrition: PJM accepted about 34 of roughly 60 GW of utility-submitted 2030 data center load; Bernstein rates about 35% of the pipeline credible; Sightline finds 30% to 50% of 2026 projects delayed or cancelled; and AEP Ohio’s large-load queue fell from about 30 GW to 13 GW once its tariff required commitments.

  4. Turn load into energy

    Expected load runs at a 75% average load factor, reflecting how evenly data centers draw power. Annual energy is that average load across 8,760 hours.

  5. Split grid from on-site power

    Grid-served load affects electric rates. On-site load bypasses the grid but burns gas locally. Hybrid campuses are split by the size of their on-site plant.

Build-stage probabilities
StatusProbabilityMeaning
Operating100%In service, no further phases announced
Operating, expanding90%Partly energized; later phases under construction
Under construction80%Site work underway
Approved65%Utility agreement, grid allocation or zoning approval in hand
Announced35%Named developer and site, no construction
Proposed15%Developer only, no named tenant, power plan unresolved

Natural gas demand

Gas burn equals average load times 24 hours times the heat rate, divided by the heat content of gas (1,036 Btu per cubic foot). On-site turbines and engines use 9,500 Btu/kWh and on-site fuel cells 7,000. Grid-served load uses 7,500 Btu/kWh, the combined-cycle range in EIA data, applied to each region’s share of new supply from gas: from none in Québec to 90% in Alberta and 60% in PJM. Campuses served by plants built for them, such as Meta’s Hyperion campus in Louisiana, count at 100% gas. Peak-day figures in Dth/d use a 95% load factor, because pipeline limits bind on the coldest days. As a check, 1 GW running flat on gas at 6,000 Btu/kWh comes to about 139 MMcf/d, in line with Enverus’s estimate of 140.

Electric bill effects

Where a market monitor puts a number on the data center share of capacity cost, we use it. In PJM, the 2028/29 auction cleared at $325 per MW-day and the independent market monitor attributes 38% of its cost to data center load. For a large user that is $325 × 365 × 38% = about $45,078 per MW of peak load contribution per year, or about $7.35 per MWh at a 70% load factor. As a cross-check, the monitor puts the data center capacity effect at $11.11 per MWh of total wholesale cost in the first half of 2026.

Energy-only markets (ERCOT, Alberta) and vertically integrated utilities are calibrated region by region from resource plans, rate cases, transmission plans and large-load tariff terms. Until then the index shows expected load and tariff protection, not a dollar figure. Large-load tariffs are rated Strong, Partial or Under review for how much data center cost they keep off other customers’ bills.

Impact rating

Each campus gets a grid score from its grid-served load by 2030 (under 150, 150 to 400, 400 to 800, 800 MW or more) and a gas score from its peak-day draw (under 25,000, 25,000 to 60,000, 60,000 to 120,000, 120,000 Dth/d or more). Regional grid gas counts at half weight. The rating is the higher of the two. Read the full impact rating explanation.

Calibration checks

Preview totals against independent forecasts
MeasureIndexBenchmarkBenchmark source
Expected data center load by 2030, all campuses52.9 GW62 GW new, 2026–2030Enverus, July 2026 (Lower 48)
PJM expected load by 203016.0 GW35.1 GW, 2026–2031PJM 2026 load forecast (accepted large loads)
Added gas burn by 20304.8 Bcf/d3 to 10 Bcf/dAnalyst range (S&P Global, PwC and others)

The preview sits inside these ranges while still missing the 100 MW to 1 GW tier. As that tier is added, totals are checked again and build-stage probabilities tightened if the index runs hot.

Limits of this edition

  • Most rows come from secondary trackers that often disagree with each other. Conflicts are noted in the dataset and graded D until resolved.
  • Coverage is weighted to gigawatt-scale projects; smaller campuses, especially in Northern Virginia, Dallas, Phoenix, Atlanta, Columbus and Chicago, are not yet complete.
  • Bill-cost figures are published for PJM only. Other regions follow as they are calibrated.
  • Canadian coverage is limited to Alberta. Québec and Ontario are added in a later pass.

Sources

Change log

October 28, 2026. Preview edition (Pass 1): 84 campuses, impact ratings, PJM bill-cost estimate.

Download the dataset (CSV)

Find out what your bills should have cost.

Send one recent bill per site, or a list of accounts. We tell you where we expect findings before you sign anything. No upfront audit fee.